Letter Sequence Request |
---|
|
|
MONTHYEARNLS2014028, License Amendment Request to Move Linear Heat Generation Rate (LHGR) and Single Loop Operation LHGR Limit from Technical Requirements Manual to Technical Specifications2014-07-17017 July 2014 License Amendment Request to Move Linear Heat Generation Rate (LHGR) and Single Loop Operation LHGR Limit from Technical Requirements Manual to Technical Specifications Project stage: Request ML14296A5552014-10-21021 October 2014 Task Order No. NRC-HQ-20-14-T-0001 Under Delivery Order No. NRC-HQ-25-14-E-0005 Project stage: Other ML15021A2492015-01-21021 January 2015 NRR E-mail Capture - Cooper Nuclear Station - RAIs for LAR Associated with Moving LHGR and Single Loop Operation LHGR Limit from TRM to TS Project stage: RAI ML15168A1712015-07-14014 July 2015 Issuance of Amendment No. 251, Request to Move Linear Heat Generation Rate (LHGR) and Single Loop Operation LHGR Limit from Technical Requirements Manual to Technical Specifications Project stage: Approval ML15240A0982015-08-24024 August 2015 Transmittal of Core Operating Limits Reports for Cycles 28 and 29 Project stage: Request ML15240A0992015-08-24024 August 2015 Enclosure 2, Core Operating Limits Report, Cycle 28, Revision 1 (Non-Proprietary) Project stage: Request ML15240A1002015-08-24024 August 2015 Enclosure 4, Core Operating Limits Report, Cycle 29, Revision 1 (Non-Proprietary) Project stage: Request ML15257A2502015-09-28028 September 2015 Request for Withholding Information from Public Disclosure - 6/18/15 Affidavit Executed by L. Trosman, Global Nuclear Fuel - Americas, LLC Core Operating Limits Report, Cycles 28 and 29 Project stage: Withholding Request Acceptance 2015-01-21
[Table View] |
|
---|
Category:Letter
MONTHYEARML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements ML23311A1122023-11-0909 November 2023 Project Manager Assignment ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report ML23102A0282023-04-19019 April 2023 U.S. Nuclear Regulatory Commission Presentation at the May 8, 2023, Brownville Village Meeting IR 05000298/20230012023-04-17017 April 2023 Integrated Inspection Report 05000298/2023001 ML23060A1582023-03-0808 March 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000298/2023001 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 ML23041A1622023-02-10010 February 2023 Licensed Operator Positive Fitness-for-Duty Test Request for Additional Information IR 05000298/20220042023-01-30030 January 2023 Integrated Inspection Report 05000298/2022004 IR 05000298/20220112022-12-23023 December 2022 License Renewal Phase 4 Inspection Report 05000298/2022011 ML22286A2072022-11-30030 November 2022 Issuance of Amendment No. 272 Revision to Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements IR 05000298/20220032022-10-27027 October 2022 Integrated Inspection Report 05000298/2022003 ML22304A0052022-10-26026 October 2022 Surveillance Capsule Location (Re-insertion Into the Reactor Vessel) IR 05000298/20223022022-10-20020 October 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022302 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information IR 05000298/20224022022-09-29029 September 2022 NRC Security Inspection Report 05000298/2022402 (Full Report) IR 05000298/20220052022-08-18018 August 2022 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298 2022005) IR 05000298/20223012022-08-10010 August 2022 NRC Examination Report 05000298/2022301 IR 05000298/20220022022-07-28028 July 2022 Integrated Inspection Report 05000298/2022002 ML22200A2772022-07-21021 July 2022 Correction to Proposed Inservice Testing Alternative RS-01, Revision of Error in Safety Evaluation ML22152A1232022-07-18018 July 2022 Issuance of Amendment No. 271 Request for Exception from Certain Primary Containment Leak Rate Testing Requirements IR 05000298/20224012022-06-29029 June 2022 Security Baseline Inspection Report 05000298/2022401 IR 05000298/20224032022-06-28028 June 2022 Security Baseline Inspection Report 05000298/2022403 IR 05000298/20220102022-06-16016 June 2022 Triennial Fire Protection Inspection Report 05000298/2022010 ML22140A1612022-06-0808 June 2022 Proposed Inservice Inspection Alternative RR5-01 Revision 1 ML22147A1122022-06-0101 June 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022301 ML22111A1382022-05-13013 May 2022 Proposed Inservice Testing Alternative RS-01, Revision 0 IR 05000298/20220012022-04-28028 April 2022 Integrated Inspection Report 05000298/2022001 IR 05000298/20224042022-04-13013 April 2022 Material Control and Accounting Program Inspection Report 05000298/2022404 - (Public) ML22084A6032022-04-0404 April 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection 05000298/2022002 and Request for Information ML22090A2892022-04-0101 April 2022 John Larson'S Invitation to Participate in the 8th Nuclear Regulatory Commission'S Workshop on Vendor Oversight ML22045A0012022-03-31031 March 2022 Proposed Inservice Inspection Alternative RI5- 02 Revision 3 IR 05000298/20210062022-03-0202 March 2022 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2021006) IR 05000298/20210042022-01-24024 January 2022 Integrated Inspection Report 05000298/2021004 ML21350A0582021-12-21021 December 2021 Withdrawal of an Amendment Request ML21340A2362021-12-20020 December 2021 Issuance of Amendment No. 270 Adoption of Technical Specifications Task Force Traveler TSTF-582, Revision 0, RPV WIC Enhancements 2024-01-03
[Table view] |
Text
Proprietary Information
-Withhold Under 10CFR2.390 N Nebraska.Public Power District Always there when you need us NLS201 5082 August 24, 2015 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, D.C. 20555-0001
Subject:
Core Operating Limits Reports for Cycles 28 and 29 j Cooper Nuclear Station, Docket No. 50-298, DPR-46
References:
- 1. Letter from David W. Van Der Kamp, Nebraska Public Power District, to U.S.Nuclear Regulatory Commission, dated October 22, 2012, "Core Operating Limits Report, Cycle 28, Revision 0" 2. Letter from Jim Shaw, Nebraska Public Power District, to U.S. Nuclear Regulatory Commission, dated October 20, 2014, "Core Operating Limits Report, Cycle 29, Revision 0" 3. Letter from Kenneth Higginbotham, Nebraska Public Power District, to U.S.Nuclear Regulatory Commission, dated February 19, 2015, "Response .to Nuclear Regulatory Commission Request for Additional Information for License Amendment Request Associated with Moving LHGR and Single Loop Operation LHGR Limit from TRM to TS"
Dear Sir or Madam:
The purpose of this letter is to request removal of the Cooper Nuclear Station (CNS) Core Operating Limits Reports (COLR) for Cycles 28 and 29 from the public domain, as Global Nuclear Fuel (GNF) has determined that these documents contain GNF proprietary information.
These reports were previously submitted to the Nuclear Regulatory Commission (NRC) by References 1 and 2 above and were recorded in the Agencywide Documents Access and Management System (ADAMS), under ML12305A005 and ML14302A074, respectively.
In addition, the Cycle 29 COLR was also provided in Reference 3, which was recorded in ADAMS under ML1 5055A038.At the request of CNS, the NRC has removed the subject documents from the public domain.*This letter formally documents thatrequest and provides appropriate follow-up information.
Enclosures 1 and 3 contain Proprietary Information.
Upon separation from these Enclosures, the cover letter and the remainder of the document are decontrolled.
COOPER NUCLEAR STATION P.O. Box 98 / Brownville, NE 68321-0098 Telephone:
(402) 825-3811 / Fax: (402) 825-5211 ww.nppd.com Proprietary Information
-Withhold Under 10CFR2.390 NLS201 5082 Page 2 of 3 Enclosed with this letter are revisions to the COLRs for Cycles 28 and 29 that appropriately identify the proprietary information.
Both a proprietary version and a non-proprietary version of each COLR is provided.
At the request of GNF, Nebraska Public Power District (NPPD)requests that the revisions in the public domain submitted by References 1 and 2 be removed and replaced with the non-proprietary versions in Enclosures 2 and 4. There are no technical changes from the previous revisions.
Reference 3 contained a proposed markup of the Cycle 29 COLR in Attachment 2, as well as a copy of the existing Section 6 of the COLR in Attachment
- 5. Both of these Attachments contain GNF proprietary information.
These documents were provided to the NRC in support of a License Amendment Request, which has since been approved.
Enclosures 5 and 6 provide replacement copies with GNF proprietary information removed. NPPD requests that Attachments 2 and 5 of Reference 3 be removed from the public domain and replaced with the non-proprietary copies in Enclosures 5 and 6.The enclosed documentation contains proprietary information as defined by 10 CFR 2.390.GNF, as the owner of the proprietary information, has executed an affidavit (Enclosure 7), which identifies that the enclosed proprietary information has been handled and classified as proprietary, is customarily held in confidence, and has been withheld from public disclosure.
The proprietary information was provided to CNS in a GNIF transmittal that is referenced in the affidavit.
This letter makes no regulatory commitments.
If you have any questions regarding this matter, please contact me at (402) 825-2788.Sincerely, SJmhaw ,11 Manager/lb
Enclosures:
- 1. Cooper Nuclear Station Core Operating Limits Report, Cycle 28, Revision 1 (Proprietary)
- 2. Cooper Nuclear Station Core Operating Limits Report, Cycle 28, Revision 1 (Non-Proprietary)
- 3. Cooper Nuclear Station Core Operating Limits Report, Cycle 29, Revision 1 (Proprietary)
- 4. Cooper Nuclear Station Core Operating Limits Report, Cycle 29, Revision 1 (Non-Proprietary)
Enclosures 1 and 3 contain Proprietary Information.
Upon separation from these Enclosures, the cover letter and the remainder of the document are decontrolled.
Proprietary Information
-Withhold Under 10CFR2.390 NLS20 15082 Page 3 of 3 5. Cooper Nuclear Station Core Operating Limits Report, Cycle 29, Revision 0, Proposed Markup of COLR to Reflect Reference to Technical Specifications (Non-Proprietary)(Replacement for NLS20 15016, Attachment 2)6. Cooper Nuclear Station Core Operating Limits Report, Cycle 29, Revision 0, Section 6, Maximum Linear Heat Generation Rate (Non-Proprietary)(Replacement for NLS2015016, Attachment 5)7. Global Nuclear Fuel Affidavit cc: Regional Administrator w/enclosures USNRC -Region IV Cooper Project Manager w/enclosures USNRC -NRR Project Directorate IV- 1 Senior Resident Inspector w/enclosures USNRC -CNS NPG Distribution w/o enclosures CNS Records w/enclosures Enclosures 1 and 3 contain Proprietary Information.
Upon separation from these Enclosures, the cover letter and the remainder of the document are decontrolled.