Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015

Safety Our top priority is safe, quality, compliant construction.

Recently Completed Milestones

  • Unit 3 CA01 module set in the Nuclear Island
  • All Unit 3 CA03 sub-modules delivered to the site
  • Unit 3 diesel fire pump and day tank installed
  • Unit 3 Turbine Tabletop concrete placement
  • Placement of turbine first bay concrete to 100 ft elevation
  • Started assembly of Unit 4 CA05

Vogtle Construction Site Major Modules U3 CA01 Ready for Hook Lifting U3 CA01 Setting U3 CA01 U3 CA01 Inside Containment U3 Containment Setting First Shield Building Panel First Course Shield Building Panels U3 Nuclear Island and Annex Building U3 Nuclear and Turbine Islands U3 Concrete Placement U3 Turbine Island U3 Turbine Island Table Top Placement U3 CA03 Assembly U3 Transformer Foundations U4 Inside Containment U4 Outside Containment U4 Nuclear Island Concrete Formwork U4 Nuclear Island U4 Turbine Island U4 Turbine Island Piping U4 CA20 Assembly Units 3&4 Cooling Towers Steam Generator Arrival Core Makeup Tank Arrival Engineering Support Building Maintenance Support Building Questions?

Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015

Safety Our top priority is safe, quality, compliant construction.

Recently Completed Milestones

  • Unit 3 CA01 module set in the Nuclear Island
  • All Unit 3 CA03 sub-modules delivered to the site
  • Unit 3 diesel fire pump and day tank installed
  • Unit 3 Turbine Tabletop concrete placement
  • Placement of turbine first bay concrete to 100 ft elevation
  • Started assembly of Unit 4 CA05

Vogtle Construction Site Major Modules U3 CA01 Ready for Hook Lifting U3 CA01 Setting U3 CA01 U3 CA01 Inside Containment U3 Containment Setting First Shield Building Panel First Course Shield Building Panels U3 Nuclear Island and Annex Building U3 Nuclear and Turbine Islands U3 Concrete Placement U3 Turbine Island U3 Turbine Island Table Top Placement U3 CA03 Assembly U3 Transformer Foundations U4 Inside Containment U4 Outside Containment U4 Nuclear Island Concrete Formwork U4 Nuclear Island U4 Turbine Island U4 Turbine Island Piping U4 CA20 Assembly Units 3&4 Cooling Towers Steam Generator Arrival Core Makeup Tank Arrival Engineering Support Building Maintenance Support Building Questions?