10 CFR 50.54 August 28, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278

Subject:

Supplement to Response to March 12, 2012, Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendations of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, Enclosure 5, Recommendation 9.3, Emergency Preparedness - Staffing, Requested Information Items 1, 2 and 6 -

Phase 2 Staffing Assessment

Reference:

Letter, M. J. Massaro (Exelon) to U.S. Nuclear Regulatory Commission, dated 5/8/15 (original response)

Based on a verbal request from Mr. Peter Bamford, U.S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation, we are providing this supplement to the referenced letter. Attachment 1 of the letter provided an evaluation and the supporting basis related to the use of security personnel during a beyond design basis event. Attachment 2 of the letter provided generic guidance intended for use by all Exelon sites in the development of their site-specific programs. This supplement is to clarify that Attachment 2 of the referenced letter is not part of the site staffing assessment. As such, some of the guidance may not be applicable to the site assessment. Any application of the guidance would be done consistent with the site study.

This letter contains no safeguards or security related information.

If you have any questions, feel free to contact Shelly Griffith at 717-456-3025.