MONTHYEARML15147A5912015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of Florida Power and Light Company'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for St. Lucie Plant, Units 1 and 2 Project stage: Other ML15224B4492015-09-0303 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation Project stage: Other ML15236A0762015-09-0303 September 2015 Enclosure, Revised St Lucie Tables-LQ-W Project stage: Other ML15273A2092015-10-0101 October 2015 Nuclear Regulatory Commission Report for the Audit of Florida Power and Light Company'S Flood Hazard Reevaluation Report Submittals Relating to the Near-Term Task Force Recommendation 2.1-Flooding for St. Lucie Plant Units 1 and 2 Project stage: Other 2015-06-01
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML22039A1962022-02-0909 February 2022 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16036A3072016-02-18018 February 2016 Regulatory Audit Plan in Support of the License Amendment Requests to Implement Risk-Informed Technical Specifications Initiative 4b ML15147A5912015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of Florida Power and Light Company'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for St. Lucie Plant, Units 1 and 2 2023-08-03
[Table view] Category:Letter
MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23332A1772023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 ML23270B8882023-10-23023 October 2023 Regulatory Audit Summary Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structure, Systems, and Components for Nuclear Power Reactors EPID L-2022-LLA-0182 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A1102023-10-0202 October 2023 License Amendment Request Revision 2 for the Technical Specifications Conversion to NUREG-1432, Revision 5 L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 ML23219A0042023-09-0101 September 2023 Transmittal Letter - Safety Evaluation Related to the SLRA of St. Lucie Plant, Units 1and 2, Revision 1 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23212B2652023-07-27027 July 2023 Operator Licensing Written Examination Approval 05000335/2023301 and 05000389/2023301 L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches ML23200A1232023-07-21021 July 2023 Transmittal Letter for the St. Lucie SLRA Review L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) ML23184A0352023-06-30030 June 2023 Notification of St. Lucie Units 1 & 2 Focused Engineering Inspection (FEI) 05000335/2023010 and 05000389/2023010 and Initial Information Request L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report 2024-01-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 1, 2015 Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420
SUBJECT:
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF FLORIDA POWER AND LIGHT COMPANY'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ST. LUCIE PLANT, UNITS 1AND2 (TAC NO. MF6113 AND MF6114)
Dear Mr. Nazar,
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of Florida Power and Light Company's (the licensee) supporting calculations for the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for St. Lucie Plant, Units 1 and 2 (St. Lucie). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.
The audit will provide the NRC staff with a better understanding of the St. Lucie FHRR which was submitted March 10, 2015 (ADAMS Accession No. ML15083A306). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the St. Lucie FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment.
The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. Ken Frehafer of your staff.
M. Nazar If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, J1uQV.~
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv
NRC PLAN FOR THE AUDIT OF FLORIDA POWER AND LIGHT COMPANY'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ST. LUCIE PLANT. UNITS 1 AND 2 BACKGROUND AND AUDIT BASIS:
By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1O of the Code of Federal Regulations (1 O CFR),
Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
By letter dated March 12, 2015, Florida Power and Light's (FPL, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for St. Lucie Plant, Units 1 and 2 (St. Lucie)
(Agencywide Documents Access and Management System Accession No. ML15083A306).
The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of FPL to aid in its review of the licensee's FHRR.
REGULATORY AUDIT SCOPE AND METHODOLGY:
The areas of focus for the regulatory audit is the information contained in the St. Lucie FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary.
Enclosure
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT:
The information required for the audit is the licensee's models and supporting calculations as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.
NRC AUDIT TEAM:
Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Henry Jones NRC Technical Manaoer Laura Quinn-Willinoham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS:
The audit meetings will be coordinated with FPL staff.
DELIVERABLES:
The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.
M. Nazar If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, IRA/
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC JLD R/F RidsNRRJLD Resource HJones, NRO MShams, NRR LQuinn-Willingham, NRO TGovan, NRR CCook, NRO ARivera, NRO KErwin, NRO MFranovich, NRR JBowen, NRR RidsNrrDorlLPl2-2 BHarvey,NRO RidsNrrPMStlucieResource ADAMS Accession No.: ML15147A591 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MShams TGovan DATE 05/28/15 05/27/15 05/31/15 06/01 /15 OFFICAL RECORD COPY