Public Meeting Slides- Draft JLD-ISG-2012-01 Revision 1, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
ML15324A257
Person / Time
Site: Purdue University
Issue date: 11/20/2015
From: Cindy Montgomery
Division of Policy and Rulemaking
To: Alexander Adams
Division of Policy and Rulemaking
Uribe, Juan, NRR/JLD 415-3809
References
Download: ML15324A257 (8)


Text

DRAFT JLD-ISG-2012-01, REVISION 1, COMPLIANCE WITH ORDER EA-12-049 EA-12-049, ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS Eric E E. Bowman Special Advisor, Japan Lessons-Learned Division

Purpose The purpose of this meeting is to discuss draft revision 1 to JLD-ISG-2012-01 in order to facilitate stakeholder comments.

1. Revision reflects lessons learned from reviews and acceptable alternative approaches Comments must be submitted in writing in order to ensure that NRC will be able to properly consider them.

2

Availability for Comment

  • Federal Register Notice published November 10 10, 2015 (80 FR 69703)
  • Comment period through December 10, 2015 g g docket ID: NRC-
  • www.regulations.gov 2012-0068 3

Endorsement of Industry Guidance with ith Clarifications Cl ifi ti andd Additions Additi NEI 12-06,, Diverse and Flexible Coping p g Strategies (FLEX) Implementation Guide, Revision 1A, dated October 2015, ML15279A426 4

Reformatted to Align with DG-1301

1. Development and Implementation Process
2. Equipment Capacity
3. Reasonable Protection
4. Equipment Maintenance 5
5. Configuration Control
6. Treatment of Reevaluated Hazards
7. G id Guidance ffor AP1000 D Design i

5

NEI 12-06 New Elements

  • Resolution of generic concerns from reviews
  • Appendix E validation process 6

Mitigating Strategies Assessments

  • Addressing reevaluated seismic and flooding hazards under March 12 12, 2012 request for information

- FLEX and d Modified M difi d FLEX

- Alternative Mitigating Strategies

- Targeted Hazard Mitigating Strategies 7

Mitigating Strategies Assessments, C ti Continued d

  • Flooding - NEI 12 12-06, 06, Appendix G
  • Seismic - placeholder in NEI 12-06 for Appendix H with substantial elements in ISG §6.1 to solicit comments 8

DRAFT JLD-ISG-2012-01, REVISION 1, COMPLIANCE WITH ORDER EA-12-049 EA-12-049, ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS Eric E E. Bowman Special Advisor, Japan Lessons-Learned Division

Purpose The purpose of this meeting is to discuss draft revision 1 to JLD-ISG-2012-01 in order to facilitate stakeholder comments.

1. Revision reflects lessons learned from reviews and acceptable alternative approaches Comments must be submitted in writing in order to ensure that NRC will be able to properly consider them.

2

Availability for Comment

  • Federal Register Notice published November 10 10, 2015 (80 FR 69703)
  • Comment period through December 10, 2015 g g docket ID: NRC-
  • www.regulations.gov 2012-0068 3

Endorsement of Industry Guidance with ith Clarifications Cl ifi ti andd Additions Additi NEI 12-06,, Diverse and Flexible Coping p g Strategies (FLEX) Implementation Guide, Revision 1A, dated October 2015, ML15279A426 4

Reformatted to Align with DG-1301

1. Development and Implementation Process
2. Equipment Capacity
3. Reasonable Protection
4. Equipment Maintenance 5
5. Configuration Control
6. Treatment of Reevaluated Hazards
7. G id Guidance ffor AP1000 D Design i

5

NEI 12-06 New Elements

  • Resolution of generic concerns from reviews
  • Appendix E validation process 6

Mitigating Strategies Assessments

  • Addressing reevaluated seismic and flooding hazards under March 12 12, 2012 request for information

- FLEX and d Modified M difi d FLEX

- Alternative Mitigating Strategies

- Targeted Hazard Mitigating Strategies 7

Mitigating Strategies Assessments, C ti Continued d

  • Flooding - NEI 12 12-06, 06, Appendix G
  • Seismic - placeholder in NEI 12-06 for Appendix H with substantial elements in ISG §6.1 to solicit comments 8