ML15324A293

From kanterella
Jump to navigation Jump to search
Implementation of TB 15-1 R1 and Unlikely Loss of Both RWSTs at NAPS---E-mail
ML15324A293
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 11/19/2015
From: Mark D. Sartain
Dominion
To: Michael Brown
Japan Lessons-Learned Division
Brown, Tony, NRR/JLD 415-1924
References
Download: ML15324A293 (1)


Text

From: Mark Sartain (Generation - 6)

To: Brown, Tony Cc: Tom Huber (Generation - 6); Thomas P Sharkey (Generation - 6); David Sommers (Generation - 6); Dave Bucheit (Generation - 6); Page Kemp (Generation - 3)

Subject:

[External_Sender] NAPS Implementation of TB 15-1 R1 and Unlikely Loss of Both RWSTs at NAPS Date: Thursday, November 19, 2015 3:53:23 PM Attachments: TB 15-1 plus RWSTs.docx

Tony, Please find attached a summary of the two issues you have been discussing with the Dominion staff as it relates to North Anna. Please let me know if you have any questions.

Mark Sartain VP, Nuclear Engineering, Dominion 804-273-3586 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.

From: Mark Sartain (Generation - 6)

To: Brown, Tony Cc: Tom Huber (Generation - 6); Thomas P Sharkey (Generation - 6); David Sommers (Generation - 6); Dave Bucheit (Generation - 6); Page Kemp (Generation - 3)

Subject:

[External_Sender] NAPS Implementation of TB 15-1 R1 and Unlikely Loss of Both RWSTs at NAPS Date: Thursday, November 19, 2015 3:53:23 PM Attachments: TB 15-1 plus RWSTs.docx

Tony, Please find attached a summary of the two issues you have been discussing with the Dominion staff as it relates to North Anna. Please let me know if you have any questions.

Mark Sartain VP, Nuclear Engineering, Dominion 804-273-3586 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.