MONTHYEARML20023A9942020-01-24024 January 2020 Audit Plan and Setup of Online Reference Portal for License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML17220A3282017-08-10010 August 2017 Nuclear Regulatory Commission Audits of Licensee Responses to Phase 2 of Order EA-13-109 to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ML17177A4462017-07-0606 July 2017 Audit Plan for Licensee Responses Concerning Seismic Hazard Reevaluations Related to Request for Information -(50.54(F) Letter) Regarding Recommendation 2.1 of the Near-Term Task Force ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16265A4492016-09-28028 September 2016 Regulatory Audit Plan for October 3-6, 2016, at General Electric - Hitachi in Support of License Amendment Request to Upgrade Hope Creek Generating Station'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring ML16231A2152016-09-16016 September 2016 Draft Audit Plan for August 16, 2016 Public Teleconference Between PSEG LLC and the Nuclear Regulatory Commission Concerning Hope Creek Generating Station (HCGS) Power Range Neutron Monitoring (Prnm) System Digital Upgrade License Amendment ML16005A4212016-01-0707 January 2016 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML15146A2862015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of PSEG Nuclear Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Hope Creek Generating Station ML14083A6202014-03-26026 March 2014 Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 ML13127A1162013-05-20020 May 2013 Plan for the Regulatory Audit Regarding Flooding Walkdowns to Support Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident 2020-01-24
[Table view] Category:Letter
MONTHYEARLR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums IR 05000272/20244032024-03-20020 March 2024 and Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations 2024-08-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 1, 2015 Mr. Robert Braun President and Chief Nuclear Officer PSEG Nuclear LLC-N09 P. 0. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR HOPE CREEK GENERATING STATION (TAC NO.
MF3789)
Dear Mr. Braun,
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of PSEG Nuclear LLC's (the licensee) supporting calculations for the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Hope Creek Generating Station (Hope Creek). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits, dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.
The audit will provide the NRC staff with a better understanding of the Hope Creek FHRR which was submitted March 12, 2014 (ADAMS Accession No. ML14071A511). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the Hope Creek FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment.
The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. William McTigue of your staff.
R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, JL~v~
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv
NRC PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR HOPE CREEK GENERATING STATION BACKGROUND AND AUDIT BASIS:
By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactorlicensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
By letter dated March 12, 2014, PSEG Nuclear LLC (PSEG, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Hope Creek Generating Station (Hope Creek)
(Agencywide Documents Access and Management System Accession No. ML14071A511).
The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of PSEG to aid in its review of the licensee's FHRR.
REGULATORY AUDIT SCOPE AND METHODOLGY:
The areas of focus for the regulatory audit is the information contained in the Hope Creek FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary.
Enclosure
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT:
The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.
NRC AUDIT TEAM:
Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Kevin Quinlan NRC Technical Manager Mike Willinaham NRC Technical Support Various Contractors Department of Energy National Laboratorv LOGISTICS:
The audit meetings will be coordinated with PSEG staff.
DELIVERABLES:
The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.
R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, IRA/
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC JLD R/F RidsNRRJLD Resource KQuinlan, NRR MShams, NRR MWillingham, NRO TGovan, NRR CCook, NRO ARivera, NRO KErwin, NRO MFranovich, NRR JBowen, NRR RidsNrrDorllpl1-2 BHarvey,NRR RidsNrrPMHopeCreekResource ADAMS Accession No.: ML15146A286 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MShams TGovan DATE 05/27/15 05/27/15 05/31/15 06/01 /15 OFFICAL RECORD COPY