MONTHYEARML13092A3922013-03-27027 March 2013 Transition to 10 CFR 50.48(c) - NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition - Transition Report Project stage: Request ML13092A3932013-03-27027 March 2013 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) (Technical Specification Change TS-480) Project stage: Request ML13087A4182013-04-0808 April 2013 National Fire Protection Association Standard 805 License Amendment Application Online Reference Portal Project stage: Other ML13128A0132013-05-0303 May 2013 Response to NRC Request for Confirmation of Terms and Conditions of Online Reference Portal, NFPA 805 License Amendment Application Project stage: Request ML13141A2912013-05-16016 May 2013 Response to NRC Request to Supplement License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Supplement ML13115A9552013-05-16016 May 2013 Final ASP Analysis-Browns Ferry Nuclear Plant, Unit 3, Reactor Trip and Subsequent Loss of Offsite Power Due Failure of Unit Station System Transformer Differential Relay (LER 296/12-004) Project stage: Request ML13149A3642013-05-31031 May 2013 Acceptance Review Concerning LAR to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, Project stage: Acceptance Review ML13298A7022013-11-19019 November 2013 RAI Regarding LAR to Request Adopt National Fire Protection Association Standard 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (TAC Nos. MF1185 - MF1187) Project stage: RAI CNL-13-141, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Set 12013-12-20020 December 2013 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Set 1 Project stage: Response to RAI CNL-14-001, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plant2014-01-10010 January 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plant Project stage: Response to RAI CNL-14-006, Response to NRC Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for Browns Ferry Plant, Units 1, 22014-01-14014 January 2014 Response to NRC Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for Browns Ferry Plant, Units 1, 2 & Project stage: Response to RAI CNL-14-020, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2014-02-13013 February 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI CNL-14-025, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2014-03-14014 March 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML14126A3882014-05-20020 May 2014 RAI Regarding Attachment X of License Amendment Request to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (TAC Nos. MF1185-1187) Project stage: RAI ML14133A5262014-05-21021 May 2014 Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (TAC MF1185-87) Project stage: RAI ML14154A4962014-05-30030 May 2014 Update to the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Request CNL-14-097, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants.2014-06-13013 June 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants. Project stage: Response to RAI CNL-14-116, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor2014-07-10010 July 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Project stage: Response to RAI CNL-14-208, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Pl2014-12-17017 December 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plan Project stage: Response to RAI ML15070A5252015-03-12012 March 2015 Request for Additional Information License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (TAC Nos. MF1185-87) Project stage: RAI CNL-15-054, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2015-03-26026 March 2015 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML15085A5522015-03-27027 March 2015 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML15076A1852015-05-0808 May 2015 Audit Report to Support Proposed Amendment to Transition to the National Fire Protection Association Standard 805 Fire Protection Licensing Basis Project stage: Other CNL-15-074, Update to License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2015-06-19019 June 2015 Update to License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Request ML15243A5562015-08-20020 August 2015 NRR E-mail Capture - Browns Ferry, 1, 2, and 3 - Issuance of Amend Transition to a RISK-INFORMED, PERFORMANCE-BASED Fire Protection Program Project stage: Approval CNL-15-191, Update to License Amendment Request to Adopt NFPA 805 Performance- Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and M2015-09-0808 September 2015 Update to License Amendment Request to Adopt NFPA 805 Performance- Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and MF1 Project stage: Request CNL-15-224, Update to License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Revised Implementation Item 492015-10-20020 October 2015 Update to License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Revised Implementation Item 49 Project stage: Request ML15212A7962015-10-28028 October 2015 Issuance of Amendments to Transition to Fire Protection Program NFPA-805 Project stage: Approval CNL-15-253, Brown Ferry, Units 1, 2, and 3 - Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk2016-01-0505 January 2016 Brown Ferry, Units 1, 2, and 3 - Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk Project stage: Other CNL-16-059, Revision to NFPA 805 Interim Compensatory Measures Commitments Regarding Hot Work and Combustible Controls2016-05-10010 May 2016 Revision to NFPA 805 Interim Compensatory Measures Commitments Regarding Hot Work and Combustible Controls Project stage: Other CNL-16-165, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 34, Revised Proposed License Conditions and Technical Specification Change2016-10-31031 October 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 34, Revised Proposed License Conditions and Technical Specification Change Project stage: Supplement CNL-17-024, Update to License Amendment Request to Revise NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor - Revision to Tables S-2 and S-32017-06-0707 June 2017 Update to License Amendment Request to Revise NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor - Revision to Tables S-2 and S-3 Project stage: Request CNL-17-109, Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Genera2017-09-18018 September 2017 Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generati Project stage: Response to RAI CNL-17-130, Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for2017-10-23023 October 2017 Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Project stage: Response to RAI ML17317A4222017-12-19019 December 2017 Issuance of Amendments to Revise NFPA 805 Performance-Based Standard for Fire Protection - Revision to Tables S-2 & S-3 (CAC Nos. MF9814, MF9815, & MF9816; EPID L-2017-LLA-0234) Project stage: Approval 2014-07-10
[Table View] |
Text
1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-224 October 20, 2015 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
Subject:
Update to License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and MF1187) - Revised Implementation Item 49
References:
- 1. Letter from TVA to NRC, "License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) (Technical Specification Change TS-480)," dated March 27, 2013 (ML13092A393)
- 2. Letter from TVA to NRC, "Response to NRC Request to Supplement License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and MF1187)," dated May 16, 2013 (ML13141A291)
- 3. NRC Electronic Mail from Farideh Saba (NRC) to Gordon Williams (TVA),
Clinton Szabo (TVA), and Edward Schrull (TVA), "NFPA 805 Draft SE Issues regarding to implementation 49," dated October 14, 2015 (ML15288A107)
By letter dated March 27, 2013 (Reference 1), Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) for Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3, to transition to National Fire Protection Association Standard (NFPA) 805. In addition, by letter dated May 16, 2013 (Reference 2), TVA provided information to supplement the Reference 1 letter.
During a telephone conversation on October 5, 2015, the NRC requested that TVA revise BFN NFPA 805, LAR, Attachment S, "Modifications and Implementation Items," Table S-3, "Implementation Items," Implementation Item 49, to include specific acceptance criteria related to BFN Residual Heat Removal (RHR) heat exchanger fouling testing. By electronic mail dated October 14, 2015 (Reference 3), the NRC provided the requested wording for Implementation Item 49. The enclosure to this letter provides the updated Table S-3 page incorporating the revised Implementation Item 49.
U. S. Regulatory Commission CNL-15-224 Page 2 October 20, 2015 Consistent with the standards set forth in Title 10 of the Code of Federal Regulations (10 CFR),
Part 50.92(c), TVA has determined that the additional information, as provided in this letter, does not affect the no significant hazards consideration associated with the proposed application previously provided in Reference 1.
There are no new regulatory commitments contained in this submittal. Please address any questions regarding this submittal to Mr. Edward D. Schrull at (423) 751-3850.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 20th day of October 2015.
Respectfully, J. W. Shea Vice President, Nuclear Licensing
Enclosure:
NFPA 805 License Amendment Request, Attachment S, Table S-3, "Implementation Items," Replacement Page Containing Revised Implementation Item 49 cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant State Health Officer, Alabama State Department of Health NRC Branch Chief - Region II J. W. Shea Digitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee Valley Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2015.10.20 15:55:14 -04'00'
ENCLOSURE Tennessee Valley Authority Browns Ferry Nuclear Plant, Units 1, 2, and 3 NFPA 805 License Amendment Request, Attachment S, Table S-3, "Implementation Items,"
Replacement Page Containing Revised Implementation Item 49 (2 pages including cover)
TVA BFN Attachment S - Modifications and Implementation Items Table S-3 Implementation Items Item Unit Description LAR Section / Source 43 1,2,3 Revise the procedure NPG-SPP-18.4.8, Control of Ignition Sources (Hot Work), to incorporate corrective actions identified in MDQ0009992013000160.
4.1 and Attachment A, 3.3.1.3.1 45 1,2,3 Revise procedures NPG-SPP-18.4.7, Control of Transient Combustibles, and NPG-SPP-18.4.8, Control of Ignition Sources (Hot Work), to strengthen risk and defense in-depth administrative controls (e.g., no storage and no hot work designated areas).
Attachment C and V 46 1,2,3 Verification of the condition of electrical cabinet doors to meet Fire Modeling Assumptions will be included in the monitoring Program.
Response to RAI PRA 01.d.i 47 1,2,3 Perform a focused-scope peer review of the Fire PRA. The peer review will include, as a minimum, the following elements: Fire PRA Cable Selection and Location (CS), Human Reliability Analysis (HRA), Fire Risk Quantification (FQ), Uncertainty and Sensitivity Analysis (UNC), Accident Sequence Analysis (AS), and LERF Analysis (element LE-C6). Any focused scope peer review Finding level Facts and Observations (F&Os) will be resolved prior to self-approval of post-transition changes.
Response to RAI PRA 11.a, b and c, PRA RAI 23.d and PRA RAI 24 Part b 48 1,2,3 Develop and deliver training to Fire Operations on incipient detection systems alarm response procedures.
Response to FPE RAI 10, Revision 1 49 1,2,3 Revise the program that monitors BFN Residual Heat Removal (RHR) heat exchanger performance for consistency with the assumptions of the NFPA 805 Net Positive Suction Head (NPSH) analysis. The monitoring program shall include verification that the tested worst fouling resistance, with measurement uncertainty added, of all BFN Units 1, 2, and 3 RHR heat exchangers is less than the design value of 0.001517 hr-ft2-°F/BTU and the worst tube plugging is less than 4.57 percent.
Attachment X /
NRC electronic mail from F. Saba (NRC) to G Williams (TVA) and C. Szabo (TVA), "Browns Ferry NFPA 805 LAR," dated June 10, 2015 /
NRC electronic mail from F. Saba (NRC) to G. Williams (TVA), C. Szabo (TVA), and E. Schrull (TVA), "NFPA 805 Draft SE Issues regarding to implementation 49," dated October 14, 2015