1 Fermi2LRANPEm Resource From:
Keegan, Elaine Sent:
Tuesday, June 30, 2015 11:26 AM To:
Randall D Westmoreland (westmorelandr@dteenergy.com); Lynne S Goodman (goodmanl@dteenergy.com)
Subject:
Schedule change letter Attachments:
ml15160a297.pdf Lynne and Randy, Attached is the schedule change letter. There was a small problem with the actual schedule in the Enclosure that we had to fix before I could send this to you. This will be sent out via Listerve today and will also be in ADAMS today.
Elaine ELAINE M KEEGAN SR. PROJECT MANAGER DIVISION OF LICENSE RENEWAL, NRR U.S. NUCLEAR REGULATORY COMMISSION 301-415-8517
Hearing Identifier:
Fermi2_LR_NonPublic Email Number:
294 Mail Envelope Properties (Elaine.Keegan@nrc.gov20150630112600)
Subject:
Schedule change letter Sent Date:
6/30/2015 11:26:22 AM Received Date:
6/30/2015 11:26:00 AM From:
Keegan, Elaine Created By:
Elaine.Keegan@nrc.gov Recipients:
"Randall D Westmoreland (westmorelandr@dteenergy.com)" <westmorelandr@dteenergy.com>
Tracking Status: None "Lynne S Goodman (goodmanl@dteenergy.com)" <goodmanl@dteenergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 398 6/30/2015 11:26:00 AM ml15160a297.pdf 174389 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 29, 2015 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
SCHEDULE REVISION FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION
Dear Mr. Kaminskas:
By letter dated April 24, 2014, DTE Electric Company (DTE) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the Fermi 2 license renewal review.
The original license renewal schedule was developed assuming only one round of Severe Accident Mitigation Alternative (SAMA) analyses request for additional information (RAI). To date, there have been three rounds of RAIs sent to DTE by NRC staff by letters dated November 18, 2014 (Agencywide Documents Access and Management System Accession No. ML14308A358), February 3, 2015 (ML15026A307), and April 9, 2015 (ML15092A945). DTEs response to the first SAMA RAI is dated January 9, 2015 (ML15009A358), the second SAMA RAI is dated March 5, 2015 (ML15064A099), and the third SAMA RAI is dated May 8, 2015 (ML15141A163).
Issuing the two additional SAMA RAIs has resulted in a delay in NRC staff completing the SAMA review. As a result of this delay, there is a corresponding delay in publishing the draft and final supplemental environmental impact statement (SEIS). The new dates for the environmental review milestones are on the Fermi 2 License Renewal Application Review Schedule which is enclosed with this letter.
Enclosed is the NRC staff's revised review schedule for the Fermi 2 license renewal application.
If you have any questions related to the revised schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.
Sincerely,
/RA/Jane Marshall for Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Revised Schedule cc w/encl: Listserv
- concurred via email OFFICE LA:DLR:RPB1 PM:RPB2:DLR PM:RPB1:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR NAME IBetts EKeegan DMeléndez-Colón BWittick YDiaz-Sanabria CMiller (JMarshall for)
DATE 6/12/15 6/15/15 6/17/15 6/25/15 6/25/15 6/29/15
FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestones Schedule Date Actual Date Receive license renewal application (LRA) 04/30/14 04/30/14 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 06/18/14 Publish FRN - environmental scoping meeting 06/2014 06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 07/24/14 07/24/14 Audit - Scoping and Screening Methodology 08/04/14 08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14 08/18/14 Environmental scoping periods ends 08/2014 08/29/14 Audit - Environmental 09/08/14 09/08/14 Audit - Aging Management Programs (Week 1) 09/15/14 09/15/14 Audit - Aging Management Programs (Week 2) 09/29/14 09/29/14 Regional Inspection - IP 71002, License Renewal Procedure 04/2015 04/13/15 Issue safety evaluation report (SER) with open item(s) 09/2015 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 11/2015 Issue draft supplemental environmental impact statement (SEIS) 10/2015 U.S. Environmental Protection Agency FRN Published - draft SEIS available for comments 11/2015 Public Meeting - draft SEIS meeting 12/2015 End of draft SEIS comment period 12/2015 Issue final SER 02/2016 ACRS Full Committee meeting 04/2016 Issue final SEIS 06/2016 U.S. Environmental Protection Agency FRN Published - final SEIS available 07/2016 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision, if hearing granted TBD ENCLOSURE
SUBJECT:
SCHEDULE REVISION FOR THE REVIEW THE FERMI 2 LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource DMeléndez-Colón EKeegan BWittick CKanatas, OGC MKunowski, RIII BKemker, RIII PSmagacz, RIII VMitlyng, RIII PChandrathil, RIII HLogaras, RIII ABarker, RIII DMcIntyre, OPA