1 IPRenewal NPEmails From:
Louie, Richard [rlouie@entergy.com]
Sent:
Monday, May 04, 2015 11:35 AM To:
Wentzel, Michael
Subject:
RE: NUREG-1930, Sup. 2 Attachments:
ML14288A608.pdf
- Mike, Ill check with the project regarding the paper copies and get back with you.
Question, the supplements are to NUREG-1930. I did not realize that they got their own NUREG numbers.
Rich From: Wentzel, Michael [1]
Sent: Monday, May 04, 2015 8:48 AM To: Louie, Richard
Subject:
NUREG-1930, Sup. 2
- Rich, Now that we are done with the ACRS, I am going through the process of getting SER Supplement 2 published as a NUREG. Would Entergy like to have any paper copies of the NUREG and, if so, how many?
- Thanks, Mike Michael Wentzel Project Manager NRR/DLR/RPB2 (301) 415-6459 michael.wentzel@nrc.gov
Hearing Identifier:
IndianPointUnits2and3NonPublic_EX Email Number:
5137 Mail Envelope Properties (CB159DC717B797428E92782CE3B5F40B0F154735)
Subject:
RE: NUREG-1930, Sup. 2 Sent Date:
5/4/2015 11:35:12 AM Received Date:
5/4/2015 11:35:16 AM From:
Louie, Richard Created By:
rlouie@entergy.com Recipients:
"Wentzel, Michael" <Michael.Wentzel@nrc.gov>
Tracking Status: None Post Office:
JDCXMETSP003.etrsouth.corp.entergy.com Files Size Date & Time MESSAGE 761 5/4/2015 11:35:16 AM ML14288A608.pdf 142962 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 6, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
SUPPLEMENT 2 TO THE SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3
Dear Sir or Madam:
By letter dated April 23, 2007, as supplemented by letters dated May 3, and June 21, 2007, Entergy Nuclear Operations, Inc., (Entergy) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application to renew the Indian Point Nuclear Generating Unit Nos. 2 and 3, (IP2 and IP3) operating licenses for an additional 20 years beyond the expirations of the initial operating licenses on September 28, 2013, for IP2, and on December 12, 2015, for IP3.
The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54), Requirements for Renewal of Operating Licenses for Nuclear Power Plants. The NRC staff determined that the LRA was complete and acceptable for docketing on July 25, 2007.
The NRC staff reviewed the LRA for compliance with the requirements of 10 CFR Part 54, and issued its findings in NUREG-1930, Safety Evaluation Report [SER] Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3, on August 11, 2009.
The SER was published in November 2009, following the staff's receipt of comments from the Advisory Committee on Reactor Safeguards (ACRS). In August 2011, the staff issued Supplement 1 to NUREG-1930, which documented the staffs review of supplemental information provided by Entergy since the issuance of the SER as documented in NUREG-1930.
The enclosed Supplement 2 to the SER documents the staff's review of additional information provided by Entergy in annual updates, LRA amendments, and responses to staff requests for additional information since the issuance of Supplement 1 to the SER.
If you have any questions regarding this matter, please contact Kimberly Green at 301-415-1627, or by e-mail at kimberly.green@nrc.gov.
Sincerely,
/RA/
Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
As stated cc w/encl: Listserv
- concurred by email OFFICE Tech Editor LA:DLR PM:DLR:RASB BC:DLR:RPB1 BC:DLR:RARB NAME QTE
- YEdmonds KGreen
- YDiaz-Sanabria
- DMorey DATE 10/8/14 10/22/14 10/29/14 10/27/14 10/24/14 OFFICE BC:DLR:RASB BC:DE:EVIB OGC D:DE D:DLR NAME
- MMarshall
- SRosenberg STurk JLubinski CMiller DATE 10/14/14 10/17/14/
10/28/14 10/29/14 11/6/14
Letter to Entergy Nuclear Operations, Inc. from Chris Miller dated November 6, 2014
SUBJECT:
SUPPLEMENT 2 TO THE SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF INDIAN POINT NUCLEAR GENERATING UNIT NOS.
2 AND 3 DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC via Listserv RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDeEvib Resource RidsRgn1MailCenter RidsNrrPMIndianPoint RidsOgcMailCenter Resource YDiaz MGray, RI KGreen ABurritt, RI JPoehler DonaldJackson, RI SRosenberg MModes, RI AHiser NSheehan, RI OPA STurk, OGC DScrenci, RI OPA BMizuno, OGC DTifft, RI DRoth, OGC NMcNamara, RI BHarris, OGC GNewman, RI SBurnell, OPA JSStewart, RI DMcIntyre, OPA AmiPatel, RI JWeil, OCA