MONTHYEARML15106A6812015-03-11011 March 2015 Required Response 2 for Near-Term Task Force Recommendation 2.1: Flooding - Hazard Re-Evaluation Report Project stage: Request ML15146A2932015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of Entergy Nuclear Operations, Inc.'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 - Flooding for Palisades Nuclear Plant Project stage: Other ML15356A7652015-12-23023 December 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request- Flood Causing Mechanism Reevaluation Project stage: Other 2015-03-11
[Table View] |
|
---|
Category:Letter
MONTHYEARPNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 ML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24263A1712024-09-20020 September 2024 Environmental Request for Additional Information ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) IR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations ML24206A0572024-07-25025 July 2024 PRM-50-125 - Letter to Alan Blind; Docketing of Petition for Rulemaking and Sufficiency Review Status (10 CFR Part 50) PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations PNP 2024-031, Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-07-18018 July 2024 Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000255/20240112024-07-15015 July 2024 Nuclear Plant - Restart Inspection Report 05000255/2024011 PNP 2024-027, Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2024-07-0909 July 2024 Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24183A1382024-07-0202 July 2024 Tribal Letter - Lac Du Flambeau Band of Lake Superior Chippewa Indians ML24137A0142024-07-0202 July 2024 OEDO-24-00011 - 2.206 Petition for Misuse of Palisades Decommissioning Trust Fund (EPID L-2023-CRS-0008) - Letter ML24183A1492024-07-0101 July 2024 Tribal Letter - Pokagon Band of Potawatomi Indians ML24156A0222024-07-0101 July 2024 Initiation of Scoping Process to Prepare an Environmental Assessment for the Environmental Review of Holtec Decommissioning International, Llc’S Licensing and Regulatory Requests for Reauthorization of Power Operations at Palisades EPID L-2 ML24183A1552024-07-0101 July 2024 Tribal Letter - Red Lake Band of Chippewa Indians ML24183A1542024-07-0101 July 2024 Tribal Letter Red Cliff Band of Lake Superior Chippewa Indians ML24172A0032024-07-0101 July 2024 Letter to L. Powers, Mackinac Bands of Chippewa and Ottawa Indians Re Initiation of Scoping Process for Environ Review Holtec Decommissioning Intl, LLC Request for Reauthorization of Power Ops-Palisades ML24183A1332024-07-0101 July 2024 Tribal Letter-Forest County Potawatomi Community ML24183A1582024-07-0101 July 2024 Tribal Letter Sault Ste. Marie Tribe of Chippewa Indians ML24183A1302024-07-0101 July 2024 Tribal Letter-Chippewa Cree Indians of the Rocky Boys Reservation ML24183A1282024-07-0101 July 2024 Tribal letter-Bay Mills Indian Community ML24183A1532024-07-0101 July 2024 Tribal Letter Quechan Tribe of the Fort Yuma Indian Reservation ML24183A1572024-07-0101 July 2024 Tribal Letter - Saint Croix Chippewa Indians of Wisconsin ML24183A1462024-07-0101 July 2024 Tribal letter-Mille Lacs Band of Ojibwe ML24183A1422024-07-0101 July 2024 Tribal Letter-Little Traverse Bay Bands of Odawa Indians ML24183A1312024-07-0101 July 2024 Tribal Letter-Citizen Potawatomi Nation ML24163A0552024-07-0101 July 2024 Rebecca Held Knoche NOAA-Palisades-NOI to Conduct Scoping Process and Prepare an EA - EPID No. L-2024-LNE-0003-Docket No. 50-0255 ML24163A2392024-07-0101 July 2024 Sara Thompson, Michigan DNR-Palisades-NOI to Conduct Scoping Process and Prepare an EPID No. L-2024-LNE-0003-Docket No. 50-0255 ML24155A0102024-07-0101 July 2024 Quentin L. Messer Jr., Michigan Econ-Palisades-NOI to Conduct Scoping Process and Prep an EA-EPID No. L-2024-LNE-0003 Docket No.50-0255P ML24155A0032024-07-0101 July 2024 Kathy Kowal, Us EPA Region 5-Palisades-NOI to Cibdyct Scoping Process and Prepare an EA EPID L-2024-LNE-0003 ML24163A0832024-07-0101 July 2024 Ltr to R Schumaker SHPO Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant ML24183A1342024-07-0101 July 2024 Tribal Letter-Grand Portage Band of Lake Superior Chippewa ML24183A1392024-07-0101 July 2024 Tribal Letter-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24183A1272024-07-0101 July 2024 Tribal Letter-Bad River Band of the Lake Superior Tribe of Chippewa ML24183A1412024-07-0101 July 2024 Tribal Letter-Little River Band of Ottawa Indians ML24163A1922024-07-0101 July 2024 Jeremy Rubio, Dept of Env, Great Lakes and Energy, Kalamazoo District-Palisades-NOI to Conduct Scoping Process and Prepare an EA EPID No. L-2024-LNE-0003 Docket No.50-0255 ML24183A1322024-07-0101 July 2024 Tribal Letter-Fond Du Lac Band of Lake Superior Chippewa ML24183A1592024-07-0101 July 2024 Tribal letter-Sokaogon Chippewa Community ML24163A0822024-07-0101 July 2024 Ltr to J Loichinger Achp Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant ML24183A1252024-07-0101 July 2024 Letter to G. Gould, Swan Creek Black River Confederated Ojibwa-Init of Scoping Process for the Env Rev of Holtec Decommissioning Intl, LLC Request for Reauth of Power Ops at Palisades ML24183A1352024-07-0101 July 2024 Tribal Letter-Hannahville Indian Community ML24183A1442024-07-0101 July 2024 Tribal Letter - Menominee Indian Tribe of Wisconsin ML24183A1502024-07-0101 July 2024 Tribal Letter - Prarie Band Potawatomi Nation ML24183A1452024-07-0101 July 2024 Tribal Letter - Miami Tribe of Oklahoma 2024-09-06
[Table view] |
Text
SNEntergy Entergy Nuclear Operations, Inc.Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 764 2000 Anthony J. Vitale Site Vice President PNP 2015-018 March 11,2015 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Required Response 2 for Near-Term Task Force Recommendation 2.1: Flooding -Hazard Re-Evaluation Report Palisades Nuclear Plant Docket 50-255 License No. DPR-20
REFERENCES:
1.NRC letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (Adams Accession No. ML12056A046).
- 2. Entergy Nuclear Operations, Inc. letter, PNP 2012-049, Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f)Regarding the Flooding Aspects of Recommendations 2.1 and 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated June 8, 2012 (ADAMS Accession No. ML12163A533).
Dear Sir or Madam:
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued a 50.54(f) letter to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 2 of Reference 1 contains specific requested actions, requested information, and required responses associated with Recommendation 2.1: Flooding.Pursuant to Required Response 2 of Enclosure 2 in Reference 1, Entergy Nuclear Operations, Inc. (ENO) is providing the Palisades Nuclear Plant Flooding Hazard Re-Evaluation Report in the attachment.
No interim action plan is included as discussed in Required Response 2 because there were no evaluations or actions required to address any higher flooding hazards relative to the design basis.
PNP 2015-018 Page 2 of 2 Summary of Commitments This letter contains no new or revised commitments.
This letter completes the following commitment made in Reference 2: 0 Submit flood hazard evaluation to the NRC by March 12, 2015.I declare under penalty of perjury that the foregoing is true and correct. Executed on March 11,2015.Sincerely, ajv/jse
Attachment:
Palisades Nuclear Plant Flooding Hazard Re-Evaluation Report cc: Director of Office of Nuclear Regulation Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC Attachment to PNP 2015-018 Palisades Nuclear Plant Flooding Hazard Re-Evaluation Report 143 pages follow