MONTHYEARIR 05000331/20193012019-06-18018 June 2019 NRC Initial License Examination Report 05000331/2019301 ML22143A9352019-05-16016 May 2019 2019 DAEC Ile ES-201-1 ML22143A9382019-05-16016 May 2019 2019 DAEC Initial License Exam Form ES-201-3 ML22143A9392019-05-16016 May 2019 2019 DAEC Initial License Exam Form ES-301-7 ML22143A9412019-05-16016 May 2019 2019 DAEC Initial License Exam Form ES-401-4 ML22143A9422019-05-16016 May 2019 2019 DAEC Initial License Exam Form ES-401-9 ML22143A9432019-05-16016 May 2019 DAEC 2019 Outline Comments NG-19-0058, 2019 DAEC Addendum to Post Exam Submittal Letter-Comments on Q-70 Clarification2019-04-26026 April 2019 2019 DAEC Addendum to Post Exam Submittal Letter-Comments on Q-70 Clarification NG-19-0057, 2019 DAEC Initial License Examination Post Exam Submittal Letter2019-04-19019 April 2019 2019 DAEC Initial License Examination Post Exam Submittal Letter ML22143A9992019-04-0808 April 2019 2019 DAEC Ile Administered Admin JPMs ML22143B0002019-04-0808 April 2019 2019 DAEC Ile Administered Sim and Inplant JPMs ML22143B0012019-04-0808 April 2019 2019 DAEC Ile Scenarios ML22143B0022019-04-0808 April 2019 2019 Deac Ile Administered Written Exam ML22143B0032019-04-0808 April 2019 RO and SRO Exam Reference Handouts ML19087A3022019-03-28028 March 2019 Operator Licensing Examination Approval (Cdz) ML22144A0672019-02-22022 February 2019 2019 DAEC Ile Proposed RO and SRO Admin JPMs ML22144A0692019-02-22022 February 2019 2019 DAEC Ile Proposed Sim and Inplant JPMs ML22144A0712019-02-22022 February 2019 2019 DAEC Ile Proposed Scenarios ML22144A0732019-02-22022 February 2019 2019 DAEC Ile Proposed Written Exam ML22144A0742019-02-22022 February 2019 2019 DAEC Initial License Exam Form ES-301-3 ML22144A0752019-02-22022 February 2019 2019 DAEC Initial License Exam Form ES-301-4 ML22144A0762019-02-22022 February 2019 2019 Duane Arnold Initial License Exam Form ES-301-6 ML22144A0792019-02-22022 February 2019 2019 DAEC Initial License Exam Form ES-401-6 ML22145A4392019-01-23023 January 2019 2019 DAEC Initial License Examination Submittal Letter ML19009A2502019-01-0808 January 2019 GFE Annual Registration Letter - 2019 Examinations, Region III ML22143B0042018-12-21021 December 2018 2019 DAEC Ile ES-201-2 ML22143B0052018-12-21021 December 2018 2019 Duane Arnold Initial License Exam Forms ES-301-1 ML22143B0062018-12-21021 December 2018 2019 Duane Arnold Initial License Exam Forms ES-301-2 ML22143B0072018-12-21021 December 2018 2019 Duane Arnold Initial License Exam Forms ES-301-5 ML22143B0082018-12-21021 December 2018 2019 Duane Arnold Initial License Exam Forms ES-401-1 and 401-3 ML22143B0092018-12-21021 December 2018 2019 Duane Arnold Initial License Exam Forms ES-D1 ML22143B0102018-11-12012 November 2018 2019 DAEC Ile Outline Submittal Letter NG-18-0089, Preparation and Scheduling of Operator Licensing Examinations (Response to RIS 2018-02)2018-07-25025 July 2018 Preparation and Scheduling of Operator Licensing Examinations (Response to RIS 2018-02) ML18099A2622018-04-0909 April 2018 Gfes Results-March 2018, Duane Arnold Energy Center (Cover Letter Only) ML18086B0662018-03-27027 March 2018 Facility Cover Letter - Riii - March 2018 - GFE ML17361A0302017-12-26026 December 2017 GFE Annual Registration Letter - 2018 Examinations - Region III IR 05000331/20173012017-07-14014 July 2017 NRC Initial License Examination Report 05000331/2017301 (Meb) ML17214A0272017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam ES-401-6 ML17214A0282017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam Admin RO-SRO JPMs ML17214A0342017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam Operating JPMs ML17214A0362017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam Scenarios 1-2-3-Alt ML17214A0382017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam RO Written Examination ML17214A0502017-06-14014 June 2017 Dua 2017 Ile - Proposed Exam SRO Written Examination ML17214A2142017-06-14014 June 2017 Dua 2017 Ile - Administered Exam Scenarios ML17214A2322017-06-14014 June 2017 Dua 2017 Ile - Administered Exam Operating Sim and IP JPMs ML17214A2592017-06-14014 June 2017 Dua 2017 Ile - Administered Exam RO-SRO Admin JPMs ML17214A2952017-06-14014 June 2017 Dua 2017 Ile - Administered Exam RO Written Examination ML17214A3072017-06-14014 June 2017 Dua 2017 Ile - Administered Exam SRO Written Examination ML17214A3502017-06-14014 June 2017 Dua 2017 Ile - Administered Exam Written Examination Handouts ML17214A4012017-06-14014 June 2017 Dua 2017 Ile Administrative Files ES-401-4 2019-06-18
[Table view] Category:Part 55 Examination Related Material
[Table view] |
Text
Appendix D Scenario Outline Form ES-D-1 Facility: Duane Arnold Energy Center Scenario No.: 1 Op-Test No.: 2015301 Examiners: ____________________________ Operators: _____________________________
Initial Conditions: The plant is operating at 80% power due to a downpour for maintenance.
Thunderstorms are forecast for the area. B SBDG was recently returned from maintenance.
Turnover:
- Complete B SBDG Testing per OI 324, SBDG, Section 6.4, synchronize and load.
- Raise Reactor power using control rods to a load line of 94-95%.
Event Malf. Event Event No. No. Type* Description 1 None N BOP Synchronize and load the B SBDG IAW OI 324, Sect 6.4, FAST MANUAL STARTUP OF THE B SBDG SYSTEM.
2 None C BOP Report from field that B SBDG has a jacket cooling water leak TS SRO B SBDG declared inoperable per TS 3.8.1 3 None R ATC Raise reactor power with control rods 4 rd02 C ATC Stuck Control Rod 3023 C RO 5 rd11b CRD Pump trip C BOP 6 hp01 HPCI spurious start requiring manual shutdown/isolation TS SRO HPCI declared inoperable per TS 3.6.
7 ed01(a- M ALL Loss of Offsite Power with Small break LOCA.
e) rr15b stdg01 Failure of A SBDG to start in AUTO, will start in Manual.
8 hp02 C BOP HPCI starts in Manual but trips shortly after.
Emergency Depressurization required.
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor Appendix D Scenario Outline Form ES-D-1
Facility: Duane Arnold Energy Center Scenario No.: 2 Op-Test No.: 2015301 Examiners: ____________________________ Operators: _____________________________
Initial Conditions: The plant is operating at 80% power due to a downpower for maintenance.
Thunderstorms are forecast for the area. B CRD pump was recently taken OOS for maintenance.
Turnover:
- Start B SBDG for ST after maintenance.
- Raise Reactor power recirculation flow.
Event Malf. Event Event No. No. Type* Description 1 None N BOP Perform MSIV test per STP 3.3.1.1-17 for D MSIVs 2 None Raise Power with Recirculation Flow to 85% RTP R RO R SRO 3 rp02a C BOP Trip of RPS MG Set TS SRO Tech Spec 3.3.8; 3.4.5, A & B & C; TRM 3.3.4 entry 4
rd01 C ATC Control Rod Drift (30-23) with AOP 255.1& 255.2 entry 3023 TS SRO Tech Spec entry 3.1.3 5 ed13a C BOP 125 VDC Div 1 panel 1D11 trip results in AOP entries TS SRO Tech Spec entry 3.8.7, Condition B 6 rc08 BOP Spurious start of RCIC, requires manually stopping RCIC TS SRO Tech Spec Entry 3.5.3, Condition A 7 mc04b R RO Condenser Vacuum Leak (recoverable)
C BOP Fast Power Reduction 8 mc04b M ALL Rising backpressure from Event 5 progression necessitates reactor scram. ATWS occurs 9 hp03 I BOP Failure of HPCI controller (complicates RPV level restoration).
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor Appendix D Scenario Outline Form ES-D-1
Facility: Duane Arnold Energy Center Scenario No.: 3 Op-Test No.: 2015301 Examiners: ____________________________ Operators: _____________________________
Initial Conditions:
- Reactor power approximately 40%.
- Power ascension in progress.
Turnover:
- Continue power ascension in accordance with IPOI 3, POWER OPERATIONS (35% - 100%)
RATED POWER, Section 4.0. Steps are completed up to step 5.
- Raise power to approximately 50%.
- Stabilize power at approximately 50% and perform RCIC pump surveillance test.
Event Malf. Event Event No. No. Type* Description 1 R ATC Raise power with recirculation flow.
C ATC 2 rr17a A Recirc Pump Speed Controller Failure.
C SRO I ATC APRM C fails (inoperable).
3 nm08c TS SRO Tech Spec review (3.3.1.1, 3.3.2.1) 4 N BOP RCIC Start IAW OI 150 rc06 A RCIC system isolation signal is received due to steam leak; C BOP 5 sw14a isolation is faulted.
sw14b TS SRO Tech Spec entry (3.5.3)
C BOP 6 sw19b River Water Supply Pump trip.
C SRO Large break LOCA occurs (Recirc Pump suction break). Faulted 7 M (ALL)
LPCI initiation.
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor