Letter Sequence Response to RAI |
---|
|
|
MONTHYEARML14342B0042014-12-0101 December 2014 Cycle 19 - 180-Day Steam Generator Tube Inspection Report Project stage: Request ML15092A1732015-04-0202 April 2015 Request for Additional Information Related to Spring 2014 Steam Generator Inspections Report Review Project stage: RAI ML15156A3892015-04-28028 April 2015 LTR-SGMP-15-25 Np, Response to NRC Request for Additional Information on the Design Features of the Sequoyah, Unit 2, Replacement Steam Generators. Project stage: Response to RAI ML15156A3882015-05-29029 May 2015 Response to NRC Request for Additional Information Related to the Spring 2014 Steam Generator Tube Inspection Project stage: Response to RAI ML15217A3282015-08-26026 August 2015 Review of the Steam Generator Tube Inservice Inspections for Cycle 19 Refueling Outage in 2014 Project stage: Approval 2015-04-28
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] |
Text
Tennessee Valley Authority, Post Office Box 2000, Soddy Daisy, Tennessee 37384-2000 May 29, 2015 10 CFR 50.4 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Unit 2 Facility Operating License No. DPR-79 NRC Docket No. 50-328
Subject:
Response to NRC Request for Additional Information Related to the Spring 2014 Steam Generator Tube Inspection (TAC No. MF5422)
Reference:
- 1. NRC letter to TVA, "Sequoyah Nuclear Plant, Units 1 and 2, Request for Additional Information Related to The Spring 2014 Steam Generator Tube Inspection (TAC No. MF5422)," dated April 2, 2015
- 2. TVA letter to NRC, "Unit 2 Cycle 19 - 180 Day Steam Generator Tube Inspection Report," dated December 1, 2014 This letter provides the response to the NRC request for additional information (Reference 1) regarding the Sequoyah Nuclear Plant, Unit 2, steam generator tube inspection report submitted under Reference 2. contains TVA's response to NRC's request for information (RAI). The response to RAI 1 is provided separately in Enclosure 2 and includes information provided by Westinghouse that is considered proprietary in nature. Pursuant to 10 CFR 2.390, "Public inspections, exceptions, requests for withholding," paragraph (a)(4), TVA requests that this information be withheld from public disclosure. contains the affidavit from Westinghouse supporting this request. provides a redacted version of Enclosure 2 that is suitable for public disclosure.
U.S. Nuclear Regulatory Commission Page 2 May 29, 2015 There are no new regulatory commitments contained in this letter. If you have any questions concerning this report, please contact Erin Henderson at (423) 843-7170.
Respectfully, John T. Carlin Site Vice President Sequoyah Nuclear Plant
Enclosures:
- 1. TVA Response to NRC Request for Additional Information
- 2. LTR-SGMP-1 5-25 P, Response to NRC Request for Additional Information on the Design Features of the Sequoyah Unit 2 Replacement Steam Generators (Proprietary)
- 3. Westinghouse Affidavit for LTR-SGMP-1 5-25 P
- 4. LTR-SGMP-1 5-25 NP, Response to NRC Request for Additional Information on the Design Features of the Sequoyah Unit 2 Replacement Steam Generators (Non-Proprietary) cc (Enclosure):
NRC Regional Administrator- Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant 4
ENCLOSURE I TVA RESPONSE TO NRC REQUEST FOR ADDITIONAL INFORMATION
Request No. I General information concerning the design of your replacement steam generators (SGs) was provided in the submittal. In order for the staff to better understand the design of your replacementSGs, please provide the following information:
- a. A tubesheet map depicting the row and column numbers
- b. Tube pitch (e.g., triangular,1.00-inch center-to-center)
- c. Expansion method and extent (e.g., hydraulic expansion for the full length of the tubesheet)
- d. Tube support plate and U-bend support materialand design
- e. Flow distribution baffle design, if applicable f Whether tubes were stress relieved after bending, and if so, the rows that were stress relieved
- g. The smallest U-bend radius
- h. Tubesheet thickness with and without clad
- i. The naming convention for the U-bend support structures and a more detailed diagram (since it appears that there are various supports running between the vertical straps within the tube bundle)
Response No. 1 of this letter contains the proprietary response to information concerning the design of the replacement steam generators. Enclosure 4 of this letter contains a redacted version of the response that is suitable for public disclosure.
Request No. 2 Please discuss the results of the foreign object search and retrievalinspections.
Response No. 2 Foreign Object Search and Retrieval was performed in each steam generator as described in the 180 day report (Reference 1). Eddy current testing (ECT) identified no possible loose parts (PLP) calls, and there were no indications of loose part wear.
Visual inspections of the top-of-tubesheet (TTS) and tube lane and no-tube lane area were performed for foreign objects after completion of sludge lancing. Foreign objects found are listed in the table below. Each of the foreign objects found were retrieved.
Steam Generator: Location Item Description 1 R93, C89 HL Annulus Area 3-7/8"L x 1/8" W - Flexitallic 1 R93, C89 HL Annulus Area 1/8" diameter Metallic ball 4-1/4" L x 1/8" W x 0.020" thick Metallic 2 R85, C1 03 HL Annulus AreaShr Shard 4 Hot Leg Annulus 90 4" L x 1/8" W x 0.030" thick Flexitallic 2-1/2" L x 1/8" W x 0.030" thick 4 Hot Leg Annulus Flexitallic 5/8" L x 0.045" thick Flex piece - wire-4 Hot Leg Ann ulus like 4 Hot Leg Annulus 1/4"L x 1/8" metallic object E1-1 of E1-2
Steam Generator: Location Item Description 3/8"L x %"W x 0.060" thick non-metallic 4 Hot Leg Annulus object Request No. 3 Please clarify Table 2-1 since the "plannedexams" and "testsacquired"columns do not match. Please confirm all tubes were inspected and analyzed full length with a bobbin coil. Please clarify the number of tubes inspected with an arrayprobe in both the hot leg and cold leg in all four SGs.
Response No. 3 Each tube was examined full length with either a bobbin probe or a bobbin/array combo probe.
When a bobbin/array combo probe is used for these examinations, the bobbin data can be separated from the array data. This allows an analysis of the bobbin data, the array data, or both data sets per the planned scope requirement.
The difference between "planned exams" and "test acquired," specifically when N/A is listed, pertains to accounting of when the data was taken. For example, bobbin data of cold leg (C/L) straight rows 1 through 4, was taken while conducting array examination of C/L from support C07 to cold-leg-tube-end (CTE) using the bobbin/array combo probe. However, it was necessary during data acquisition to retrieve data above a C07 support to achieve full tube inspection to support the C/L straight rows 1 through 4. Similarly, peripheral tube array examinations of rows 5 and above from support H01 to the hot-leg-tube-end (HTE) and support C01 to CTE were fulfilled by data acquisition from the full length bobbin examination using the bobbin/array combo probe.
As stated in Reference 1, 4816 array coil inspections were performed. These include examinations of periphery tubes, tubes in the no-tubes lane, and tubes with prior bobbin indications.
References
- 1. TVA letter to NRC, "Unit 2 Cycle 19 - 180 Day Steam Generator Tube Inspection Report," dated December 1, 2014 E1-2 of E1-2