UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:
LASALLE COUNTY STATION, UNITS 1 AND 2
Dear Mr. Hanson:
We have received your corporate letter RS-2015-05, dated May 20, 2015, in response to U.S.
Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letter, you requested initial operator licensing examinations be scheduled for October 2016, October 2018, and October 2020 at the LaSalle County Station. In response, we have scheduled initial operator licensing examinations for the weeks of:
- October 17, 24, and 31, 2016, with an onsite validation date the week of September 19, 2016.
- October 29, November 5 and November 12, 2018 with an onsite validation date the week of October 1, 2018.
With consideration for future NRC resource challenges, we have adjusted your requested exam dated from our last RIS Response letter dated January 28, 2015. Based on these anticipated resources challenges, and class size, the above dates have changed. Additionally, we have scheduled and initial operator licensing examination for the weeks of:
- October 19, and 26, 2020, with an onsite validation date the week of September 21, 2020.
In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than 18 applicants being considered for 2 of the 3 examinations, the 2016 and 2018 examinations were each scheduled for three weeks. Please inform us if the number of candidates decline below 18 for any examination, as this will impact the examination schedule.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.
B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 cc w/encl: Distribution via LISTSERV
B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 cc: Distribution via LISTSERV DISTRIBUTION:
Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMLaSalle RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A918 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton: HPeterson DATE 10/20/15 11/20/15 OFFICIAL RECORD COPY
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:
LASALLE COUNTY STATION, UNITS 1 AND 2
Dear Mr. Hanson:
We have received your corporate letter RS-2015-05, dated May 20, 2015, in response to U.S.
Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letter, you requested initial operator licensing examinations be scheduled for October 2016, October 2018, and October 2020 at the LaSalle County Station. In response, we have scheduled initial operator licensing examinations for the weeks of:
- October 17, 24, and 31, 2016, with an onsite validation date the week of September 19, 2016.
- October 29, November 5 and November 12, 2018 with an onsite validation date the week of October 1, 2018.
With consideration for future NRC resource challenges, we have adjusted your requested exam dated from our last RIS Response letter dated January 28, 2015. Based on these anticipated resources challenges, and class size, the above dates have changed. Additionally, we have scheduled and initial operator licensing examination for the weeks of:
- October 19, and 26, 2020, with an onsite validation date the week of September 21, 2020.
In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than 18 applicants being considered for 2 of the 3 examinations, the 2016 and 2018 examinations were each scheduled for three weeks. Please inform us if the number of candidates decline below 18 for any examination, as this will impact the examination schedule.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.
B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 cc w/encl: Distribution via LISTSERV
B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 cc: Distribution via LISTSERV DISTRIBUTION:
Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMLaSalle RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A918 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton: HPeterson DATE 10/20/15 11/20/15 OFFICIAL RECORD COPY