NSIR REVIEW - TAC A11004 10 CFR 50.54(p)(2) CHANGES TO SECURITY PLAN ENTERGY OPERATIONS GRAND GULF NUCLEAR STATION, UNIT 1 DOCKET NO. 50-416 LICENSE NO. NPF-29

1.0 INTRODUCTION

By letter dated October 22, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15300A098), Entergy Operations, Inc. submitted the Grand Gulf Nuclear Stations Revision 15 to their security plans (Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan) dated August 28, 2015 under the provisions of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(p)(2).

The review of the Licensee security plan was conducted consistent with the applicable requirements of 10 CFR Part 73 as well as the guidance contained within the Office of Nuclear Security and Incident Response (NSIR) Procedure LIC 800 Security Review Procedure for 10 CFR 50.54(p)(2) and the U.S. Nuclear Regulatory Commission (NRC)-endorsed Nuclear Energy Institute (NEI) 03-12, Revision 7, Template for Security Plans as appropriate.

2.0 REGULATORY EVALUATION

Pursuant to 10 CFR 50.54(p)(2): the licensee may make changes to the plans without prior Commission approval if the changes do not decrease the safeguards effectiveness of the security plans. The licensee must submit a report to the NRC containing the description of each change, within two months after changes are made.

The NRC staff review consisted of determining whether the licensee properly concluded that changes did not decrease the safeguards effectiveness of the Commission-approved security plans.

3.0 TECHNICAL EVALUATION

The reviewer compared these changes with the previous Revision 14 of the security plan, which was dated October 28, 2012, and referred to the guidance documents listed above.

Reviewer Action: The reviewer noted that Entergy Operations security plans, Revision 15 contained multiple changes for Grand Gulf Nuclear Station, Unit 1.

The following items were noted:

a. The licensee revised page 7 of the PSP, to address changes in the equipment list for Security force members.
b. The licensee revised section 11.2.1 of the PSP, to address changes to the SOCA Monitoring Center.
c. Section 13.2 was revised to clarify access control and lock destruction procedures.
d. A statement was revised in section 15.3 to address the addition of an Intrusion Detection System.

ML15344A452 PACKAGE: ML15344A457 OFFICE NSIR/DSP NSIR/DSP:BC TITLE DSP Review Branch Chief NAME R. Rockhill D. Huyck DATE 12/14/2015 12/14/2015 NSIR REVIEW - TAC A11004 10 CFR 50.54(p)(2) CHANGES TO SECURITY PLAN ENTERGY OPERATIONS GRAND GULF NUCLEAR STATION, UNIT 1 DOCKET NO. 50-416 LICENSE NO. NPF-29

1.0 INTRODUCTION

By letter dated October 22, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15300A098), Entergy Operations, Inc. submitted the Grand Gulf Nuclear Stations Revision 15 to their security plans (Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan) dated August 28, 2015 under the provisions of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(p)(2).

The review of the Licensee security plan was conducted consistent with the applicable requirements of 10 CFR Part 73 as well as the guidance contained within the Office of Nuclear Security and Incident Response (NSIR) Procedure LIC 800 Security Review Procedure for 10 CFR 50.54(p)(2) and the U.S. Nuclear Regulatory Commission (NRC)-endorsed Nuclear Energy Institute (NEI) 03-12, Revision 7, Template for Security Plans as appropriate.

2.0 REGULATORY EVALUATION

Pursuant to 10 CFR 50.54(p)(2): the licensee may make changes to the plans without prior Commission approval if the changes do not decrease the safeguards effectiveness of the security plans. The licensee must submit a report to the NRC containing the description of each change, within two months after changes are made.

The NRC staff review consisted of determining whether the licensee properly concluded that changes did not decrease the safeguards effectiveness of the Commission-approved security plans.

3.0 TECHNICAL EVALUATION

The reviewer compared these changes with the previous Revision 14 of the security plan, which was dated October 28, 2012, and referred to the guidance documents listed above.

Reviewer Action: The reviewer noted that Entergy Operations security plans, Revision 15 contained multiple changes for Grand Gulf Nuclear Station, Unit 1.

The following items were noted:

a. The licensee revised page 7 of the PSP, to address changes in the equipment list for Security force members.
b. The licensee revised section 11.2.1 of the PSP, to address changes to the SOCA Monitoring Center.
c. Section 13.2 was revised to clarify access control and lock destruction procedures.
d. A statement was revised in section 15.3 to address the addition of an Intrusion Detection System.

ML15344A452 PACKAGE: ML15344A457 OFFICE NSIR/DSP NSIR/DSP:BC TITLE DSP Review Branch Chief NAME R. Rockhill D. Huyck DATE 12/14/2015 12/14/2015