MONTHYEARSVP-23-022, Correction/Errata for the 2022 Annual Radioactive Effluent Release Report2023-05-12012 May 2023 Correction/Errata for the 2022 Annual Radioactive Effluent Release Report ML23132A2042023-05-12012 May 2023 Annual Radioactive Effluent Release Report ML16056A1392016-03-11011 March 2016 Correction to the U.S. Nuclear Regulatory Commission Analysis of Licensees' Decommissioning Funding Status Reports ML15239B2152015-09-0404 September 2015 Master Report - Tables 1 and 2 ML15238B6912015-09-0404 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation RA-13-081, Proposed Resolution for Completion of the Seismic Walkdowns Associated with NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.3 of the Near-Term.2013-09-16016 September 2013 Proposed Resolution for Completion of the Seismic Walkdowns Associated with NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.3 of the Near-Term. RA-13-075, Response to NRC Request for Information Per 10 CFR 50.54(f) Re the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident- 1.5 Year Response for CEUS Sites2013-09-12012 September 2013 Response to NRC Request for Information Per 10 CFR 50.54(f) Re the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident- 1.5 Year Response for CEUS Sites ML12012A1952012-01-11011 January 2012 SAMG-2 RPV, Containment, and Radioactivity Release Control ML12012A1942012-01-11011 January 2012 SAMG-1 Primary Containment Flooding NEI 08-09, Re-Submittal of the Exelon Cyber Security Plan2010-07-23023 July 2010 Re-Submittal of the Exelon Cyber Security Plan ML0728203072007-10-11011 October 2007 Electronic Distribtion Initiative Letter, Licensee List, Electronic Distribution Input Information, Division Plant Mailing Lists ML0709304662007-05-24024 May 2007 NRC Receipt of Quad Cities Nuclear Power Station Units 1 & 2, Response to Generic Letter 2003-01, Control Room Habitability (TAC No. MB9845 and MB9846) RS-06-156, Response to Request for Additional Information Related to Extended Power Uprate Operation Commitments2006-10-17017 October 2006 Response to Request for Additional Information Related to Extended Power Uprate Operation Commitments RS-05-123, Commitments and Plans Related to Extended Power Uprate Operation2005-09-23023 September 2005 Commitments and Plans Related to Extended Power Uprate Operation ML18227D1461976-02-26026 February 1976 Quad-Cities Units 1 & 2 - Submits Table 2, Revised as Supplement C to Quad-Cities Special Report, Which Indicates Latest Core Wide Metal to Water Reaction Percentage of .18 ML17252B1821974-03-29029 March 1974 Report No. 29, Supplement B Transient Analysis for Dresden-3 Cycle 3 and Quad-Cities-1 Cycle 2. 2023-05-12
[Table view] |
Text
Quad Cities, Units 1 & 2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference Elevation Runup Hazard Elevation Local Intense Precipitation Not included Not included Not included FHRR Enclosure 1 Section 2.c in DB in DB in DB Streams and Rivers 603.0 ft Not 603.0 ft FHRR Enclosure 2 Table 1 MSL1912 applicable MSL1912 Failure of Dams and Onsite Water Control/Storage Structures Not included Not included Not included FHRR Enclosure 2 Table 1 in DB in DB in DB Storm Surge No Impact No Impact No Impact FHRR Enclosure 2 Table 1 on the Site on the Site on the Site Identified Identified Identified Seiche No Impact No Impact No Impact FHRR Enclosure 2 Table 1 on the Site on the Site on the Site Identified Identified Identified Tsunami No Impact No Impact No Impact FHRR Enclosure 2 Table 1 on the Site on the Site on the Site Identified Identified Identified Ice-Induced Flooding Not included Not included Not included FHRR Enclosure 2 Table 1 in DB in DB in DB Channel Migrations/Diversions No Impact No Impact No Impact FHRR Enclosure 2 Table 1 on the SIte on the Site on the Site Identified Identified Identified Note: Reported values are rounded to the nearest one-tenth of a foot.
Quad Cities, Units 1 & 2 Table 2. Reevaluated Flood Hazards for Flood-Causing Mechanisms for Use in the MSA Mechanism Stillwater Waves/ Reevaluated Reference Elevation Runup Hazard Elevation Local Intense Precipitation Min-doors by Safety Related 596.5 ft Minimal 596.5 ft Table 4-2 in Enclosure 2 of the Structures, Systems and MSL1912 MSL1912 January 13, 2015 Response to Components Request for Additional Information (ML15021A179)
Max-doors by Safety Related 598.4 ft Minimal 598.4 ft Table 4-2 in Enclosure 2 of the Structures, Systems and MSL1912 MSL1912 January 13, 2015 Response to Components Request for Additional Information (ML15021A179)
Failure of Dams and Onsite Water Control/Storage Structures Combined Event: Riverine, Dam 600.9 ft 4.1 ft 605.0 ft FHRR Enclosure 2, Table 1 Failure and Waves MSL1912 MSL1912 July 3, 2014 Response to Request for Additional Information (See RAI Item
- 2) ML14238A384 Note 1: The licensee is expected to develop flood event duration parameters and applicable flood associated effects to conduct the MSA. The staff will evaluate the flood event duration parameters (including warning time and period of inundation) and flood associated effects during its review of the MSA.
Note 2: Reevaluated hazard mechanisms bounded by the current design basis (see Table 1) are not included in this table.