1 TurkeyPointLANPEm Resource From:

Hoeg, Tim Sent:

Tuesday, September 01, 2015 2:42 PM To:

Barry J White

Subject:

RE: Other FPL power sources

Barry, When reactor plants are taken down for maintenance, power remains supplied to the electrical grid from other operating power plants that are tied into the electrical grid system. Many electrical power sources both nuclear and non-nuclear are synchronized to the electrical grid in order to maintain adequate capacity for the many consumers. The power company monitors and operates the electrical grid load distribution system. Power companies plan their outages carefully to make sure enough power is being put on the grid to ensure the consumers receive a reliable source of electricity during high demand periods or other forecasted conditions. In addition, the power companies have the capability to also increase output from other sources as needed to compensate for their planned outages.

R/

Tim Hoeg Senior Resident Inspector Region II, Division of Reactor Projects U.S. Nuclear Regulatory Commission Turkey Point Nuclear Station Office: 305-245-7669 9760 SW 344th ST. Fax: 305-247-0224 Homestead, FL 33035


Original Message-----

From: Barry J White [1]

Sent: Tuesday, September 01, 2015 7:44 AM To: Craig Grossenbacher <grossc@miamidade.gov>; Philip Stoddard <pkstoddard@gmail.com>; McCrackine, Sean

<MCCRAS@miamidade.gov>

Subject:

[External_Sender] Other FPL power sources Do we know how and from where FPL drew power as TP 3 & 4 were off line one at a time for seven months each in 2012/2013?

Barry Sent from my iPhone

Hearing Identifier:

TurkeyPoint_LA_NonPublic Email Number:

529 Mail Envelope Properties (Tim.Hoeg@nrc.gov20150901144200)

Subject:

RE: Other FPL power sources Sent Date:

9/1/2015 2:42:27 PM Received Date:

9/1/2015 2:42:00 PM From:

Hoeg, Tim Created By:

Tim.Hoeg@nrc.gov Recipients:

"Barry J White" <bwtamia@bellsouth.net>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1614 9/1/2015 2:42:00 PM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

1 TurkeyPointLANPEm Resource From:

Hoeg, Tim Sent:

Tuesday, September 01, 2015 2:42 PM To:

Barry J White

Subject:

RE: Other FPL power sources

Barry, When reactor plants are taken down for maintenance, power remains supplied to the electrical grid from other operating power plants that are tied into the electrical grid system. Many electrical power sources both nuclear and non-nuclear are synchronized to the electrical grid in order to maintain adequate capacity for the many consumers. The power company monitors and operates the electrical grid load distribution system. Power companies plan their outages carefully to make sure enough power is being put on the grid to ensure the consumers receive a reliable source of electricity during high demand periods or other forecasted conditions. In addition, the power companies have the capability to also increase output from other sources as needed to compensate for their planned outages.

R/

Tim Hoeg Senior Resident Inspector Region II, Division of Reactor Projects U.S. Nuclear Regulatory Commission Turkey Point Nuclear Station Office: 305-245-7669 9760 SW 344th ST. Fax: 305-247-0224 Homestead, FL 33035


Original Message-----

From: Barry J White [2]

Sent: Tuesday, September 01, 2015 7:44 AM To: Craig Grossenbacher <grossc@miamidade.gov>; Philip Stoddard <pkstoddard@gmail.com>; McCrackine, Sean

<MCCRAS@miamidade.gov>

Subject:

[External_Sender] Other FPL power sources Do we know how and from where FPL drew power as TP 3 & 4 were off line one at a time for seven months each in 2012/2013?

Barry Sent from my iPhone

Hearing Identifier:

TurkeyPoint_LA_NonPublic Email Number:

529 Mail Envelope Properties (Tim.Hoeg@nrc.gov20150901144200)

Subject:

RE: Other FPL power sources Sent Date:

9/1/2015 2:42:27 PM Received Date:

9/1/2015 2:42:00 PM From:

Hoeg, Tim Created By:

Tim.Hoeg@nrc.gov Recipients:

"Barry J White" <bwtamia@bellsouth.net>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1614 9/1/2015 2:42:00 PM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: