Summary of 890112 Meeting W/Util in Seneca,Sc Re Licensing & Insp Issues.Meeting Participants Listed in Encl 1 & Viewgraphs Provided in Encl 2
ML15224B233
Person / Time
Site: Oconee, Mcguire, Catawba, McGuire, 05000000
Issue date: 01/25/1989
From: Pastis H
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8902010181
Download: ML15224B233 (21)


Text

january 25, 1989 Docket Nos.:

50-269, 50-270, 50-287 50-369, 50-370 50-413, 50-414.

FACILITIES:

Oconee Nuclear Station - Units 1, 2, and 3; McGuire Units 1 and 2; and Catawba Units 1 and 2 UTILITY:

Duke Power Company

SUBJECT:

SUMMARY

OF JANUARY 12, 1989 MEETING ON ACTIVITIES OF DUKE POWER COMPANY On January 12, 1989, the NRC staff met at the Oconee site in Seneca, South Carolina with Duke Power Company (Duke) to discuss licensing and inspection issues. The meeting was unique in that issues generic to Duke were addressed in addition to plant-specific activities. Current and future issues were discussed in a forum that included personnel from Duke, NRC Region II, NRC resident inspection staff, and NRR.

In the morning session Duke (1) discussed its recent reduction in force and reorganization, (2) presented selected generic activities regarding all three stations, and (3) then discussed specific activities at Oconee. In the afternoon session,.the participants formed three groups in a workshop format and discussed plant-specific issues relating to Oconee, McGuire, and Catawba.

We plan to continue the meetings on a bimonthly basis, rotating among Duke sites.

The next meeting is projected for March at the McGuire site.

Meeting participants are listed in Enclosure 1. Viewgraphs used by Duke during the presentation are provided in Enclosure 2.

Helen Nicolaras Pastis, Project Manager Project Directorate 11-3 Division of Reactor Project -I/II Office of Nuclear Reactor Regulation P

-3' H

is:sw D tthews 1t 89 1/ 1/89 R920 101='f -390125 PDR ADOCK 05000269 P

PDiC

Mr. H. B. Tucker Oconee Nuclear Station Duke Power Company Units Nos. 1, 2 and 3 cc:

Mr. A. V. Carr, Esq.

Mr. Paul Guill Duke Power Company Duke Power Company P. 0. Box 33189 Post Office Box 33189 422 South Church Street 422 South Church Street Charlotte, North Carolina 28242 Charlotte, North Carolina 28242 J. Michael McGarry, III, Esq.

Bishop, Liberman, Cook, Purcell & Reynolds 1200 Seventeenth Street, N.W.

Washington, D.C. 20036 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 525 1700 Rockville Pike Rockville, Maryland 20852 Manager, LIS NUS Corporation 2536 Countryside Boulevard Clearwater, Florida 33515 Senior Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 610 Seneca, South Carolina 29678 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W., Suite 2900 Atlanta, Georgia 30323 Mr. Heyward G. Shealy, Chief Bureau of Radiological Health South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, South Carolina 29201 Office of Intergovernmental Relations 116 West Jones Street Raleigh, North Carolina 27603 Honorable James M. Phinney County Supervisor of Oconee County Walhalla, South Carolina 29621

DISTRIBUTION FOR MEETING

SUMMARY

DATED: January ?5". 1989 Facility: *Oconee Units 1, 2, and 3 McGuire Units 1 and 2 Catawba Units 1 and 2 Docket File NRC PDR Local PDR PDII-3 Reading T. Murley 12-G-18 J. Sniezek 12-G-18 G. Holohan 13-A-2 S. Varga 14-E-4 G. Lainas 14-H-3 D. Matthews 14-H-25 M. Rood 14-H-25 H. Pastis 14-H-25 D. Hood 14-H-25 K. Jabbour 14-H-25 OGC 15-B-18 E. Jordan MNBB-3302 B. Grimes 9-A-2 ACRS (10)

P-315 B. Borchardt 17-D-19 R. Jones 8-E-23 C. Heh1 RII P. Skinner RII P. VanDoorn RII W. Orders RII

ENCLOSURE 1 DUKE/NRC INTERFACE MEETING January 12, 1989 Name Organization Robert Gill Duke, Regulatory Compliance Bob Futrell Duke, Nuc. Safety Assurance J. S. Warren Duke, Regulatory Compliance R. 0. Sharpe Duke, McGuire Compliance R. Michael Glover Duke, Catawba Compliance D. Hood NRR Project Manager - McGuire K. N. Jabbour NRR Project Manager - Catawba Paul Guill Duke, Regualatory Compliance Helen N. Pastis NRR Project Manager -

Oconee David Matthews NRC/NRR/PDI1-3 Robert Jones NRC/NRR/Reactor Systems Branch C. W. Hehl NRC/RII P. H. Skinner NRC/Sr. Resident Insp.- Oconee P. K. VanDoorn NRC/Sr. Resident Insp.- McGuire W. T. Orders NRC/Sr. Resident Insp.- Catawba Peter LeRoy Duke, Regulatory Compliance Gus Lainas NRC/NRR/ADR2 Craig Harlin DPC/Compl. Eng. -

Oconee Ed LeGette DPC/Compl. ONS M. D. McIntosh DPC/Nuc. Prod. Dept./General Office Mike Tuckman Station Manager Oconee John McIntosh Supt. of Support Duke Power/NRC Regulatory Compliance Interface Meeting January 12, 1989 Oconee Nuclear Station Visitor Center AGENDA 8:00 AM Opening Remarks R C Futrell 8:15 AM Duke Presentation of Selected Generic Activities of Interest o

Work Activity Review o

Mid-Loop Operations o

Operability Determinations 10:00 AM BREAK 10:15 AM Duke Presentation of Selected Oconee M S Tuckman Specific Activities of Interest 11:45 AM Closing Remarks/Next Meeting 12:00 Noon LUNCH 1:00 PM -

Duke/NRC Regulatory Activities Project Manager 3:00 PM Status Review Meeting Resident Inspector Develop 1989 Priority Activities List Compliance Engineers

Nuclear Safety Assurance Organizational Chart ID #NP-03 Total Group Employees 52 Approved Open Positions 3

Total Approved 55 MANAGER, NUCLEAR SAFETY ASSURANCE R C Futrell SECRETARY III NSRB V M McDermott TECH. SYS. MANAGER TECH. SYS. MANAGER OPERATIONAL REGULATORY NUCLEAR SAFETY COMPLIANCE ST Rose R L Gill SEE DETAIL SEE DETAIL CHART #NP-03A F

CHART #NP-03C OCONEE SRG McGUIRE SRG CATAWBA SRG CHAIRPERSON CHAIRPERSON CHAIRPERSON H R Lowery A R Sipe CSEE DETAIL SEE DETAIL SEE DETAIL RT #NP-03B CHART #NP-03B CHART #NP-03B

  • To Be Filled 12/1/88

Nuc1 Safety Assurance Organ ational Chart 10 #NP-03A MANAGER, NUCLEAR SAFETY ASSURANCE R C Futrell TECH. SYS. MGR.

OPERATIONAL NUCLEAR SAFETY S T Rose SUPERVISOR SUPPORT ENGINEER SUPPORT ENGINEER NUCLEAR SAFETY &

OPERATIONAL EVENT SAFETY COMPLIANCE SUPPORT DATA ANALYSIS ANALYSIS R F Cole R M Roberts R L White T E Mooney S G Adams PT Vu HP Smith L J Rudy M J LaForrest PROGRAMS PROGRAMS SUPPORT COORDINATION J A Reavis J S Muransky M T Kuck 0 Mendezoff K V Crane B C Wells H A Froebe

Nucle Safety Assurance Organ tional Chart ID #NP-03B MANAGER, NUCLEAR SAFETY ASSURANCE R C Futrell OCONEE SRG McGUIRE SRG CATAWBA SRG CHAIRPERSON CHAIRPERSON CHAIRPERSON H R Lowery A R Sipe D J Berkshire J S Reeside**

Open Eng. Position**

K F Brown C L Brown M D Gilmore N T Clarkson G R Clayton R W Kirk G C O'Neal R J Delonis B 0 McNeill L P Powell A D Jones J R Wallace B C Beaver M M Helms To be filled Permanent assignment as SRG Group Member

Nucl9 Safety Assurance Organizational Chart ID #NP-03C MANAGER, NUCLEAR SAFETY ASSURANCE R C Futrell TECH. SYS. MGR.

REGULATORY COMPLIANCE R L Gill SECRETARY II L C Smith SUPPORT ENGINEER SUPPORT ENGINEER SUPPORT ENGINEER OCONEE REGULATORY McGUIRE REGULATORY CATAWBA REGULATORY COMPLIANCE COMPLIANCE COMPLIANCE P F Guill JS Warren P G LeRoy M A Haghi P B Nardoci R W Ouellette P J North S E LeRoy L T Burba R E Eller S A Gewehr J G Torre W T Byers W R Cross

Nuclear Safety Assurance Functal Organizational Chart Opera?"onal Nuclear Safety OPERATIONAL NUCLEAR SAFETY NUCLEAR SAFETY &

COMPLIANCE SUPPORT PROG5RAMS PROGRAMS SUPPORT COORDINATION

  • OEP Support
  • OEP Coordination Document Receipt & Logging Department Directive (SOER, SER, PIR, VIL, IEN, OE, etc.)

Implementation and Training Document Distribution and Tracking OEP Assessment Corrective Action Commitment Tracking Document Research for Prior Escalation Policy & Status Reporting Attention Incident Report Loading Document Research for Prior Attention

  • Criterion XVI Coordination
  • NETWORK Coordination
  • QA Department Coordination
  • Performance Indicator Reporting Support NSRB Audit Plan Schedule and Tracking NRC Gray Book Coord. Dept. Audit Responses Executive Summary Report (Monthly)

Audit Team Support Coord.

INPO Quarterly Report INPO Activity Coordination

  • Maintain Nuclear Safety and Regulatory Compliance File Correspondence Plant Evaluation Scheduling
  • FSAR Update Support and Responses Document Assimilation,
  • APM and Department Directive Distribution and Control Coordination
  • Facility Operating License and
  • Nuclear Insurance Coordination Tech. Spec. Amendment Support

@ New Rules and Regulations Document Distribution and Control Receipt and Screening LISNUS Information Coordination Coordinate Reviews and Comments

  • Duke Nuclear Guide Coordination

SI OPERATIONAL NUCLEAR SAFETY OPERATIONAL DATA EVENT SAFETY ANALYSIS ANALYSIS

  • NPROS Coordination
  • Engineering Analysis Failure Reporting & Records Update Trip and Safety System User and Software Support Actuation Review Event Safety Analysis and
  • Trend Reporting and Analysis Investigation Support System Operational Readiness Incident Reports, NRC Inspection Evaluations Reports 0EP Report Screening and OE Data Base Management Results Review Routine Trend Analysis
  • Component Failure Monitoring Prepare/Track Transmittals Periodic Component Failure Analysis Meeting Agenda Definition Reports of Performance Trends Staff Action Items and Plant Evaluation Support Outstanding Items Resolution 10CFR50.59 Safety Evaluation
  • Data Base Applications Support Screening Meeting Minutes Report Coding Internal Data Bases Owners Group Data Bases
  • INPO SEE-IN Contacts INPO/NRC Data Bases Nuclear NETWORK Entries
  • AOTC Monitoring
  • Owners Group Participation
  • Safety System Performance Indicator Program BWOG Transient Assessment Committee
  • Monitoring External Data and Trend WOG TRAP Committee Reports Report Preparation and Utilization INPO and NRC Performance Indicators o SOER Response Assessment

Nuclear Safety Assurance Fun nal Organizational Chart Stat n Safety Review Groups NUCLEAR SAFETY ASSURANCE OCONEE McGUIRE CATAW8A SRG SRG SRG Independent On-site Review and Assessment of Safety-Related Activities Programmatic Reviews Surveillances/In-plant Observations OEP Urgent Distribution of Information Reviews of Effectiveness of Corrective Actions LER Investigation and Report Preparation NSRB Support Provide Responses to NSRB Member Questions and Requests for Information Provide Semi-Annual Report to NSRB of SRG Activities a

Prepare and Submit Monthly Report to Management

Nuclear Safety Assurance Functional Organizational Chart Regulatory Compliance Section REGULATORY COMPLIANCE OCONEE McGUIRE CATAWBA REGULATORY REGULATORY REGULATORY COMPLIANCE COMPLIANCE COMPLIANCE New Rules & Regulations Develop Actions to Address New Rules Regulatory Issues Review Issues arising from NRC Enforcement Actions, Generic Letters, and Bulletins Coordinate Responses to Significant Issues Respond to NRC Requests for Information regarding Plant Design, Plant Programs, etc.

Operating License Coordinate Preparation and Submittal of License Amendment Request, including Tech. Spec. Changes Routine Responses to NRC Prepare and Submit Responses of o

Annual FSAR Update o

Annual 10CFR50.59 Reports o

ISI Reports o

ILRT Reports o

IWV & IWP Updates o

Relief Requests Review and Submit LERs

-2 Maintain Quality Standards Manual NRC Commitment Index NRC Inspection Reports Review and Distribute Coordinate Responses to Violations Interpret Rules and Regulations Security Plans Interpretation Change Applications NRC-ONRR Support Support for Station Procedure Development Security Compliance Activity Inspection Interface Response to Inspection Items QA Audit Participation and Response Regulatory Effectiveness Review Interface Design Engineering Interface Relative to Security Design Bases Interpretation Design Studies and NSM Activities Station Direct Security Support Hardware Training Procedure and Manual Development Local Law Enforcement Liaison Power Group Interface Relative to Security Owners Group Activities

Nuclear Safety Assurance The major organizational and functional changes involving Nuclear Safety Assurance (NSA) following the work activity review are as follows:

1. Licensing has been transferred from the Nuclear Technical Services Group to the NSA Group and has been named Regulatory Compliance.
2. Security Support has been transferred from the Nuclear Department Service Group to the NSA Group and consolidated with Regulatory Compliance. The Security Support function of the previous Generic Licensing Unit has also been consolidated with Regulatory Compliance.
3. The remaining functions of the Generic Licensing Unit has been consolidated with the Operating Experience Management Unit and named Nuclear Safety and Compliance Support.
4. The preparation of LERs is in the process of being transferred from the Regulatory Compliance Section to the station Safety Review Groups (SRGs).

Initiatives to strengthen activities in the Regulatory Compliance are as follows:

1. Improving Verbal Communication with NRC (Resident, Region II and NRC Staff)

Routine meetings to exchange information.

Approximate two month interval for middle management.

Approximate eight month interval for high level management.

2. Improving Written Communication with NRC Quality and timeliness.

Closer supervision and performance management program.

3. Improving Duke Management Awareness and Involvement with regulatory issues Monthly management briefings on major issues.

Periodic status reports.

4. Improving Station and General Office Coordination and Communication regarding regulatory issues.

Increased number of functional area meetings.

Coordinated with routine meetings with NRC.

-2

5. Strengthening the Security Support Function Increased management oversight.

Consolidate Security Regulatory Compliance activities under one management scheme.

6. Improving LERs Quality, accuracy and timeliness.

Foster closer working relationship between SRGs and Station Compl iance.

OCONEE SPECIFIC ACTIVITIES OF INTEREST NOTEWORTHY ACTIVITIES Ul HAD BEST RUN EVER (235 CONTINUOUS DAYS)

U2 HAD BEST RUN EVER (351 CONTINUOUS DAYS)

ONS HAD 4 RUNS IN EXCESS OF 100 CONTINUOUS DAYS RADIATION EXPOSURES LOWEST SINCE 1975 (877 PERSON-REM)

SUCCESSFULLY CLEANED Ul & U2 OTSG'S TOPFORM / ONSITE DE OFFICE / DE REORGANIZATION SITA AUDIT PROGRAM CONCERNS BAD START FOR 1989 (2 TRIPS; FIRE; FAILURE OF RBCU DROPOUT PLATES)

HPI PIGGYBACK CIVIL PENALTY U3 LOSS OF RHR IN DRAIN DOWN CONDITION EVENT OF 9/11/88 (LER 287/88-05)

WIRING DISCREPANCY / OPEN SLIDING LINKS FOULING OF U3 RBCU'S

MAJOR ACTIVITIES DURING Ul REFUELING OUTAGE RECOVERY / REPAIR OF ITA SWITCHGEAR DROPOUT PLATE TEST RBCU TESTING AND CLEANING INSPECTION AND CLEANING OF OTHER HEAT EXCHANGERS 52% OF SG TUBES IN A & B OTSG INSPECTED UT OF BATCH 13 FUEL ASSEMBLIES NSM'S IMPLEMENT GL 88-17 EXPEDITIOUS ACTIONS 42 INCH MSR PIPE REPLACEMENT LAST OF 780 LIMITORQUES IEB 88-11 PRZ SURGE LINE THERMAL STRATIFICATION VISUAL INSPECTION OF Ul PRZ SURGE LINE INSTRUMENTING Ul PRZ SURGE LINE AS WELL AS HPI INJECTION LINE (IEB 88-08)

STATUS OF HED / REG. GUIDE 1.97 MODIFICATIONS CHANGES IN COMMITMENT PROVIDED BY A 4/20/88 LETTER SCHEDULE FOR COMPLETION U1EOC14 REFUELING OUTAGE (5/93)

U2EOC13 REFUELING OUTAGE (10/93)

U3EOC13 REFUELING OUTAGE (11/92)

STILL ON SCHEDULE STATUS OF PALS 2+ MODIFICATION IMPLEMENTED ON UNIT 3 SCHEDULE FOR Ul AND U2 PROVIDED BY A 1/3/89 LETTER UNIT 1 - 4/1/90 UNIT 2 - 8/1/90 FOR INTERIM, CURRENT Ul & U2 SYSTEM FUNCTIONAL

STATUS OF RBCU FOULING UPDATE PROVIDED BY A 12/15/88 LETTER Ul RBCU TESTED 11/8/88 U2 RBCU TESTED 10/4/88 U3 RBCU TESTED 10/6/88 AND 11/1/88 OPERABILITY CRITERIA FOR RBCU AND LPI COOLERS HAS BEEN REVISED GOAL: DELETE RBCU'S AS A REQUIRED SAFETY SYSTEM INSTALLATION OF CAVITATING VENTURIS CHANGE IN COMMITMENT PROVIDED BY A 12/16/88 LETTER IDENTIFIED A PROBLEM (EXCESSIVE VIBRATION)

EVALUATING OTHER ALTERNATIVES TO RESOLVE OPERATOR BURDEN ISSUE (BY 6/15/89)

STATUS OF BWOG / SPIP ACTIVITIES RECOMMENDATIONS UNDER EVALUATION 29 RECOMMENDATIONS BEING IMPLEMENTED 35 RECOMMENDATIONS CLOSED 159 CLOSED / OPERABLE 86 CLOSED/NA 54 CLOSED / REJECTED 19