Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015
Safety Our top priority is safe, quality, compliant construction.
Recently Completed Milestones
- Unit 3 CA01 module set in the Nuclear Island
- All Unit 3 CA03 sub-modules delivered to the site
- Unit 3 diesel fire pump and day tank installed
- Unit 3 Turbine Tabletop concrete placement
- Placement of turbine first bay concrete to 100 ft elevation
- Started assembly of Unit 4 CA05
Vogtle Construction Site
Major Modules
U3 CA01 Ready for Hook
Lifting U3 CA01
Setting U3 CA01
U3 CA01 Inside Containment
U3 Containment
Setting First Shield Building Panel
First Course Shield Building Panels
U3 Nuclear Island and Annex Building
U3 Nuclear and Turbine Islands
U3 Concrete Placement
U3 Turbine Island
U3 Turbine Island Table Top Placement
U3 CA03 Assembly
U3 Transformer Foundations
U4 Inside Containment
U4 Outside Containment
U4 Nuclear Island Concrete Formwork
U4 Nuclear Island
U4 Turbine Island
U4 Turbine Island Piping
U4 CA20 Assembly
Units 3&4 Cooling Towers
Steam Generator Arrival
Core Makeup Tank Arrival
Engineering Support Building
Maintenance Support Building
Questions?
Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015
Safety Our top priority is safe, quality, compliant construction.
Recently Completed Milestones
- Unit 3 CA01 module set in the Nuclear Island
- All Unit 3 CA03 sub-modules delivered to the site
- Unit 3 diesel fire pump and day tank installed
- Unit 3 Turbine Tabletop concrete placement
- Placement of turbine first bay concrete to 100 ft elevation
- Started assembly of Unit 4 CA05
Vogtle Construction Site
Major Modules
U3 CA01 Ready for Hook
Lifting U3 CA01
Setting U3 CA01
U3 CA01 Inside Containment
U3 Containment
Setting First Shield Building Panel
First Course Shield Building Panels
U3 Nuclear Island and Annex Building
U3 Nuclear and Turbine Islands
U3 Concrete Placement
U3 Turbine Island
U3 Turbine Island Table Top Placement
U3 CA03 Assembly
U3 Transformer Foundations
U4 Inside Containment
U4 Outside Containment
U4 Nuclear Island Concrete Formwork
U4 Nuclear Island
U4 Turbine Island
U4 Turbine Island Piping
U4 CA20 Assembly
Units 3&4 Cooling Towers
Steam Generator Arrival
Core Makeup Tank Arrival
Engineering Support Building
Maintenance Support Building
Questions?