Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 20555-0001 Mr. Bryan C. Hanson Senior Vice President May 8, 2015 Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO)

Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - PROJECT MANAGER REASSIGNMENT

Dear Mr. Hanson:

This letter is to inform you that effective May 17, 2015, Ms. Eva Brown will be reassigned as the U.S. Nuclear Regulatory Commission's Licensing Senior Project Manager for Quad Cities Nuclear Power Station, Units 1 and 2. Ms. Brown may be reached at 301-415-2315 or via e-mail at Eva.Brown@nrc.gov.

Docket Nos. 50-254 and 50-265 cc. Distribution via ListServ Sincerely, Travis L. Tate, Chief Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulations

ML15125A362 OFFICE NRR/LPL3-2/PM NRR/LPL3-2/LA NAME EBrown SRohrer DATE 5/6/15 5/6/15 Sincerely, IRA/

Travis L. Tate, Chief Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulations RidsAcrsAcnw_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl3-2 Resource NRR/LPL3-2/BC TT ate 51 8/15