Letter Sequence RAI |
---|
TAC:MF5184, Deletion of E BAR Definition and Revision to RCS Specific Activity Tech Spec (Open) TAC:MF5185, Deletion of E BAR Definition and Revision to RCS Specific Activity Tech Spec (Open) |
|
MONTHYEARAEP-NRC-2014-65, License Amendment Request to Adopt TSTF-490, Rev. 0, Deletion of E Bar Definition and Revision to Reactor Coolant System Specific Activity Technical Specification, and Implement Full-Scope Alternative Source Term2014-11-14014 November 2014 License Amendment Request to Adopt TSTF-490, Rev. 0, Deletion of E Bar Definition and Revision to Reactor Coolant System Specific Activity Technical Specification, and Implement Full-Scope Alternative Source Term Project stage: Request ML14365A0122014-12-30030 December 2014 NRR E-mail Capture - LIC-109 Acceptance Review of D.C.Cook Units 1 and 2 LAR to Adopt TSTF-490, Revision 0, and Implement full-scope AST - MF5184 and MF5185 - Unacceptable with Opportunity to Supplement Project stage: Acceptance Review ML14363A4912015-01-16016 January 2015 DC Cook Nuclear Plant, Units 1 and 2 - Supplemental Information Needed for Acceptance of Requested Licensing Action to Adopt TSTF-490, Rev.0, Deletion of E-Bar Definition and Revision to Reactor Coolant System Specific Activity Technical Sp Project stage: Acceptance Review AEP-NRC-2015-19, Supplemental Information for the License Amendment Request to Adopt TSTF-490, Rev 0, Deletion of E Bar Definition and Revision to Reactor Coolant System Specific Activity Technical Specification and Implement Full-Scope.2015-02-12012 February 2015 Supplemental Information for the License Amendment Request to Adopt TSTF-490, Rev 0, Deletion of E Bar Definition and Revision to Reactor Coolant System Specific Activity Technical Specification and Implement Full-Scope. Project stage: Supplement ML15056A1632015-03-0303 March 2015 DC Cook, Units 1 & 2 - Acceptance of Requested Licensing Action to Adopt TSTF-490, REV.0, Deletion of E-Bar Definition & Revision to Reactor Coolant System Specific Activity Technical Specification & Implement Full-Scope Alternative Source Project stage: Acceptance Review ML15112A5052015-04-21021 April 2015 NRR E-mail Capture - D.C. Cook Units 1 and 2 Esgb RAI Concerning LAR to Adopt TSTF-490 and Implement FULL-SCOPE AST (TAC Nos. MF5184 and MF5185) Project stage: RAI ML15195A6982015-07-14014 July 2015 NRR E-mail Capture - D.C. Cook Units 1 and 2 - Srxb RAI Concerning LAR to Adopt TSTF-490 and Implement FULL-SCOPE AST (TAC Nos. MF5184 and MF5185) Project stage: RAI ML15216A2402015-07-30030 July 2015 NRR E-mail Capture - D.C. Cook Nuclear Plant, Units 1 and 2 - Draft Request for Additional Information TSTF-490 and AST Project stage: Draft RAI AEP-NRC-2015-75, Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-24024 August 2015 Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term Project stage: Request AEP-NRC-2015-80, Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-28028 August 2015 Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term Project stage: Request ML15259A5772015-09-15015 September 2015 NRR E-mail Capture - D.C. Cook Units 1 and 2 - Arcb RAI Concerning LAR to Adopt TSTF-490 and Implement FULL-SCOPE AST (MF5184 and MF5185) Project stage: RAI ML15323A4342015-11-16016 November 2015 Response (Part 1) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term Project stage: Request AEP-NRC-2016-24, Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2016-02-19019 February 2016 Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term Project stage: Request 2015-04-21
[Table View] |
Similar Documents at Cook |
---|
Category:E-Mail
MONTHYEARML24221A4172024-08-0101 August 2024 DC Cook 2024 PI&R Inspection Request for Information ML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24156A0052024-05-22022 May 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Reserve Feed Enclosure ML24103A1392024-04-12012 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Adoption of 10 CFR 50.69 ML24096A1132024-04-0505 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Delay in Issuance of License Amendment Regarding Neutron Flux Instrumentation ML24093A0582024-04-0202 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Request Regarding Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML23361A1022023-12-21021 December 2023 Security Rule Exemption Request - ISFSI Docket No. Reference ML23321A1222023-11-17017 November 2023 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML23052A1502023-02-21021 February 2023 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Neutron Flux Instrumentation ML22307A2532022-11-0303 November 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Verbal Authorization of Relief Request ISIR-5-06 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML22122A0902022-04-29029 April 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-554, Revision 1 ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML21341A6252021-12-0707 December 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-577, Revision 1 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21236A0262021-08-23023 August 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21113A2812021-04-23023 April 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Containment Water Level Instrumentation ML21089A0222021-03-24024 March 2021 DC Cook Power Operated Valves (POV) Preliminary Request for Information ML21082A0262021-03-22022 March 2021 Acceptance of Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML21008A4742021-01-0808 January 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Extension Containment Type a ILRT ML20366A1012020-12-31031 December 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Deferral of Steam Generator Inspection ML20316A0152020-11-0606 November 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML20318A0202020-10-16016 October 2020 NRR E-mail Capture - Regarding Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A7122020-10-15015 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20290A4252020-10-15015 October 2020 Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20318A0192020-10-15015 October 2020 NRR E-mail Capture - (External_Sender) Supplemental Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A1192020-10-0909 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request for Alternative to N-729-4 for RPV Head Visual Examination ML20318A0182020-10-0909 October 2020 NRR E-mail Capture - (External_Sender) Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20149K6272020-05-28028 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment and Exemptions Regarding UFSAR 10 CFR 50.71(e)(4) Update Schedule (Epids: L-2020-LLA-0100, L-2020-LLE-0052, L-2020-LLE-0053) ML20149K4332020-05-26026 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-567, Revision 1 ML20141L6062020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-541, Revision 2 ML20141L8112020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request Regarding Impracticality for Inservice Inspection for Certain Welds ML20136A5162020-05-15015 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-412, Revision 3 ML20133J9662020-05-11011 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19345F9382019-12-0909 December 2019 D.C. Cook 50.54(f) SPRA Submittal - Completeness Review Done and Path Forward ML19333B8042019-11-29029 November 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-569 (L-2019-LLA-0248) ML19309F9212019-11-0505 November 2019 Request for Eportal Access for Audit Review of the DC Cook SPRA Supporting Documents ML19270E7372019-09-26026 September 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-421, Reactor Coolant Pump Flywheel Inspection Program ML19207A4642019-07-26026 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Delete Diesel Generator Load Test Resistor Banks ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19175A3032019-06-24024 June 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS ML19092A4802019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-563 ML19092A4792019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Address Issues Identified in Westinghouse Document NSAL-15-1 2024-08-01
[Table view] |
Text
NRR-PMDAPEm Resource From: Dietrich, Allison Sent: Tuesday, April 21, 2015 3:37 PM To: hletheridge@aep.com Cc: dmburgoyne@aep.com; Obodoako, Aloysius; Pelton, David; Kulesa, Gloria; Terry L Curtiss (tlcurtiss@aep.com)
Subject:
D.C. COOK UNITS 1 AND 2 - ESGB RAI CONCERNING LAR TO ADOPT TSTF-490 AND IMPLEMENT FULL-SCOPE AST (TAC NOS. MF5184 AND MF5185)
Attachments: ESGB RAI regarding Alternate Source Term MF5184 MF5185.docx By letter dated November 14, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14324A209), as supplemented by letter dated February 12, 2015 (ADAMS Accession No. ML14363A491), Indiana Michigan Power Company (I&M, the licensee) submitted a license amendment request for the Donald C. Cook Nuclear Plant (CNP), Units 1 and 2. The proposed amendment consists of adoption of Technical Specifications Task Force (TSTF)-
490, Revision 0, and implementation of a full scope alternate source term radiological analysis methodology.
The U.S. Nuclear Regulatory Commission (NRC) staff in the Steam Generator Tube Integrity and Chemical Engineering Branch (ESGB) of the Office of Nuclear Reactor Regulation is currently reviewing your submittal, as supplemented. The staff has determined that additional information is needed in order to complete the review, as described in the attached Request for Additional Information (RAI). The draft RAI was sent to I&M via electronic mail on April 8, 2015. A clarification telephone conference was held on April 21, 2015. Based on our discussion, we understand that a response to the RAI will be provided by July 22, 2015.
Please let me know if you have any questions or concerns.
Sincerely, Allison W. Dietrich, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301-415-2846 1
Hearing Identifier: NRR_PMDA Email Number: 2020 Mail Envelope Properties (Allison.Dietrich@nrc.gov20150421153600)
Subject:
D.C. COOK UNITS 1 AND 2 - ESGB RAI CONCERNING LAR TO ADOPT TSTF-490 AND IMPLEMENT FULL-SCOPE AST (TAC NOS. MF5184 AND MF5185)
Sent Date: 4/21/2015 3:36:56 PM Received Date: 4/21/2015 3:36:00 PM From: Dietrich, Allison Created By: Allison.Dietrich@nrc.gov Recipients:
"dmburgoyne@aep.com" <dmburgoyne@aep.com>
Tracking Status: None "Obodoako, Aloysius" <Aloysius.Obodoako@nrc.gov>
Tracking Status: None "Pelton, David" <David.Pelton@nrc.gov>
Tracking Status: None "Kulesa, Gloria" <Gloria.Kulesa@nrc.gov>
Tracking Status: None "Terry L Curtiss (tlcurtiss@aep.com)" <tlcurtiss@aep.com>
Tracking Status: None "hletheridge@aep.com" <hletheridge@aep.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1467 4/21/2015 3:36:00 PM ESGB RAI regarding Alternate Source Term MF5184 MF5185.docx 20828 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUEST FOR ADDITIONAL INFORMATION REGARDING ADOPTION OF TSTF-490, REVISION 0 AND IMPLEMENTATION OF FULL-SCOPE ALTERNATE SOURCE TERM DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-315 AND 50-316 TAC NOS.MF5184 AND MF5185 RAI-ESGB-1 Identify all sources of post loss of coolant accident (LOCA) strong acid generation in containment and time-dependent or bounding values of strong acid concentrations in the sump for a period of 30 days post-LOCA.
- a. Provide the amounts of strong acids used in the calculations and the decrease of sump water pH due to strong acids generation.
RAI-ESGB-2 Describe the analysis used, including assumptions and inputs, to determine the pH in the sump water during a period of 30 days post-LOCA. Include detailed calculations of time-dependent or bounding pH values in the sump during a 30-day period post-LOCA to demonstrate that the pH remains greater than 7 throughout this time period.
ENCLOSURE