GO2-15-171, Request for Extension to Respond to the November 12, 2015 NRC Integrated Inspection Report (EA-15-202)
| ML15345A218 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 12/11/2015 |
| From: | Hettel W Energy Northwest |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| EA-15-202, GO2-15-171 | |
| Download: ML15345A218 (1) | |
Text
.
- w. Grover Hettel EIJER V
Columbia Generating Station NORIHAIEST Ph.
wghettel@ energy-northwest.com U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397; REQUEST FOR EXTENSION TO RESPOND TO THE NOVEMBER 12, 2015 NRC INTEGRATED INSPECTION REPORT tEA-i 5-202)
Reference:
Letter dated November 1 2, 201 5, 1W Pruett (NRC) to ME Reddemann (Energy Northwest), Columbia Generating Station NRC Integrated Inspection Report 05000397/201 5003 and Exercise of Enforcement Discretion
Dear Sir or Madam:
The purpose of this letter is to document a verbal agreement between JR Groom, Region IV Reactor Projects Branch Chief, and DM Wolfgramm, Regulatory Compliance Supervisor, for an extension of the 30 day requirement to submit a letter to contest a violation in the referenced report. Additional time is required to prepare the response. A response will be provided by the agreed upon date of December 22, 2015.
If you have any questions or require additional information, please contact DM Wolfgramm, Regulatory Compliance Supervisor, at (509) 377-4792.
Executedon z/Io JiC Respectfully, W.G.Hettel Vice President, Operati ns cc: NRC Region IV Administrator NRC Director, Office of Enforcement NRC Senior Resident Inspector/988C CD Sonoda BPN1 399 WA Horin Winston & Strawn December 11, 2015 GO2-15-171
- w. Grover Hettel EIJER V
Columbia Generating Station NORIHAIEST Ph.
wghettel@ energy-northwest.com U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397; REQUEST FOR EXTENSION TO RESPOND TO THE NOVEMBER 12, 2015 NRC INTEGRATED INSPECTION REPORT tEA-i 5-202)
Reference:
Letter dated November 1 2, 201 5, 1W Pruett (NRC) to ME Reddemann (Energy Northwest), Columbia Generating Station NRC Integrated Inspection Report 05000397/201 5003 and Exercise of Enforcement Discretion
Dear Sir or Madam:
The purpose of this letter is to document a verbal agreement between JR Groom, Region IV Reactor Projects Branch Chief, and DM Wolfgramm, Regulatory Compliance Supervisor, for an extension of the 30 day requirement to submit a letter to contest a violation in the referenced report. Additional time is required to prepare the response. A response will be provided by the agreed upon date of December 22, 2015.
If you have any questions or require additional information, please contact DM Wolfgramm, Regulatory Compliance Supervisor, at (509) 377-4792.
Executedon z/Io JiC Respectfully, W.G.Hettel Vice President, Operati ns cc: NRC Region IV Administrator NRC Director, Office of Enforcement NRC Senior Resident Inspector/988C CD Sonoda BPN1 399 WA Horin Winston & Strawn December 11, 2015 GO2-15-171