ML15281A215
| ML15281A215 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon (DPR-080, DPR-082) |
| Issue date: | 10/14/2015 |
| From: | Siva Lingam Plant Licensing Branch IV |
| To: | Halpin E Pacific Gas & Electric Co |
| Lingam S | |
| References | |
| CAC MF6591, CAC MF6592 | |
| Download: ML15281A215 (2) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 14, 2015 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 - WITHDRAWAL OF AN AMENDMENT REQUEST RE: REVISE TECHNICAL SPECIFICATION 3.8.9, "DISTRIBUTION SYSTEMS - OPERATING," CONDITION B, REQUIRED ACTION B.1 COMPLETION TIME FROM 2 HOURS TO 24 HOURS (CAC NOS. MF6591 AND MF6592)
Dear Mr. Halpin:
By letter dated August 12, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15224B642), Pacific Gas and Electric Company (PG&E, the licensee) submitted an exigent license amendment request (LAR) for Diablo Canyon Power Plant (DCPP), Unit Nos. 1 and 2. The proposed amendment would have revised the Technical Specification 3.8.9, "Distribution Systems - Operating, Condition B, Required Action B.1 Completion Time from 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to accommodate the replacement of the output breaker for Unit 1 Inverter IY-14 and similar output breakers for Unit 2 online. Subsequently, by letter dated October 7, 2015 (ADAMS Accession No. ML15280A429), you withdrew the LAR.
The purpose of this letter is to advise that the above-cited application is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.
If you have any questions regarding this matter, I may be reached at 301-415-1564.
Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv Sincerely,
~cr*~
Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
ML15280A429), you withdrew the LAR.
The purpose of this letter is to advise that the above-cited application is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.
If you have any questions regarding this matter, I may be reached at 301-415-1564.
Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL4-1 Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorllpl4-1 Resource ADAMS Accession No
- ML15281A215 Sincerely,
/RAJ Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrDeEeeb Resource RidsNrrLAJBurkhardt Resource RidsNrrPMDiabloCanyon Resource RidsRgn4MailCenter Resource OFFICE NRR/DORULPL4-1 /PM NRR/DORULPL4-1 /LA NRR/DORULPL4-1/BC NRR/DORULPL4-1 /PM NAME SLingam JBurkhardt MMarkley Sling am DATE 10/13/15 10/14/15 10/14/15