Associated ISFSIs - Submittal of Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and ISFSI Security Program, Revision 21
ML15314A830
Person / Time
Site: Millstone, Surry, North Anna, 07200002, 07200055  Dominion icon.png
Issue date: 11/05/2015
From: Clark G
Dominion, Dominion Nuclear Connecticut, Dominion Resources Services
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Office of Nuclear Security and Incident Response
References
15-280A
Download: ML15314A830 (3)


Text

-

Dominion Resources Services, Inc.

Innsbrook Technical Center Safeguards Information Dominion 10 CFR 50.54 10 CFR 72.186 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 November 5, 2015 Attention: Document Control Desk Director, Division of Security Policy, Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 DOMINION NUCLEAR CONNECTICUT, INC.

VIRGINIA ELECTRIC AND POWER COMPANY MILLSTONE POWER STATION UNITS 1, 2, AND 3 NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 AND ASSOCIATED ISFSls SUBMITTAL OF SECURiTY PLAN, TRAINING Serial No.:

15-280A NL&OS/MLW: R1 Docket Nos.:

50'-245/336/423 50-338/339 50-280/281 72-2/16/47/55/56 License Nos.: DPR-21/65

. NPF-49 NPF-4/7 DPR~32/37 SNM-2501/2507.

AND QUALIFICATION PLAN, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI) SECURITY PROGRAM - REVISION 21 I

Pursuant to 10 CFR 50. 54(p )(2) and 10 CFR 72.186(b ), Revision 21 of the Millstone, North Anha and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and ISFSI Security Program is provided as Enclosure 1. This revision includes changes to the Millstone. Power Station (MPS) vehicle barrier system (VBS) and owner controlled area (OCA) checkpoint. The evaluation of the MPS changes are provided as Enclosure 2. This plan became effective October 1, 2015. The changes that were made to the plan did not decrease the safeguards effectiveness of the plan.

The enclosed material contains Safeguards lr.iformation as defined by 10 CFR 73.22 and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended.

If you have any questions, please contact Michael Whitlock at 804-273-3123.

Sincerely,

~c__~.

Gianna C. Clark Vice President-Nuclear Support Services Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company Classified By:

Name: Roger Minner

Title:

COORD NUCLEAR SECURITY PROGRAMS Organization: Nuc. Protection SeNices/ Dominion Effective Date: October 13 2015 Unauthorized Disclosure Of Safeguards Information Wi!! Be Subiect To Civil And Criminal Sanctions NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

}-lS~f.-. oz_

µ J.{ SQ.;(p I

Safeguards Information soot

Safeguards Information

  • Serial No. 15-280A Sec. Plan Submittal Page 2 of 3 : Millstone, North Anna and Surry Power Statiqns' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and ISFSI Security Program (SGI) : Millstone Power Station Evaluation of Changes NEI 11-08 PSP 21 50.54 (p) evaluation (SGI)

Commitments made by this letter: None cc:

U. S. Nuclear Regulatory Commission, Region I Attn.: Regional Administrator 2100 Renaissance Blvd.

Suite 100 King of Prussia, Pennsylvania 19406-2713 U. S. Nuclear Regulatory Commission, Region II Attn.: Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257.

Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. J.M. Goshen (Without Enclosure)

NRC Project Manager U.S. Nuclear Regulatory Commission One White Flint North Mail Stop EBB-E3 D2M 11555.Rockville.Pike Rockville, MD 20852-2738 Mr. J. N. Nguyen (Without Enclosure)

Senior Project Manager U. S. Nuclear Regulatory Commission Two White Flint North Mail Stop T 4834 11545 Rockville Pike Rockville, MD 20852 NOTE: THE ENCLOSURES TO THIS LETTER 80NTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

Safeguards Information

Safeguards Information.

Mr. T. H. Carter (Without Enclosure)

NRG Senior Project Manager Millstone Unit 1 & Kewaunee Two White Flirit North Mail Stop T-8 F5 11545 Rockville Pike Rockville, MD 20852-2738 Mr. R. V.,Guzman (Without Enclosure)

NRC Senior Project Manager Millstone Units 2 & 3.

U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton (Without Enclosure)

NRC Project Manager Surry U.S. NuclearRegulatory Coml)'lission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas (Without Enclosure)

NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD. 20852-2738 Ms. L. A. Kauffman (Without Enclosure)

NRC Inspector 2100 Renaissance Blvd.

Suite 100 King of Prussia, PA 19406-2713 NRC Senior Resident Inspector (Without Enclosure)

Millstone Power Station

  • NRC Senior Resident Inspector (Without Enclosure)
    • North Anna Power Station NRC Senior Resident Inspector (Without Enclosure)

Surry Power Station Serial No. 15-280A Sec. Plan Submittal Page 3 of 3 NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

Safeguards Information.

Dominion Resources Services, Inc.

Innsbrook Technical Center Safeguards Information Dominion 10 CFR 50.54 10 CFR 72.186 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 November 5, 2015 Attention: Document Control Desk Director, Division of Security Policy, Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 DOMINION NUCLEAR CONNECTICUT, INC.

VIRGINIA ELECTRIC AND POWER COMPANY MILLSTONE POWER STATION UNITS 1, 2, AND 3 NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 AND ASSOCIATED ISFSls SUBMITTAL OF SECURiTY PLAN, TRAINING Serial No.:

15-280A NL&OS/MLW: R1 Docket Nos.:

50'-245/336/423 50-338/339 50-280/281 72-2/16/47/55/56 License Nos.: DPR-21/65

. NPF-49 NPF-4/7 DPR~32/37 SNM-2501/2507.

AND QUALIFICATION PLAN, SAFEGUARDS CONTINGENCY PLAN, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI) SECURITY PROGRAM - REVISION 21 I

Pursuant to 10 CFR 50. 54(p )(2) and 10 CFR 72.186(b ), Revision 21 of the Millstone, North Anha and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and ISFSI Security Program is provided as Enclosure 1. This revision includes changes to the Millstone. Power Station (MPS) vehicle barrier system (VBS) and owner controlled area (OCA) checkpoint. The evaluation of the MPS changes are provided as Enclosure 2. This plan became effective October 1, 2015. The changes that were made to the plan did not decrease the safeguards effectiveness of the plan.

The enclosed material contains Safeguards lr.iformation as defined by 10 CFR 73.22 and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended.

If you have any questions, please contact Michael Whitlock at 804-273-3123.

Sincerely,

~c__~.

Gianna C. Clark Vice President-Nuclear Support Services Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company Classified By:

Name: Roger Minner

Title:

COORD NUCLEAR SECURITY PROGRAMS Organization: Nuc. Protection SeNices/ Dominion Effective Date: October 13 2015 Unauthorized Disclosure Of Safeguards Information Wi!! Be Subiect To Civil And Criminal Sanctions NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

}-lS~f.-. oz_

µ J.{ SQ.;(p I

Safeguards Information soot

Safeguards Information

  • Serial No. 15-280A Sec. Plan Submittal Page 2 of 3 : Millstone, North Anna and Surry Power Statiqns' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and ISFSI Security Program (SGI) : Millstone Power Station Evaluation of Changes NEI 11-08 PSP 21 50.54 (p) evaluation (SGI)

Commitments made by this letter: None cc:

U. S. Nuclear Regulatory Commission, Region I Attn.: Regional Administrator 2100 Renaissance Blvd.

Suite 100 King of Prussia, Pennsylvania 19406-2713 U. S. Nuclear Regulatory Commission, Region II Attn.: Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257.

Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. J.M. Goshen (Without Enclosure)

NRC Project Manager U.S. Nuclear Regulatory Commission One White Flint North Mail Stop EBB-E3 D2M 11555.Rockville.Pike Rockville, MD 20852-2738 Mr. J. N. Nguyen (Without Enclosure)

Senior Project Manager U. S. Nuclear Regulatory Commission Two White Flint North Mail Stop T 4834 11545 Rockville Pike Rockville, MD 20852 NOTE: THE ENCLOSURES TO THIS LETTER 80NTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

Safeguards Information

Safeguards Information.

Mr. T. H. Carter (Without Enclosure)

NRG Senior Project Manager Millstone Unit 1 & Kewaunee Two White Flirit North Mail Stop T-8 F5 11545 Rockville Pike Rockville, MD 20852-2738 Mr. R. V.,Guzman (Without Enclosure)

NRC Senior Project Manager Millstone Units 2 & 3.

U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton (Without Enclosure)

NRC Project Manager Surry U.S. NuclearRegulatory Coml)'lission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas (Without Enclosure)

NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD. 20852-2738 Ms. L. A. Kauffman (Without Enclosure)

NRC Inspector 2100 Renaissance Blvd.

Suite 100 King of Prussia, PA 19406-2713 NRC Senior Resident Inspector (Without Enclosure)

Millstone Power Station

  • NRC Senior Resident Inspector (Without Enclosure)
    • North Anna Power Station NRC Senior Resident Inspector (Without Enclosure)

Surry Power Station Serial No. 15-280A Sec. Plan Submittal Page 3 of 3 NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ENCLOSURES, THIS LETTER IS "DECONTROLLED."

Safeguards Information.