~YANKEE ATOMIC ELECTRIC COMPANY ANKE49 Yankee Road, Rowe, Massachusetts 01367 October 8, 2015 BYR 2015-032 10 CFR 50.71(e)(4) and 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 - 0001 Yankee Atomic Electric Company Yankee Nuclear Power Station Independent Spent Fuel Storage Installation N-RC License Nos. DPR-3 and SFGL-13 (NRC Docket Nos.50-029 and 72-31)

Subject:

Biennial Update to the Yankee Nuclear Power Station License Termination Plan Pursuant to the requirements of 10 CFR 50.7 1(e)(4) and 10 CFR 50.4, Yankee Atomic Electric Company provides the following update regarding the Yankee Nuclear Power Station (YNPS)

License Termination Plan (LTP). No changes have been made to the YNPS LTP, since the submittal of Revision 4 of the YNPS LTP in the last biennial update on October 23, 2013 (Reference 1).

This letter contains no commitments.

If you have any questions regarding this submittal, please do not hesitate to contact Brian Smith at (413) 424-5261 ext. 303.

I state under penalty of perjury that the foregoing is true and correct. Executed on October 8, 2015.

Wayne Norton YAEC President and Chief Executive Officer

Reference:

1. Letter from W. Norton (YAEC) to Document Control Desk (NRC), Biennial Update of the License Termination Plan, dated October 23, 2013 (BYR 20 13-032).

Yankee Atomic Electric Company BYR 2015-032/October 8, 2015/Page 2 cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager J. Giarrusso, Planning, Preparedness & Nuclear Section Chief, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Reyes, State of Massachusetts Office of the Attorney General

~YANKEE ATOMIC ELECTRIC COMPANY ANKE49 Yankee Road, Rowe, Massachusetts 01367 October 8, 2015 BYR 2015-032 10 CFR 50.71(e)(4) and 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 - 0001 Yankee Atomic Electric Company Yankee Nuclear Power Station Independent Spent Fuel Storage Installation N-RC License Nos. DPR-3 and SFGL-13 (NRC Docket Nos.50-029 and 72-31)

Subject:

Biennial Update to the Yankee Nuclear Power Station License Termination Plan Pursuant to the requirements of 10 CFR 50.7 1(e)(4) and 10 CFR 50.4, Yankee Atomic Electric Company provides the following update regarding the Yankee Nuclear Power Station (YNPS)

License Termination Plan (LTP). No changes have been made to the YNPS LTP, since the submittal of Revision 4 of the YNPS LTP in the last biennial update on October 23, 2013 (Reference 1).

This letter contains no commitments.

If you have any questions regarding this submittal, please do not hesitate to contact Brian Smith at (413) 424-5261 ext. 303.

I state under penalty of perjury that the foregoing is true and correct. Executed on October 8, 2015.

Wayne Norton YAEC President and Chief Executive Officer

Reference:

1. Letter from W. Norton (YAEC) to Document Control Desk (NRC), Biennial Update of the License Termination Plan, dated October 23, 2013 (BYR 20 13-032).

Yankee Atomic Electric Company BYR 2015-032/October 8, 2015/Page 2 cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager J. Giarrusso, Planning, Preparedness & Nuclear Section Chief, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Reyes, State of Massachusetts Office of the Attorney General