ML15112A101
ML15112A101 | |
Person / Time | |
---|---|
Site: | Indian Point |
Issue date: | 04/21/2015 |
From: | Office of Nuclear Reactor Regulation |
To: | |
References | |
Download: ML15112A101 (34) | |
Text
IPRenewal NPEmails From: Green, Kimberly Sent: Tuesday, April 21, 2015 3:57 PM To: Louie, Richard (rlouie@entergy.com)
Subject:
NRC's Draft ACRS Slides Attachments: IP ACRS SubCommittee 4-23 Briefing 04-22-15.pdf
- Rich, Attached is our current draft ACRS presentation.
Kim 1
Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 5085 Mail Envelope Properties (Kimberly.Green@nrc.gov20150421155600)
Subject:
NRC's Draft ACRS Slides Sent Date: 4/21/2015 3:56:36 PM Received Date: 4/21/2015 3:56:00 PM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients:
"Louie, Richard (rlouie@entergy.com)" <rlouie@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 82 4/21/2015 3:56:00 PM IP ACRS SubCommittee 4-23 Briefing 04-22-15.pdf 503703 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Advisory Committee on Reactor Safeguards License Renewal Subcommittee Indian Point Nuclear Generating Units 2 and 3 Status Briefing April 23, 2015 Division of License Renewal Office of Nuclear Reactor Regulation
Presentation Outline
- History of LRA and Staff Review
- Timely Renewal Activities for Indian Point 2 (IP2)
- SER Supplement 2
- Staffs Ongoing Review 1
- License Renewal Application (LRA) submitted April 23, 2007
- Supplemented May 3 and June 21, 2007
- 16 amendments to LRA
- Operating License Expiration Dates
- IP2: September 28, 2013
- IP3: December 12, 2015 2
Safety Evaluation Report
- NUREG-1930 published November 2009
- Staffs initial evaluation and findings
- ACRS letter
- NUREG-1930, Supplement 1 published October 2011
- Changes to LRA since August 2009
- Operating experience since GALL Report, Revision 1
- NUREG-1930, Supplement 2 issued November 2014
- Changes to LRA since August 2011
- Reactor Vessel Internals inspection plan and program 3
Timely Renewal
- Administrative Procedure Act
- 10 CFR 2.109, Effect of timely renewal application
- At least 5 years before expiration of existing license
- Sufficient application
- Existing license will not be deemed to have expired until the application has been finally determined
- Continue to meet all of the regulations and license conditions of the existing license 4
Timely Renewal (cont.)
- Licensees Voluntary Actions
- Implement IP2 commitments
- Update IP2 UFSAR
- NRCs Activities
- Acknowledgement letter
- Conducted Temporary Instruction (TI) 2516 inspections 5
License Renewal Inspections Mel Gray, Branch Chief, Engineering Branch 1, Division of Reactor Safety Michael Modes, Senior Inspector Region I 6
License Renewal Inspection Results
- TI 2516/001, Review of License Renewal Activities
- Specific to applicants in timely renewal
- Satisfies completion of IP 71003 inspection requirements
- Conducted 3 license renewal inspections
- March 2012: 4 commitments implemented; 2 commitments needed further assessment
- May 2013: 30 commitments implemented; 11 commitments needed further assessment
- September 2013: 10 commitments implemented
- No findings identified
- Fall 2015: IP3 Commitment Inspection scheduled 7
Reactor Oversight Process (IMC 0305)
Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response 8
Indian Point Historical Performance IP2 & IP3 2009-2014 IP3 July 2009 - June 2010 (White PI)
Licensee Regulatory Degraded Multiple Repetitive Unacceptable Response Response Cornerstone Degraded Performance Cornerstone All Inputs are 1 or 2 White 2 White or 1 Multiple Yellow Overall Green; Inputs; Yellow Input; Inputs or 1 Red Unacceptable Cornerstone Cornerstone Cornerstone Input; Cornerstone Performance; Objectives Objectives Objectives Met w/ Objectives Met w/ Plants not Fully Met Fully Met Moderate Significant permitted to Degradation in Degradation in Operate w/in this Safety Safety Performance Column; Performance Unacceptable Margin to Safety 9
Baseline Inspection Results
- Inspection Results for CY2014
- Indian Point Unit 2 and 3 performance placed the units in the Licensee Response Column of the Action matrix for all of CY2014
- Approximately 8300 inspection hours
- All performance indicators in the Green band
- 13 findings of very low safety significance (Green) 10
SER Supplement 2
- Supplement 2 to the SER issued November 6, 2014
- Reactor Vessel Internals Inspection Plan and Program
- Annual Updates in 2011, 2012, and 2013
- Buried Piping and Tanks Inspection Program
- Other AMPs
- No changes to time-limited aging analyses
- Conclusion is unchanged
- List of Commitments in Appendix A
- IP2: completed with exception of three
- IP3: will complete by December 12, 2015 with exception of two 11
RVI Program - Background
- 4/30/2007 - IP2 and IP3 LRA submitted
- Consistent with GALL Report, Rev. 1
- LRA Commitment 30 to implement industry program
- 8/11/2009 - NRC issued SER related to license renewal of IP2 and IP3
- 7/14/2010 - Applicant submitted LRA Amendment 9 -
AMP for RVI based on MRP-227, Rev. 0
RVI Program- Background (cont.)
- 9/28/2011 - Applicant submitted RVI Inspection Plan based on MRP-227, Rev. 0 and SE, Rev. 0, meeting Commitment 30 date
- 2/3/2012 - NRC endorsed MRP-227-A for referencing in licensing applications related to PWR RVI inspection
- 2/17/2012 - Applicant submitted update to RVI Inspection Plan consistent with MRP-227-A + updated AMP
- 11/6/2014 - RVI Inspection Plan for IP2 & IP3 first approved by NRC staff for a Westinghouse-design reactor 13
MRP-227-A Process
- Generic components for each PWR vendor were evaluated
- Each component screened for eight aging mechanisms
- Screened-in components put through Failure Modes, Effects and Consequences Analysis (FMECA)
- Risk rankings developed based on FMECA
- FMECA results, plus some analytical work, used to develop final inspection recommendations
- All components assigned to one of four inspection categories 14
Reactor Vessel Internals for Typical Westinghouse Reactor 15
MRP-227-A Component Categorization
- Primary - Highest susceptibility category, will be inspected (lead components)
- Expansion - High to moderate susceptibility with some tolerance for degradation. Not lead component.
Inspected if degradation found in lead components.
- No Additional Measures - Low susceptibility and/or no functional impact of failure. No augmented inspections recommended, but may be inspected under ASME Code,Section XI as applicable.
- Existing Program - Susceptible to aging effects, but existing programs such as ASME,Section XI Inservice Inspection deemed adequate to detect aging 16
IP2 and IP3 RVI Program Staff Review
- Staff review concentrated on:
- AMP Elements
- Applicant/Licensee Action Items (A/LAIs)
- AMP elements met recommendations of LR-ISG-2011-04, therefore acceptable.
- ISG updated GALL, Rev. 2 guidance consistent with MRP-227-A
- A/LAIs 1, 2, 3, 5, 7 and 8 applicable to Westinghouse plant such as IP2 and IP3 17
RVI Program A/LAI 1: Plant-Specific Applicability
- A/LAI 1
- Applicant must assess its plant design and operating history and demonstrate MRP-227-A is applicable
- Ensure operating conditions assumed for generic components during development of MRP-227-A are valid for the specific plant
- MRP-227-A basic applicability criteria:
- Base load operation
- Low leakage core before 30 years
- No plant-specific modifications
- Generic staff concerns that basic criteria were not sufficient led to MRP letter 2013-025 additional criteria:
- Core design (relates to RVI fluence and temperature assumptions)
- Fabrication - no cold work (relates to SCC susceptibility) 18
RVI Program A/LAI 1 - Plant-Specific Applicability (cont.)
- Applicant Evaluation
- Applicant showed IP2 and IP3 meet basic and additional criteria
- Staff Finding
- MRP-227-A is applicable to IP2 and IP3
- Applicant adequately addressed A/LAI 1 19
RVI Program A/LAI 2 - RVI Components within Scope of License Renewal
- A/LAI 2
- Recommends applicants ensure that all RVI components within scope of LR are covered by generic components in MRP-191.
If not, modify plant-specific program to address the components not covered.
- Applicant Evaluation
- Determined all components
- Have an equivalent generic component, or
- Have an equivalent generic component, but different material
- Plant-specific screening and FMECA for components with different materials - no differences in aging management
- Staff Finding
- Applicant adequately evaluated differences in material, thus applicant adequately addressed A/LAI 2.
20
RVI Program A/LAI 3: Plant-Specific Programs
- A/LAI 3
- Recommends a justification of the adequacy of plant-specific program, or modify program to manage aging for the PEO
- Applicant Evaluation
- Split pins are only component with plant-specific program for IP2 & IP3
- IP3 split pins previously replaced with SCC-resistant material (cold-worked Type 316 stainless steel)
- Commitment 50 to replace IP2 split pins during 2016 RFO
- Applicant justified replacement date with a statistical analysis of remaining life
- Staff Finding
- Applicant adequately addressed A/LAI 3 based on replacement of split pins with SCC-resistant material (IP3), or commitment to do so (IP2) 21
Split Pin Location Lower Part of Control Rod Guide Tube Assembly Split Pin Location 22
RVI Program A/LAI 5: Application of Physical Measurements
- A/LAI 5
- Recommends licensees identify plant-specific acceptance criteria to be used when performing physical measurements
- Applicant Evaluation
- Applicable to IP hold-down springs
- Applicant explained how measurements evaluated
- Linear interpolation between initial and 60-year minimum height to determine acceptable height at first measurement
- If spring height unacceptable, a follow-up measurement will be performed, or spring replaced
- Staff Finding
- Applicant clarified how acceptable spring height is determined
- Staff also performed audit of detailed spring height calculation
- Applicant adequately addressed A/LAI 5 23
Hold-Down Spring 24
RVI Program A/LAI 7: Plant-specific Evaluation of Cast Austenitic Stainless Steel
- A/LAI 7
- Licensees must demonstrate functionality of CASS components through end of life considering loss of fracture toughness due to thermal embrittlement (TE ) and irradiation embrittlement (IE)
- Applicant Evaluation
- Applicable to lower support column caps at IP
- Initially made Commitment 47 to provide detailed analysis prior to PEO
- In response to staff RAIs, the applicant:
- Performed screening for column caps - TE screened out
- Showed pre-existing flaws in column caps unlikely
- Showed service-induced cracking of column caps unlikely
RVI Program A/LAI 7: Plant-specific Evaluation of Cast Austenitic Stainless Steel
- Staff Finding
- Applicant provided sufficient information to provide reasonable assurance of functionality of the column caps through PEO because:
- Screened out TE, therefore only IE applicable, column caps thus equivalent to wrought stainless steel
- Showed pre-service and in-service flaws very unlikely
- Applicant adequately addressed A/LAI 7
- Staff agreed with deletion of Commitment 47 26
Westinghouse Lower Support Column Bodies 27
RVI Program A/LAI 8: Submittal of Information for Staff Review and Approval
- A/LAI 8
- Recommends submission of an RVI AMP and Inspection Plan +
for current LR applicants, submit FSAR supplement, TS markup and TLAAs related to RVI
- For fatigue TLAAs, A/LAI recommends these account for reactor water environmental effects
- Applicant Evaluation
- Applicant provided AMP and Inspection Plan
- Applicant committed to update RVI fatigue TLAAs to account for environmental effects as recommended by A/LAI 8
- Staff Finding
- Applicant adequately addressed A/LAI 8 because it provided the recommended information and made commitment to revise fatigue TLAAs 28
RVI Program Conclusion
- RVI AMP - Applicant has demonstrated
- Effects of aging will be adequately managed per 54.21(a)(3)
- FSAR supplement adequate per 54.21(d)
- RVI Inspection Plan implements elements of RVI AMP in an acceptable manner
- Program is consistent with the generic RVI inspection and evaluation guidelines of MRP-227-A
- Adequately addressed all of the applicable A/LAIs
- RVI Inspection Plan addresses the conditions of the final SE for MRP-227, Revision 0 29
SER Conclusion
- On the basis of its review of the LRA, the staff determines that the requirements of 10 CFR 54.29(a) have been met.
- Additional information provided by Entergy Nuclear Operations, Inc., does not alter the staffs conclusions stated in the SER 30
Staffs Ongoing Review
- Annual Update in December 2014
- Changes to plant since December 2013 that materially affect LRA
- RAI response to LR-ISG-2012-02, Aging Management of Internal Surfaces, Fire Water Systems, Atmospheric Storage Tanks, and Corrosion Under Insulation
- RAI response to LR-ISG-2013-01, Aging Management of Loss of Coating or Lining Integrity for Internal Coatings/Linings on In-Scope Piping, Piping Components, Heat Exchangers, and Tanks 31