MONTHYEARML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML22264A3052022-09-30030 September 2022 Regulatory Audit in Support of Review of License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue-191 ML22216A2032022-08-11011 August 2022 Regulatory Audit in Support of Review of the Application to Adopt Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21214A0352021-08-16016 August 2021 Subsequent License Renewal Application (SLRA) Compiled Aging Management Audit Breakout Questions ML21070A2072021-03-15015 March 2021 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML21007A2602021-01-15015 January 2021 Subsequent License Renewal Application - Aging Management Audit Plan ML18046A9872018-02-21021 February 2018 Audit Plan and Setup of Online Reference Portal for License Amendment Request-10 CFR 50.69 (CAC Nos. MGO196 and MG0197; EPID L-2017-LLA-0284) ML17319A2272017-11-17017 November 2017 Audit Plan for License Amendment Request to Resolve Non-Conformances Relating to Containment Dome Truss ML17202G5912017-07-25025 July 2017 Audit Plan and Setup of Online Reference Portal for License Amendment Request - Risk-Informed Approach to Resolve Construction Truss Design Code Nonconformances ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML15153A1522015-06-0404 June 2015 Nuclear Regulatory Commission Plan for the Audit of NextEra Energy Point Beach, Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 - Flooding for Point Beach Nuclear Plant, Units 1 and 2 ML15117A6662015-05-0404 May 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 ML14356A0032015-02-10010 February 2015 Audit of Licensee Responses to the Expedited Seismic Evaluation Process to Support Implementation of Near-Term Task Force Recommendation 2.1, Seismic ML14127A2942014-05-0909 May 2014 Regulatory Audit in Support of License Amendment Request to Implement NFPA 805, as Incorporated Into 10 CFR 50.48(c) ML14083A6202014-03-26026 March 2014 Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 ML13130A0452013-05-17017 May 2013 Seismic Walkdown Audit Plan 2023-08-03
[Table view] Category:Letter
MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23352A2752024-01-23023 January 2024 Issuance of Amendment Nos. 274 and 276 Regarding Revision to Technical Specification 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-174, Subsequent License Renewal Application - Third Annual Update2023-12-13013 December 2023 Subsequent License Renewal Application - Third Annual Update L-2023-176, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-159, Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 ML23279A0672023-11-0909 November 2023 Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 ML23208A2262023-08-28028 August 2023 Exemption from the Requirements of 10 CFR 50,46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors (EPID L-2022-LLE-0026) - Letter ML23208A0952023-08-28028 August 2023 Issuance of Amendment Nos. 273 and 275 Regarding Revising Licensing Basis to Address Generic Safety Issue-191 and Respond to Generic Letter 2004-02 Using a Risk Informed Approach IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23160A0642023-08-21021 August 2023 Issuance of Amendment Nos. 272 and 274 Regarding Revision to Use Beacon Power Distribution Monitoring System L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-089, Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections2023-07-24024 July 2023 Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-2023-088, 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval2023-06-27027 June 2023 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval ML23171B1062023-06-21021 June 2023 Info Meeting with a Question and Answer Session to Discuss NRC 2022 EOC Plant Performance Assessment of Ptbh, Units 1 and 2 ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 L-2023-075, Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-022023-06-0909 June 2023 Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-02 L-2023-073, Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response2023-06-0101 June 2023 Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response ML23103A1332023-06-0101 June 2023 Issuance of Amendment Nos. 271 and 273 Regarding Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 ML23114A1222023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-2023-058, 2022 Annual Monitoring Report2023-04-10010 April 2023 2022 Annual Monitoring Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications 2024-02-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 4, 2015 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF NEXTERA ENERGY POINT BEACH, LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. MF6100 AND MF6101)
Dear Mr. McCartney:
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of NextEra Energy Point Beach, LLC's (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach).
This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.
The audit will provide the NRC staff with a better understanding of the Point Beach FHRR which was submitted March 12, 2015 (ADAMS Accession No. ML15071A413). Specifically, the audit will provide the NRC staff with a better understanding of the analyses of the flooding hazards presented in the Point Beach FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment.
The enclosed audit plan outlines the process that will allow the N RC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. Wayne Fromm of your staff.
E. McCartney If you have any questions, please contact me at (301) 415-6185 or by e-mail at Anthony.Minarik@nrc.gov.
Sincerely, Anthony J. Minarik, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv
NRC PLAN FOR THE AUDIT OF NEXTERA ENERGY POINT BEACH. LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR POINT BEACH NUCLEAR PLANT. UNITS 1AND2 BACKGROUND AND AUDIT BASIS By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
By letter dated March 12, 2015, NextEra Energy Point Beach, LLC (NextEra, the licensee) submitted the Flood Hazard Reevaluation Report (FHRR) for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach) (Agencywide Documents Access and Management System Accession No. ML15071A413). The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of NextEra to aid in its review of the licensee's FHRR.
REGULATORY AUDIT SCOPE AND METHODOLGY The areas of focus for the regulatory audit is the information contained in the Point Beach FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary.
Enclosure
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.
NRC AUDIT TEAM Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Henry Jones NRC Technical Manager Mike Willingham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS The audit meetings will be coordinated with NextEra staff.
DELIVERABLES The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.
E. McCartney If you have any questions, please contact me at (301) 415-6185 or by e-mail at Anthony.Minarik@nrc.gov.
Sincerely, IRA by Tekia Govan for!
Anthony J. Minarik, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC JLD R/F RidsNRRJLD Resource RidsNrrDorllpl3-1 HJones, NRO MShams, NRR MWillingham, NRO AMinarik, NRR CCook, NRO ARivera, NRO KErwin, NRO MFranovich, NRR JBowen, NRR BHarvey,NRO RidsNrrPMPointBeachResource ADAMS Accession No.: ML15153A152 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MS hams AMinarik (TGovan for)
DATE 06/03/15 06/02/15 06/04/15 06/04/15 OFFICAL RECORD COPY