Attachment 6 OBDI 202 - IOLE Process Rev 1 DRAFT OUTLINE COMMENTS Facility:

ANO2 First Exam Date:

8/24/15 Written Exam Outline Comment Resolution 1 NRC Generated N/A 2

The SRO outline needs to have reference at the end changed to Revision 10.

Outline updated 3

4 5

Administrative JPM Outline Comment Resolution 1

2 3

4 5

Control Room / In-Plant System JPM Outline Comment Resolution 1

S5 - is performed in two of the scenarios. Need to select another pressure control JPM After discussing with the exam author, determined there is an alternate path with critical steps different than the scenarios.

This JPM is acceptable.

2 3

4 5

Simulator Scenario Outline Comments Comment Resolution 1 Generic Comment - Need to specify what the basis are for the specific values Corrected

OBDI 202 - IOLE Process Rev 1 and times associated with the critical tasks? Example is that some critical tasks are associated with 1015.050 time critical actions but not all.

2 Scenario 1, Event 8 - Is this supposed to be the Red train? The turnover says it is a Red train maintenance week.

It is supposed to be a Red train component failure.

3 Scenario 2, Event 6 - Should be a component failure instead of reactivity.

NUREG 1021 allows for a one for one swap of reactivity with an instrument or component failure. Will need to adjust the 301-5 for the ROs and the 301-4.

This will be changed.

Corrected on D-1 4

Scenario 2, CT 2,3 - Have two critical tasks that seem to contradict themselves. One says cannot go below a value (but may as a result of plant conditions) and the other says you have 10 minutes to take action if you go below the same value. Are these CT correct?

If so need to make sure they are clear on the criteria for passing the CT.

The critical tasks will be reworded.

Critical tasks updated 5

ES-301-5 SRO(I) - Does not show what event types the applicant would get if the spare scenario was used for the CRS position.

This has been corrected.

6 7

8 9

10