MONTHYEARML15153A0332015-06-29029 June 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Reevaluations Project stage: RAI ML15217A3562015-08-14014 August 2015 Nuclear Regulatory Commission Plan for the Audit of Pacific Gas and Electric Company'S Seismic Hazard and Screening Report Submittal Related to the Near-Term Task Force Recommendation 2.1 - Seismic for Diablo Canyon Power Plant, Unit Nos. 1 Project stage: Other ML15238B7742015-08-27027 August 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Reevaluations Project stage: RAI ML15244B0992015-09-0404 September 2015 Nuclear Regulatory Commission Plan for the Audit of Pacific Gas and Electric Company'S Seismic Hazard and Screening Report Submittal Related to the Near-Term Task Force Recommendation 2.1- Seismic for Diablo Canyon Power Plant Unit Nos. 1 a Project stage: Other DCL-15-111, Response to NRC Request for Additional Information Dated August 27, 2015, Regarding Recommendation 2.1 of the Near-Term Task Force Seismic Hazard and Screening Report2015-09-16016 September 2015 Response to NRC Request for Additional Information Dated August 27, 2015, Regarding Recommendation 2.1 of the Near-Term Task Force Seismic Hazard and Screening Report Project stage: Response to RAI ML15267A7742015-10-0101 October 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1 Seismic Evaluations Project stage: RAI ML15355A5502015-12-21021 December 2015 Transmittal of Response to NRC Request for Additional Information Dated October 1, 2015, and November 13, 2015, Regarding Recommendation 2.1 of the Near-Term Task Force Seismic Hazard and Screening Report Project stage: Response to RAI DCL-15-154, Response to NRC Request for Additional Information Dated October 1, 2015, and November 13, 2015, Regarding Recommendation 2.1 of the Near-Term Task Force Seismic Hazard and Screening Report2015-12-21021 December 2015 Response to NRC Request for Additional Information Dated October 1, 2015, and November 13, 2015, Regarding Recommendation 2.1 of the Near-Term Task Force Seismic Hazard and Screening Report Project stage: Response to RAI 2015-08-14
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML24002B1802024-01-29029 January 2024 LRA Audit Plan ML23264A0012023-09-21021 September 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML19106A3902019-04-23023 April 2019 Regulatory Audit Plan for Audit in Support of the License Amendment Request to Revise Technical Specification for Use of Full Spectrum Loss-Of-Coolant Accident Methodology ML17177A4462017-07-0606 July 2017 Audit Plan for Licensee Responses Concerning Seismic Hazard Reevaluations Related to Request for Information -(50.54(F) Letter) Regarding Recommendation 2.1 of the Near-Term Task Force ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16193A3322016-07-12012 July 2016 Audit Plan for August 3-4, 2016, Nrr/Dra/Arcb Regulatory Audit at Westinghouse Facility in Rockville, MD, to Support Review of License Amendment Request for Adoption of Alternative Source Term ML15355A1572015-12-24024 December 2015 Regulatory Audit Plans for 01/12-14/2016 Audit at Westinghouse Facility to Support Review of License Amendment Requests for Adoption of Alternative Source Term and Revision of the UFSAR for Beacon Methodology ML15244B0992015-09-0404 September 2015 Nuclear Regulatory Commission Plan for the Audit of Pacific Gas and Electric Company'S Seismic Hazard and Screening Report Submittal Related to the Near-Term Task Force Recommendation 2.1- Seismic for Diablo Canyon Power Plant Unit Nos. 1 a ML15233A5182015-08-28028 August 2015 License Renewal Environmental Site Audit Regarding Diablo Canyon Power Plant, Units 1 and 2-SAMA ML15217A3562015-08-14014 August 2015 Nuclear Regulatory Commission Plan for the Audit of Pacific Gas and Electric Company'S Seismic Hazard and Screening Report Submittal Related to the Near-Term Task Force Recommendation 2.1 - Seismic for Diablo Canyon Power Plant, Unit Nos. 1 ML15189A3382015-07-20020 July 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 ML15148A2072015-06-10010 June 2015 Nuclear Regulatory Commission Plan for the Audit of Pacific and Gas Electric Company'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 Flooding for Diablo Canyon Power Plant, Units 1 and 2 ML15121A3102015-05-15015 May 2015 Regulatory Audit Plan for June 8-12, 2015 Audit at the Westinghouse Facility in Warrendale, PA, to Support Digital Replacement of Process Protection System License Amendment Request (TAC ME7522-ME7523) ML14126A3772014-05-20020 May 2014 Regulatory Audit Plan for June 3-5, 2014 Audit at the Invensys Operations Management Facility in Lake Forest, CA, to Support Digital Replacement of Process Protection System License Amendment Request (TAC ME7522-ME7523) ML14083A6202014-03-26026 March 2014 Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 ML13192A3142013-07-22022 July 2013 Regulatory Audit Plan for August 6-8, 2013, Audit to Support Review of Digital Instrumentation and Control License Amendment Request ML13029A6672013-02-0101 February 2013 Audit Plan for 2/11-14/13, Regulatory Audit at the CS Innovations/Westinghouse Facility in Scottsdale, Az, to Support Digital Replacement of Process Protection System License Amendment Request (TAC Nos. ME7522-ME7523) 2024-01-29
[Table view] Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 4, 2015 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company P.O. Box 56 Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF PACIFIC GAS AND ELECTRIC COMPANY'S SEISMIC HAZARD AND SCREENING REPORT SUBMITTAL RELATED TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1 - SEISMIC FOR: DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 (TAC NOS. MF5275 AND MF5276)
Dear Mr. Halpin:
This letter documents the U.S Nuclear Regulatory Commission (NRG) staff's plan to perform a regulatory audit of Pacific Gas and Electric Company's (PG&E, the licensee) Seismic Hazard and Screening report (SHSR) submittal related to the Near-Term Task Force Recommendation 2.1-"Seismic" for Diablo Canyon Power Plant, Unit Nos. 1 and 2 (Diablo Canyon). The audit will take place at the Lettis Consultants International offices in, Walnut Creek, CA and is expected to last one day on Friday, September 11, 2015. This technical audit will be performed consistent with NRG Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits,"
dated December 29, 2008, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The NRG staff will develop an audit summary report to document its observations and conclusions within 90 days of the completion of the audit.
The audit will provide the NRG with a better understanding of the seismic hazard reevaluation and the supporting analysis performed for Diablo Canyon, as documented in the SHSR (ADAMS Accession No. ML15071A046). The audit is intended to support the NRG staff review of the SHSR and the subsequent issuance of a Staff Assessment. Additional information is provided below.
The enclosed audit plan outlines the process that will allow the NRG staff to review the SHSR related documentation, identify additional information potentially necessary for PG&E to supplement its SHSR, and discuss technical concerns. The details of this audit have been discussed with Mr. Philippe Soenen of your staff.
E. Halpin If you have any questions, please contact me at (301) 415-1115 or by e-mail at Nicholas.DiFrancesco@nrc.gov.
Sincerely, Nicholas DiF cesco, Senior Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation
Enclosure:
Audit Plan Docket Nos. 50-275 and 50-323 cc w/encl: Distribution via Listserv
NRC PLAN FOR THE AUDIT OF PACIFIC GAS AND ELECTRIC COMPANY'S SEISMIC HAZARD AND SCREENING REPORT SUBMITTAL RELATED TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-SEISMIC DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 BACKGROUND AND AUDIT BASIS:
On March 12, 2012, the U.S Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50 (1 O CFR),
Section 50.54(f). The purpose of that request was to gather information concerning, in part, the seismic hazard at operating reactor sites to enable the NRC staff to determine whether licenses should be modified, suspended, or revoked. The "Required Response" section of Enclosure 1 of the request indicated that licensees should provide a seismic hazard evaluation and screening report within 3 years from the date of the letter for Western United States plants.
By letter dated March 11, 2015 1 , to the NRC, Pacific Gas and Electric Company (PG&E, the licensee) submitted for NRC review its Seismic Hazard and Screening Report (SHSR) for Diablo Canyon Power Plant, Unit Nos. 1 and 2 (Diablo Canyon). On April 28, 2015, the NRC staff held a public meeting with PG&E2 and by letter dated June 29, 2015, NRC staff issued a request of additional information (RAl) 3 to gain a better understanding of the information provided in the SHSR. By letter dated August 12, 20154 , the licensee provided a response to the NRC staff RAI. The NRC staff continues to review the information provided by PG&E and plans to conduct a regulatory audit of Diablo Canyon's site response analysis used in its seismic hazard reevaluation. Specific documents that will be reviewed by the NRC staff during the audit are listed below. The NRC staff performed a separate audit on Diablo Canyon's seismic source characterization models on August 26-27, 2015 5 .
REGULATORY AUDIT SCOPE AND METHODOLGY:
The area(s) of focus for the regulatory audit is the information contained in Diablo Canyon's SHSR and in the August 12, 2015, RAI response related to the site response analysis and all associated and relevant supporting documentation used in the development of these models including, but not limited to, methodology, process information, calculations, computer models, etc.
1 The licensee's SHSR can be found in Agencywide Documents Access and Management System (ADAMS) under Accession No. ML15071A046.
2 The April 28, 2015, public meeting summary can be found in ADAMS under Accession No. ML15125A186.
3 The NRCs Staff's RAls can be found in ADAMS under Accession No. ML15153A033.
4 The licensee's response can be found in ADAMS under Accession No. ML152248575.
5 The audit plan can be found in ADAMS under Accession No. ML15217A356.
Enclosure
DOCUMENTS REQUESTED FOR STAFF EXAMINATION The staff requests that the below documents are available for examination and discussion during the audit:
Fugro (2015). Update of the Three-Dimensional Velocity Model for the Diablo Canyon Power Plant (DCPP) Foundation Area, May 2015 NRG AUDIT TEAM:
Title Team Member Team Leader, NRR/JLD Nicholas DiFrancesco Technical Lead (NRO/DSEA) Clifford Munson Technical Support (NRO/DSEA) Vladimir Graizer Technical Support (NRG/RES) Jon Ake Technical Support (SWRC/Consultant) John Stamatakos Technical Support (RES/DE) Scott Stovall LOGISTICS:
The audit is scheduled on Friday, September 11, 2015. The audit will take place at the Lettis Consultants International offices in Walnut Creek, CA.
DELIVERABLES:
Within 90 days of the audit, the NRG staff will prepare a detailed audit report documenting the information reviewed during the audit, and any open items identified as a result of the audit.
The NRG staff will also document its understanding of the proposed resolution of any identified open items.
The information discussed in these audits may be included, fully or in part, in the development of the NRG technical staff assessments as a result of the SHSR reviews.
E. Halpin If you have any questions, please contact me at (301) 415-1115 or by e-mail at Nicholas.Difrancesco@nrc.gov.
Sincerely, IRA/
Nicholas DiFrancesco, Senior Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation
Enclosure:
Audit Plan Docket Nos. 50-275 and 50-323 cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrPMDiabloCanyon Resource JLD R/F MMarkley, NRR RidsNRRJLD Resource RidsRgn4MailCenter FVega, NRR RidsNrrDorllp14-1 MShams. NRR DJackson, NRR NDiFrancesco, NRR ADAMS Accession No.: ML152448099 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRO/DSEA/RGS/BC* NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME FVega Slent DJackson MS hams NDifrancesco DATE 09/02/2015 09/02/2015 09/04/2015 09/04/2015 09/04/2015 OFFICAL RECORD COPY