ML15153A152

From kanterella
Jump to navigation Jump to search

Nuclear Regulatory Commission Plan for the Audit of NextEra Energy Point Beach, Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 - Flooding for Point Beach Nuclear Plant, Units 1 and 2
ML15153A152
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/04/2015
From: Minarik A
Japan Lessons-Learned Division
To: Mccartney E
Point Beach
Minarik A, NRR/JLD, 415-6185
References
TAC MF6100, TAC MF6101
Download: ML15153A152 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 4, 2015 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF NEXTERA ENERGY POINT BEACH, LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. MF6100 AND MF6101)

Dear Mr. McCartney:

This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of NextEra Energy Point Beach, LLC's (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach).

This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.

The audit will provide the NRC staff with a better understanding of the Point Beach FHRR which was submitted March 12, 2015 (ADAMS Accession No. ML15071A413). Specifically, the audit will provide the NRC staff with a better understanding of the analyses of the flooding hazards presented in the Point Beach FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment.

The enclosed audit plan outlines the process that will allow the N RC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. Wayne Fromm of your staff.

E. McCartney If you have any questions, please contact me at (301) 415-6185 or by e-mail at Anthony.Minarik@nrc.gov.

Sincerely, Anthony J. Minarik, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

Audit Plan cc w/encl: Distribution via Listserv

NRC PLAN FOR THE AUDIT OF NEXTERA ENERGY POINT BEACH. LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR POINT BEACH NUCLEAR PLANT. UNITS 1AND2 BACKGROUND AND AUDIT BASIS By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR),

Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).

By letter dated March 12, 2015, NextEra Energy Point Beach, LLC (NextEra, the licensee) submitted the Flood Hazard Reevaluation Report (FHRR) for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach) (Agencywide Documents Access and Management System Accession No. ML15071A413). The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of NextEra to aid in its review of the licensee's FHRR.

REGULATORY AUDIT SCOPE AND METHODOLGY The areas of focus for the regulatory audit is the information contained in the Point Beach FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary.

Enclosure

INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.

NRC AUDIT TEAM Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Henry Jones NRC Technical Manager Mike Willingham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS The audit meetings will be coordinated with NextEra staff.

DELIVERABLES The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.

The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.

E. McCartney If you have any questions, please contact me at (301) 415-6185 or by e-mail at Anthony.Minarik@nrc.gov.

Sincerely, IRA by Tekia Govan for!

Anthony J. Minarik, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC JLD R/F RidsNRRJLD Resource RidsNrrDorllpl3-1 HJones, NRO MShams, NRR MWillingham, NRO AMinarik, NRR CCook, NRO ARivera, NRO KErwin, NRO MFranovich, NRR JBowen, NRR BHarvey,NRO RidsNrrPMPointBeachResource ADAMS Accession No.: ML15153A152 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MS hams AMinarik (TGovan for)

DATE 06/03/15 06/02/15 06/04/15 06/04/15 OFFICAL RECORD COPY