UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 21, 2015 APPLICANT: Tennessee Valley Authority FACILITY:
Watts Bar Nuclear Plant, Unit 2
SUBJECT:
SUMMARY
OF APRIL 1, 2015, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE WATTS BAR NUCLEAR PLANT, UNIT 2 OPERATING LICENSE APPLICATION (FIRE PROTECTION REPORT)
On April 1, 2015, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Tennessee Valley Authority (TVA). The topic of discussion was the Fire Protection Report (FPR) that the staff is reviewing as part of the operating license application for Watts Bar Nuclear Plant (WBN), Unit 2. The meeting notice and agenda, dated March 20, 2015, is available in the Agencywide Documents Access and Management System at Accession No. ML15079A432. A list of attendees is provided as Enclosure 1.
The NRC staff presented no information. TVA provided a handout of a draft schedule for submittal of the updated FPR (see Enclosure 2).
TVA explained its strategy for updating the FPR to the staff. Additionally, TVA told the staff about a recent discovery at the plant that caused it to modify some of the calculations needed to complete the report. These modifications have delayed TVA's submittal of the finalized FPR.
The modifications include physical changes to the plant as well as a re-prioritization of operator actions to ensure certain plant equipment is always available in the event of a fire. The NRC staff asked clarifying questions of TVA's explanations to better understand the impacts to the FPR.
TVA then presented the NRC staff with its draft schedule for the submittal of the FPR and subsequent timeline for fuel load and receipt of the operating license pending the staff's final decision on the application. The staff informed TVA that the proposed schedule as written seemed very optimistic, based on the NRC requiring the necessary time needed to complete its safety review, as well as procedural requirements associated with licensing action reviews.
Additionally, the NRC staff informed TVA that an estimate of when the NRC staff would complete its safety review based on the new information would be beyond TVA's currently scheduled fuel load date of July 28, 2015. The NRC staff also requested TVA to evaluate whether they are able to submit a high quality document earlier to allow the NRC staff to complete its safety review more efficiently. If TVA is not able to provide the FPR by April 30, 2015, the NRC staff informed TVA that it is highly unlikely that the NRC staff would complete its safety review in time for TVA's currently scheduled fuel load date. The NRC requested that TVA continue to have weekly discussions with NRC staff on the schedule for the FPR submittal.
Additionally, the staff discussed the option to audit TVA's calculations and information associated with the FPR by way of document sharing services. TVA agreed that this approach would decrease the lag time between document submittals and could allow for more efficient and effective review of the information. The NRC staff informed TVA that they would work to formulate an audit plan. TVA staff commented that they would apply insights from the WBN, Unit 2 review to the remainder of the TVA fleet.
There were no public comments and no feedback forms were received.
Docket No. 50-391
Enclosures:
- 1. List of Attendees
- 2. WBN Fire Protection Program Recovery Project cc w/enclosures: Distribution via Listserv Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
LIST OF ATTENDEES APRIL 1, 2015, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE WATTS BAR NUCLEAR PLANT, UNIT 2 OPERATING LICENSE APPLICATION (FIRE PROTECTION REPORT)
Applicant: Tennessee Valley Authority (TVA)
Subject:
Fire Protection Report Location:
Teleconference NAME TITLE Anthony Minarik Project Manager Robert Schaaf Project Manager Jessie Quichocho Branch Chief Dan Frumkin Fire Protection Engineer Alex Klein Branch Chief Gordon Arent Licensing Manager Jim Polickoski Licensing Engineer Bill Crouch Fire Protection Engineer Jon Pangle Fire Protection Engineer Paul Ouellet Member of the Public Plant: Watts Bar Nuclear Plant. Unit 2 Date: April 1, 2015 Time: 9:00 a.m. -12:00 p.m.
ORGANIZATION NRC/NRR/DORL/LPWB NRC/NRR/DORL/LPWB NRC/NRR/DORL/LPWB NRC/NRR/DRA/AFPB NRC/NRR/DRA/AFPB TVA TVA TVA TVA EPM (TVA Support)
TENTATIVE - DRAFT ec SCHEDULE Tv:A. *vve.~.J Dual Unit,.a..s-Constructed FF~ subroisgon expected NLT 08 May2015 NRC Region II" \\:\\ie.r.. J Di.Jal Unit Fire Protection Inspection T\\.:t:..-NRCJoi nt l'vleetingfor FPR Document and Changes\\Alalkthrough supporting Staff Re*1iev*l Tv:c.. V\\lfH**J Submit Unitl EffectivenessL.C..~: vi a LC NRC I ssw~s SSER 28 NRC.l:..pproves Urnt 1 EffectJvenessLl:..R T'v:.c.. )NBN Dual Unit FPR hnplernented>vvithUnitl (procedures issued_. training complete)
Unit2 Fuel Load 04-08 rv1ay2015 18*22 rvlay 2015 13 rv1av2015 (alt27 May2015) 15 May2015 26 Jun2015 1, I I /Ole:
... tJ.... _..)
24 Jul 2015 2-:;. J I *1n1* c:
v l.J...__
- )
TENTATIVE - DRAFT would decrease the lag time between document submittals and could allow for more efficient and effective review of the information. The NRC staff informed TVA that they would work to formulate an audit plan. TVA staff commented that they would apply insights from the WBN, Unit 2 review to the remainder of the TVA fleet.
There were no public comments and no feedback forms were received.
Please direct any inquiries to me at 301-415-2048 or justin.poole@nrc.gov.
Docket No. 50-391
Enclosures:
1. List of Attendees
- 2. WBN Fire Protection Program Recovery Project
/RAJ Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/enclosures: Distribution via Listserv DISTRIBUTION:
PUBLIC LPWB Reading RidsACRS_MailCTR Resource RidsNrrDorllp_WB Resource AWilson, Rll RidsNrrPMWattsBar1 Resource RidsNrrPMWattsBar2 Resource RidsNrrLABClayton Resource RidsRgn2MailCenter Resource EKeegan, NRR SLaVie, NSIR RidsNrrDraAfpb Resource ADAMS A ccess1on N os.: M f
S ee mg ummary ML15110A405 LRonewicz, NRR MWaters, OEDO TWertz, NRR AMinarik, NRR DFrumkin, NRR RSchaaf, NRR M
f N f ML15079A432 ee mg 01ce OFFICE DORL/LPWB/PM DORL/LPWB/PM DORL/LPWB/LAiT DORL/LPWB/LA NAME AMinarik JPoole LRonewicz BClayton DATE 4/17/2015 4/22/2015 4/21/2015 4/21/2015 OFFICE DORL/LPWB/BC DORL/LPWB/PM NAME JQuichocho JPoole DATE 5/15/2015 5/21/2015 OFFICIAL RECORD COPY