ML15322A223

From kanterella
Jump to navigation Jump to search
Construction Update Presentation for CIP Meeting November 18, 2015
ML15322A223
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 11/18/2015
From: Yox M
Southern Nuclear Operating Co
To:
Office of New Reactors
Webb M
References
Download: ML15322A223 (32)


Text

Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015

Safety Our top priority is safe, quality, compliant construction.

Recently Completed Milestones

  • Unit 3 CA01 module set in the Nuclear Island
  • All Unit 3 CA03 sub-modules delivered to the site
  • Unit 3 diesel fire pump and day tank installed
  • Unit 3 Turbine Tabletop concrete placement
  • Placement of turbine first bay concrete to 100 ft elevation
  • Started assembly of Unit 4 CA05

Vogtle Construction Site

Major Modules

U3 CA01 Ready for Hook

Lifting U3 CA01

Setting U3 CA01

U3 CA01 Inside Containment

U3 Containment

Setting First Shield Building Panel

First Course Shield Building Panels

U3 Nuclear Island and Annex Building

U3 Nuclear and Turbine Islands

U3 Concrete Placement

U3 Turbine Island

U3 Turbine Island Table Top Placement

U3 CA03 Assembly

U3 Transformer Foundations

U4 Inside Containment

U4 Outside Containment

U4 Nuclear Island Concrete Formwork

U4 Nuclear Island

U4 Turbine Island

U4 Turbine Island Piping

U4 CA20 Assembly

Units 3&4 Cooling Towers

Steam Generator Arrival

Core Makeup Tank Arrival

Engineering Support Building

Maintenance Support Building

Questions?

Vogtle Units 3&4 Construction Update Michael Yox Southern Nuclear Operating Company Nov. 18, 2015

Safety Our top priority is safe, quality, compliant construction.

Recently Completed Milestones

  • Unit 3 CA01 module set in the Nuclear Island
  • All Unit 3 CA03 sub-modules delivered to the site
  • Unit 3 diesel fire pump and day tank installed
  • Unit 3 Turbine Tabletop concrete placement
  • Placement of turbine first bay concrete to 100 ft elevation
  • Started assembly of Unit 4 CA05

Vogtle Construction Site

Major Modules

U3 CA01 Ready for Hook

Lifting U3 CA01

Setting U3 CA01

U3 CA01 Inside Containment

U3 Containment

Setting First Shield Building Panel

First Course Shield Building Panels

U3 Nuclear Island and Annex Building

U3 Nuclear and Turbine Islands

U3 Concrete Placement

U3 Turbine Island

U3 Turbine Island Table Top Placement

U3 CA03 Assembly

U3 Transformer Foundations

U4 Inside Containment

U4 Outside Containment

U4 Nuclear Island Concrete Formwork

U4 Nuclear Island

U4 Turbine Island

U4 Turbine Island Piping

U4 CA20 Assembly

Units 3&4 Cooling Towers

Steam Generator Arrival

Core Makeup Tank Arrival

Engineering Support Building

Maintenance Support Building

Questions?