IR 05000346/2016007, March 28, 2016, Davis-Besse; Request for Information for an NRC Post-Approval Site Inspection for License Renewal
ML15355A196
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/18/2015
From: Christine Lipa
NRC/RGN-III/DRS/EB2
To: Boles B
FirstEnergy Nuclear Operating Co
References
IR 2016007
Download: ML15355A196 (5)


See also: IR 05000346/2016007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

December 18, 2015

Mr. Brian D. Boles

Site Vice President

FirstEnergy Nuclear Operating Co.

Davis-Besse Nuclear Power Station

5501 N. State Rte. 2, Mail Stop A-DB-3080

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION; REQUEST FOR INFORMATION

FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL;

INSPECTION REPORT 05000346/2016007

Dear Mr. Boles:

On March 28, 2016, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-Approval

Site Inspection for License Renewal at your Davis-Besse Nuclear Power Station. This

inspection will be performed in accordance with NRC Inspection Procedure (IP) 71003. This

inspection will focus on outage related activities to verify license conditions added as part of

your renewed license and a sample of license renewal commitments have been implemented.

In order to minimize the inspection impact on the site and to ensure a productive inspection for

both parties, we have enclosed a request for information needed for the inspection. It is

important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into two groups:

  • The first group lists information necessary for our initial inspection scoping and in-office

preparation activities. During the in-office preparation activities, the team will identify as

much as possible the information and activities to be reviewed during the inspection.

This information should be provided to the lead inspector by March 4, 2016.

  • The second group includes the additional information required for the team to review

the selected activities. This information should be available to the team on-site on

March 28, 2016. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the lead inspector as the documents are

generated.

The lead inspector for this inspection is Dr. Stuart Sheldon. We understand that our primary

contact for this inspection is Mr. Gerald Wolf, of your organization. If there are any questions

about the inspection or the material requested in the enclosure, please contact the lead

inspector at (630) 829-9727, or via e-mail at Stuart.Sheldon@nrc.gov.

B. Boles -2-

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Christine A. Lipa, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-346

License No. NPF-3

Enclosure:

Document Request for Post-Approval

Site Inspection for License Renewal

cc: Distribution via LISTSERV

DOCUMENT REQUEST FOR POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL

Inspection Report: 05000346/2016007

Inspection Dates: March 28, 2016 - April 8, 2016

Inspection Procedure: IP 71003 Post-Approval Site Inspection for License Renewal

Lead Inspector: Dr. Stuart Sheldon

(630) 829-9727

Stuart.Sheldon@nrc.gov

I. Information Requested Prior to the On-Site Inspection Week

The following information is requested by March 4, 2016, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. (Please provide the information electronically in

.pdf files, Excel, or other searchable formats, preferably on some portable electronic

media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain

descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information

in lists should contain enough information to be easily understood by someone who

has knowledge of light water reactor technology).

1. Provide a list of your license renewal commitments with an approximate

completion status of each.

2. Provide a list of your Aging Management Programs (AMPs), copies of the

program basis documents for each, and a listing of the action tracking items

for each.

3. For AMPs that are one-time inspection programs, provide a list of completed

work order numbers for inspections that have been completed. This may be

incorporated with the previous item and should include identification of the

inspected component.

4. Provide a list of the one-time inspections credited for license renewal that will

be completed during your outage. This list should include at least the system,

component, work order number, and type of inspection.

5. Provide a list of other planned inspections, which will be conducted during the

outage, that are credited for license renewal. Of particular interest are those that

provide observations of areas that are generally inaccessible at power, e.g., tank

internal inspections, drywell liner inspections and containment coating

inspections. Include work order numbers where applicable.

6. Provide an outage schedule, sufficiently detailed as to list the work orders noted

in Items 4 and 5.

Enclosure

DOCUMENT REQUEST FOR POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL

7. Provide current management and license renewal organizational charts.

8. Provide electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements Manual.

9. Provide copies of any internal/external self-assessments and associated

corrective action documents generated in preparation for the inspection.

II. Information Requested to be Available When the Inspectors Arrive On-Site on

March 28, 2016

1. Copies of the work orders requested during the preparation week. This will

include work orders of inspections to be observed and completed work orders

to be reviewed by the team.

2. Contact information for the Outage Control Center to facilitate inspector

observation of the selected work orders.

3. Documentation demonstrating completion of license renewal commitments which

are complete as of the inspection date. For example, this may be in the form of a

binder for each commitment which includes the implementing documentation and

references.

III. Information Requested to be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection

to each team member).

If you have questions regarding the information requested, please contact the lead inspector.

2

B. Boles -2-

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Christine A. Lipa, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-346

License No. NPF-3

Enclosure:

Document Request for Post-Approval

Site Inspection for License Renewal

cc: Distribution via LISTSERV

DISTRIBUTION:

Janelle Jessie

RidsNrrDorlLpl3-2 Resource

RidsNrrPMDavisBesse Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Jim Clay

Carmen Olteanu

ROPreports.Resource@nrc.gov

ADAMS Accession Number ML15355A196

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII N RIII RIII RIII

NAME SSheldon:jw CLipa

DATE 12/16/15 12/18/15

OFFICIAL RECORD COPY