MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 11, 2015 Mr. Mark E. Reddemann Chief Executive Officer Energy Northwest MD 1023 76 North Power Plant Loop P.O. Box 968 Richland, WA 99352
SUBJECT:
COLUMBIA GENERATING STATION - RESPONSE REGARDING PHASE 2 STAFFING SUBMITTALS ASSOCIATED WITH NEAR-TERM TASK FORCE RECOMMENDATION 9.3 RELATED TO THE FUKUSHIMA DAl-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NO. MF5511)
Dear Mr. Reddemann:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter), regarding Recommendations 2.1 (seismic and flooding evaluations), 2.3 (seismic and flooding walkdowns), and 9.3 (emergency preparedness communication and staffing) of the Near-Term Task Force (NTTF) review of insights from the Fukushima Dai-ichi accident. With respect to Recommendation 9.3, Enclosure 5 to the NRC's letter requested licensees and holders of construction permits to assess their means to power communications equipment onsite and offsite during a prolonged station blackout (SBO) event and to perform a staffing assessment to determine the staff required to fill all necessary positions in response to a multi-unit event.
The 50.54(f) letter in part, required licensee responses pursuant to the provisions of 10 CFR 50.54(f) pertaining to onsite and augmented staff availability to implement the strategies discussed in the emergency plan and/or plant operating procedures including new staff or functions resulting from the assessment, any identified collateral duties, an implementation schedule to perform the assessments, any identified modifications, and any changes that have been made or will be made to the emergency plan regarding on-shift or augmented staffing. In addition, NTTF Recommendation 9.3 has a dependency on the implementation of NTTF Recommendation 4.2 (mitigating strategies). As a result of this dependency, licensees responded to the 50.54(f) letter in phases. The Phase 1 staffing assessment requested licensees to evaluate their ability to respond to a multi-unit extended loss of alternating current (ac) power (ELAP) event utilizing existing processes and procedures. The licensee responses to the 50.54(f) letter for Phase 1 staffing assessments for multi-unit sites were received and evaluated by the NRC staff by April 30, 2013. The staff issued acknowledgement letters to all licensees with multi-unit sites, with the exception of San Onofre Nuclear Generating Station, by April 28, 2014.
M. Reddemann Licensees were also requested to submit for NRC staff review a Phase 2 staffing assessment, which provides an assessment of the staffing necessary to perform the functions related to the strategies developed in response to NTTF Recommendation 4.2 and the resulting Order EA 049, "Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events [BDBEE]" (ADAMS Accession No. ML12054A736).
Licensees were requested to provide their Phase 2 Staffing Assessments to the NRC no later than four months prior to the beginning of their second refueling outage (as used in the context of NRC Order EA-12-049). By letter dated December 23, 2014 (ADAMS Accession No. ML15006A030), Energy Northwest (the licensee) submitted its Phase 2 staffing assessment for Columbia Generating Station (Columbia) to the NRC in response to the 50.54(f) letter.
The NRC staff reviewed your Phase 2 assessment for staffing in accordance with the assumptions and guidelines of Sections 2.2, 2.3, and 3 of the Nuclear Energy Institute (NEI) guidance document NEI 12-01, "Guideline for Assessing Beyond Design Basis Accident Response Staffing and Communications Capabilities," (ADAMS Accession No. ML12125A412),
which was endorsed by the NRC staff by letter dated May 15, 2012 (ADAMS Accession No. ML12131A043). The NRC staff noted that you assessed your current onsite minimum staffing levels to identify any enhancements needed to respond following a beyond-design-basis large-scale natural event, and to ensure that the strategies contained in the existing emergency plan and/or plant operating procedures, such as those used in response to a SBO, can be performed by the site staff. Your assessment assumed that a large-scale natural event causes: ( 1) an ELAP, (2) all units on the site to be affected, and (3) access to the site to be impeded for a minimum of six hours. You also assessed your capability to perform the site specific functions related to the strategies developed in response to NTTF Recommendation 4.2 and the resulting Order EA-12-049. You conducted independent reviews and concluded, based on your staffing assessment, that the existing on-shift minimum staff is sufficient to implement the existing loss of all ac power event response strategies, including those strategies developed to support the requirements of NRC Order EA-12-049, while supporting performance of the required emergency planning duties without unacceptable collateral duties.
The NRC staff reviewed your Phase 2 staffing submittal and confirmed that your existing emergency response resources, as described in your emergency plan, are sufficient to perform the required plant actions and emergency plan functions, and implement the event response strategies that were developed in response to NRC Order EA-12-049 without the assignment of collateral duties that would impact the performance of assigned emergency plan functions.
As a result, the NRC staff concludes that your Phase 2 staffing submittal adequately addresses the response strategies needed to respond to a BDBEE using your procedures and guidelines.
The NRC staff will verify the implementation of your staffing capabilities through the inspection program.
M. Reddemann If you have any questions regarding this letter, please contact Stephen Philpott at (301) 415-2365 or via email at Stephen.Philpott@nrc.gov.
Sincerely, M~d~
Mandy K. Halter, Acting Chief Orders Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket No. 50-397 cc: Distribution via Listserv