MONTHYEARML24304A8492024-10-31031 October 2024 December 2024 Requalification Inspection Notification Letter IR 05000327/20250102024-10-29029 October 2024 Notification of Sequoyah, Units 1 and 2 - Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000327/2025010 and 05000328/2025010 ML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions ML24247A2212024-08-29029 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-21-160, NEI 03-08 Needed Guidance: PWR Lower Radial Support Clevis Insert X-750 Bolt Inspection Requirements, September 1, 2021 ML24247A1802024-08-28028 August 2024 Application to Revise the Fuel Handling Accident Analysis, to Delete Technical Specification 3.9.4, Containment Penetrations, and to Modify Technical Specification 3.3.6, Containment Ventilation Isolation Instrumentation for Sequoyah Nuclea IR 05000327/20240052024-08-26026 August 2024 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2024005 and 05000328/2024005 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), IR 05000327/20240022024-07-31031 July 2024 Integrated Inspection Report 05000327/2024002 and 05000328/2024002 ML24211A0572024-07-29029 July 2024 Submittal of Emergency Plan Implementing Procedure Revision ML24211A0542024-07-29029 July 2024 Operator License Examination Report ML24211A0412024-07-26026 July 2024 Unit 1 Cycle 26 Refueling Outage - 90-Day Inservice Inspection Summary Report ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24191A4652024-07-0909 July 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24177A0282024-06-25025 June 2024 Emergency Plan Implementing Procedure Revisions ML24176A0222024-06-24024 June 2024 Retraction of Interim Report of a Deviation or Failure to Comply – Transducer Model 8005N ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24145A0852024-05-30030 May 2024 1B-B Diesel Generator Failure - Final Significance Determination Letter ML24145A1052024-05-29029 May 2024 301 Exam Approval Letter ML24134A1762024-05-13013 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24128A0352024-05-0707 May 2024 Providing Supplemental Information to Apparent Violation ML24120A0582024-04-26026 April 2024 10 CFR 50.46 Annual Report for Sequoyah Nuclear Plant Units 1 and 2 ML24116A2612024-04-25025 April 2024 Interim Report of a Deviation or Failure to Comply - Transducer Model 8005N ML24114A0482024-04-23023 April 2024 Annual Radioactive Effluent Release Report for 2023 Monitoring Period CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24144A2362024-04-20020 April 2024 Discharge Monitoring Report (Dmr), March 2024 ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24089A0882024-04-18018 April 2024 – Exemption from Select Requirements of 10 CFR Part 73; Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000327/20240012024-04-17017 April 2024 Integrated Inspection Report 05000327/2024001 and 05000328/2024001 ML24109A0272024-04-16016 April 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) ML24106A0502024-04-12012 April 2024 Discharge Monitoring Report (Dmr), February 2024 2024-09-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 11, 2015 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3R-C Chattanooga, TN 37 402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - RESPONSE REGARDING PHASE 2 STAFFING SUBMITTALS ASSOCIATED WITH NEAR-TERM TASK FORCE RECOMMENDATION 9.3 RELATED TO THE FUKUSHIMA DAl-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NOS. MF5692 AND MF5693)
Dear Mr. Shea:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 10 of the Code of Federal Regulations (1 O CFR) Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter), regarding Recommendations 2.1 (seismic and flooding evaluations), 2.3 (seismic and flooding walkdowns), and 9.3 (emergency preparedness communication and staffing) of the Near-Term Task Force (NTTF) review of insights from the Fukushima Dai-ichi accident. With respect to Recommendation 9.3, Enclosure 5 to the NRC's letter requested licensees and holders of construction permits to assess their means to power communications equipment onsite and offsite during a prolonged station blackout (SBO) event and to perform a staffing assessment to determine the staff required to fill all necessary positions in response to a multi-unit event.
The 50.54(f) letter in part, required licensee responses pursuant to the provisions of 10 CFR 50.54(f) pertaining to onsite and augmented staff availability to implement the strategies discussed in the emergency plan and/or plant operating procedures including new staff or functions resulting from the assessment, any identified collateral duties, an implementation schedule to perform the assessments, any identified modifications, and any changes that have been made or will be made to the emergency plan regarding on-shift or augmented staffing. In addition, NTTF Recommendation 9.3 has a dependency on the implementation of NTTF Recommendation 4.2 (mitigating strategies). As a result of this dependency, licensees responded to the 50.54(f) letter in phases. The Phase 1 staffing assessment requested licensees to evaluate their ability to respond to a multi-unit extended loss of alternating current (ac) power (ELAP) event utilizing existing processes and procedures. The licensee responses to the 50.54(f) letter for Phase 1 staffing assessments for multi-unit sites were received and evaluated by the NRC staff by April 30, 2013. The NRC staff issued acknowledgement letters to all licensees with multi-unit sites, with the exception of San Onofre Nuclear Generating Station, by April 28, 2014
J. Shea Licensees were also requested to submit for NRC staff review a Phase 2 staffing assessment, which provides an assessment of the staffing necessary to perform the functions related to the strategies developed in response to NTTF Recommendation 4.2 and the resulting Order EA 049, "Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events [BDBEE]" (ADAMS Accession No. ML12054A736).
Licensees were requested to provide their Phase 2 Staffing Assessments to the NRC no later than four months prior to the beginning of their second refueling outage (as used in the context of NRC Order EA-12-049). By letter dated January 30, 2015 (ADAMS Accession No. ML15030A512), Tennessee Valley Authority (the licensee) submitted its Phase 2 staffing assessment for Sequoyah Nuclear Plant, Units 1 and 2 to the NRC in response to the 50.54(f) letter.
The NRC staff reviewed your Phase 2 staffing assessment in accordance with the assumptions and guidelines of Sections 2.2, 2.3, and 3 of the Nuclear Energy Institute (NEI) guidance document NEI 12-01, "Guideline for Assessing Beyond Design Basis Accident Response Staffing and Communications Capabilities," (ADAMS Accession No. ML12125A412), which was endorsed by the NRC staff by letter dated May 15, 2012, (ADAMS Accession No. ML12131A043). The NRC staff noted that you assessed your current onsite minimum staffing levels to identify any enhancements needed to respond following a beyond-design-basis large-scale natural event, and to ensure that the strategies contained in the existing emergency plan and/or plant operating procedures, such as those used in response to a SBO, can be performed by the site staff. Your assessment assumed that a large-scale natural event causes: (1) an ELAP, (2) all units on the site to be affected, and (3) access to the site to be impeded for a minimum of six hours. You also assessed your capability to perform the site specific functions related to the strategies developed in response to NTTF Recommendation 4.2 and the resulting Order EA-12-049. You conducted independent reviews and concluded, based on your staffing assessment, that the existing on-shift minimum staff is sufficient to implement the existing loss of all ac power, multi-unit event response strategies, including those strategies developed to support the requirements of NRC Order EA-12-049, while supporting performance of the required emergency planning duties without unacceptable collateral duties.
The NRC staff reviewed your Phase 2 staffing submittal and confirmed that your existing emergency response resources, as described in your emergency plan, are sufficient to perform the required plant actions and emergency plan functions, and implement the multi-unit event response strategies that were developed in response to NRC Order EA-12-049 without the assignment of collateral duties that would impact the performance of assigned emergency plan functions.
As a result, the NRC staff concludes that your Phase 2 staffing submittal adequately addresses the response strategies needed to respond to a BDBEE using your procedures and guidelines.
The NRC staff will verify the implementation of your staffing capabilities through the inspection program.
J. Shea If you have any questions regarding this letter, please contact Stephen Philpott at (301) 415-2365 or via email at Stephen.Philpott@nrc.gov.
Mandy K. Halter, Acting Branch Chief Orders Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328 cc: Distribution via Listserv
ML15190A375 *via email OFFICE NRR/JLD/JOMB/PM NRR/JLD/LA NSIR/DPR/DDEP/NRLB/BC* NRR/JLD/JOMB/BC NAME SPhilpott Slent A Rivera MHalter DATE 07/22/15 07/09/15 07/07/15 08/11/15