MONTHYEARML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML22098A0042022-04-0808 April 2022 2022 10 CFR 50.46 Annual Report ML21098A0212021-04-0808 April 2021 2021 10 CFR 50.46 Annual Report ML20099A0982020-04-0808 April 2020 R. E. Ginna Nuclear Plant - 2020 10 CFR 50.46 Annual Report ML19098A6892019-04-0808 April 2019 2019 10CFR 50.46 Annual Report ML18096A0042018-04-0606 April 2018 Submittal of 2018 10 CFR 50.46 Annual Report ML18142A6002018-02-14014 February 2018 Annual Report #12, January 1, 1976 to December 31, 1976 Inclusive ML18011A6252017-12-11011 December 2017 the 2017 Annual Report of the Ceng Independent Nuclear Advisory Committee to the Ceng Board of Directors ML17097A0942017-04-0707 April 2017 Submittal of 2017 10 CFR 50.46 Annual Report ML16145A5062016-05-12012 May 2016 Annual Radioactive Effluent Release Report and Annual Radiological Environment Operating Report ML16126A1942016-04-29029 April 2016 Report of Facility Changes, Tests and Experiments Conducted Without Prior Commission Approval and Report of Commitment Changes Performed in Accordance with NEI 99-04 ML16098A1462016-04-0707 April 2016 Submittal of 2016 10 CFR 50.46 Annual Report ML16011A0032016-01-0707 January 2016 Submittal of Annual Report of the Nuclear Advisory Committee ML15099A0082015-04-0909 April 2015 Submittal of 2015 10 CFR 50.46 Annual Report RS-15-104, Annual Property Insurance Status Report2015-04-0101 April 2015 Annual Property Insurance Status Report ML14105A0152014-04-0909 April 2014 10 CFR 50.46 Annual ECCS Report ML13094A0752013-04-0101 April 2013 CFR 50.46 Annual ECCS Report ML13037A3802012-12-17017 December 2012 Attachment 1b, 2012 Annual Report of the Ceng Independent Nuclear Advisory Committee ML12142A2972012-05-31031 May 2012 Annual Radiological Environmental Operating Report: January 1, 2011 - December 31, 2011 ML1014101042010-05-14014 May 2010 Annual Radiological Environmental Operating Report: January 1, 2009 - December 31, 2009 ML1009001532010-03-26026 March 2010 CFR 50.46 Annual Emergency Core Cooling System (ECCS) Report ML1014101022009-12-31031 December 2009 Annual Radioactive Effluent Release Report ML0831801342008-11-0707 November 2008 Submittal of Report of Facility Changes, Tests, and Experiments Conducted Without Prior Commission Approval ML0807206682008-03-0404 March 2008 10CFR50.54(w)(3) Annual Reporting of Property Damage Insurance ML0615301132006-05-26026 May 2006 Annual Financial Report ML0513001382005-05-0404 May 2005 10CFR50.46 30 Day and Annual ECCS Report ML0513805292004-12-31031 December 2004 Annual Radiological Environmental Operating Report 2023-04-10
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Text
10 CFR 50.46 April 9, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 R.E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 NRG Docket No. 50-244
Subject:
2015 10 CFR 50.46 Annual Report
Reference:
Letter from Thomas G. Morgan (Exelon) to U.S. Nuclear Regulatory Commission, "1 O CFR 50.46 Annual ECCS Report," dated April 9, 2014.
The purpose of this letter is to submit the 10 CFR 50.46 annual reporting information for R.E. Ginna Nuclear Power Plant. The referenced document is the most recent annual 10 CFR 50.46 Report report submitted to the U.S. Nuclear Regulatory Commission.
Two attachments are included with this letter that provide the current Ginna 10 CFR 50.46 status. Attachment 1 provides the Peak Cladding Temperature (PCT) "rack-up" sheets. , "Assessment Notes," contains a detailed description of each change/error reported.
There are no commitments contained in this letter. If you have any questions, please contact Ron Reynolds at 610-765-5247.
Respectfully, James Barstow Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
10 CFR 50.46 Annual Report April 9, 2015 Page 2 Attachments: 1) Peak Cladding Temperature Rack-Up Sheet for R.E. Ginna Nuclear Power Plant
- 2) Assessment Notes cc: USNRC Administrator, Region I USNRC Project Manager, Ginna USNRC Senior Resident Inspector, Ginna
ATTACHMENT 1 10 CFR 50.46 "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors" Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Peak Cladding Temperature Rack-Up Sheet for R.E. Ginna Nuclear Power Plant
Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Attachment 1 Peak Cladding Temperature Rack-Up Sheet for Ginna Page 1 of 2 PLANT NAME: Ginna ECCS EVALUATION MODEL: Small Break Loss of Coolant Accident (SBLOCA)
REPORT REVISION DATE: 4/9/2015 CURRENT OPERATING CYCLE: 38 ANAL VSIS OF RECORD Evaluation Model: NOTRUMP Calculation: Westinghouse CN-LIS-04-206, April 2005 Fuel: 422 Vantage+
Limiting Fuel Type: 422 Vantage+
Limiting Single Failure: Diesel Generator Failure to Start Limiting Break Size and Location: 2-inch Equivalent High Tavg Cold Leg Break Reference Peak Cladding Temperature (PCT) PCT= 1167.0°F MARGIN ALLOCATION A. PRIOR LOSS OF COOLANT ACCIDENT (LOCA) MODEL ASSESSMENTS 10 CFR 50.46 report dated April 30, 2007 (Note 1) ilPCT = 0°F 10 CFR 50.46 report dated February 10, 2009 (Note 3) ilPCT = 0°F 1o CFR 50.46 report dated March 4, 2011 (Note 5) LiPCT = 0°F 10 CFR 50.46 report dated March 27, 2012 (Note 6) ilPCT = 0°F 10 CFR 50.46 report dated April 1, 2013 (Note 8) ilPCT = 0°F 10 CFR 50.46 report dated April 9, 2014 (Note 9) ilPCT = 0°F NET PCT PCT =1167.0°F B. CURRENT LOCA MODEL ASSESSMENTS General Code Maintenance (Note 10) ilPCT = 0°F Fuel Rod Gap Conductance Error (Note 12) ilPCT = 0°F Radiation Heat Transfer Model Error (Note 13) GP'C1 =Uvr SBLOCTA Pre-DNB Cladding Surface Heat Transfer Coefficient ilPCT = 0°F Calculation (Note 14)
Total PCT change from current assessments I ilPCT = 0°F Cumulative PCT change from current assessments I IilPCT I= 0°F NET PCT PCT =1167.0°f
Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Attachment 1 Peak Cladding Temperature Rack-Up Sheet for Ginna Page 2 of 2 PLANT NAME: Ginna ECCS EVALUATION MODEL: Large Break Loss of Coolant Accident (LBLOCA}
REPORT REVISION DATE: 4/9/2015 CURRENT OPERATING CYCLE: 38 ANALYSIS OF RECORD Evaluation Model: ASTRUM (2004)
Calculation: Westinghouse CN-LIS-05-11, April 2005 Fuel: 422 Vantage+
Limiting Fuel Type: 422 Vantage+
Limiting Single Failure: Loss of one train of ECCS flow Limiting Break Size and Location: Cold Leg Split Break Reference PCT PCT= 1870.0°F MARGIN ALLOCATION A. PRIOR LOSS OF COOLANT ACCIDENT (LOCA) MODEL ASSESSMENTS 10 CFR 50.46 report dated April 30, 2007 (Note 1) LiPCT = 0°F 10 CFR 50.46 report dated May 4, 2008 (Note 2) LiPCT = 37°F 10 CFR 50.46 report dated February 10, 2009 (Note 3) LiPCT = 0°F 10 CFR 50.46 report dated March 26, 2010 (Note 4) LiPCT = 0°F 10 CFR 50.46 report dated March 4, 2011 (Note 5) LiPCT = 0°F 10 CFR 50.46 report dated March 27, 2012 (Note 6) T = 0°F 10 CFR 50.46 report dated August 16, 2012 (Note 7) T = 134°F 10 CFR 50.46 report dated April 1, 2013 (Note 8) T = 75°F 10 CFR 50.46 report dated April 9, 2014 (Note 9) LiPCT = 2°F NET PCT PCT =2118.0°F B. CURRENT LOCA MODEL ASSESSMENTS General Code Maintenance (Note 10) LiPCT = 0°F Errors in Decay Group Uncertainty Factors (Note 11) LiPCT = 0°F Total PCT change from current assessments I LiPCT = 0°F Cumulative PCT change from current assessments I ltiPCTI= 0°F NET PCT PCT =2118.0°F
ATTACHMENT 2 10 CFR 50.46 "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors" Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessment Notes R.E. Ginna Nuclear Power Plant
Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Attachment 2 Assessment Notes Page 1of3
- 1) Prior LOCA Model Assessment The 10 CFR 50.46 report dated April 30, 2007, reported new licensing basis peak cladding temperature (PCT) for small break loss of coolant accident (SBLOCA) and large break loss of coolant accident (LBLOCA) analyses to support fuel assembly transition from OFA to 422 Vantage+ and extended power uprate. The new licensing basis PCT reported for SBLOCA and LBLOCA are 1167°F and 1870°F, respectively.
- 2) Prior LOCA Model Assessment The 10 CFR 50.46 report dated May 4, 2008, reported an evaluation for LBLOCA related to HOTSPOT fuel relocation error which resulted in a 37°F PCT assessment.
- 3) Prior LOCA Model Assessment The 10 CFR 50.46 report dated February 10, 2009, reported evaluations for SBLOCA and LBLOCA model changes which resulted in 0°F PCT change.
- 4) Prior LOCA Model Assessment The 10 CFR 50.46 report dated March 26, 2010, reported evaluations for LBLOCA model changes which resulted in 0°F PCT change.
- 5) Prior LOCA Model Assessment The 10 CFR 50.46 report dated March 4, 2011, reported evaluations for SBLOCA and LBLOCA model changes which resulted in 0°F PCT change.
- 6) Prior LOCA Model Assessment The 10 CFR 50.46 report dated March 27, 2012, reported evaluations for SBLOCA and LBLOCA model changes which resulted in 0°F PCT change.
- 7) Prior LOCA Model Assessment The 30-day 10 CFR 50.46 report dated August 16, 2012, reported evaluations for fuel pellet thermal conductivity degradation (TCD) and peaking factor burndown, and design input change assessments which resulted in a 134°F PCT impact for LBLOCA.
- 8) Prior LOCA Model Assessment The 10 CFR 50.46 report dated April 1, 2013, reported evaluations for SBLOCA model changes which resulted in 0°F PCT impact. A LBLOCA assessment for the evaluation of an elevated initial containment and accumulator temperature was submitted in a License Amendment Request for NRG review and approval. The assessment resulted in a 75°F PCT impact. This increase in temperature was approved in an NRG Safety Evaluation Report (SER)
Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Attachment 2 Assessment Notes Page 2 of 3 (ML14232A331) dated August 21, 2014. The SER (ML14232A331) evaluated the 10 CFR 50.46 reporting criteria explicitly.
- 9) Prior LOCA Model Assessment The 10 CFR 50.46 report dated April 9, 2014, reported evaluations for SBLOCA model changes which resulted in O"F PCT impact. A LBLOCA assessment was reported related to revised heat transfer multiplier distribution which resulted in a 2°F PCT assessment.
- 10) Current LOCA Model Assessment - General Code Maintenance (LBLOCA and SBLOCA)
Various changes have been made to enhance the usability of codes and to streamline future analyses. Examples of these changes include modifying input variable definitions, units and defaults; improving the input diagnostic checks; enhancing the code output; optimizing active coding; and eliminating inactive coding. These changes resulted in an estimated PCT impact of O"F.
- 11) Current LOCA Model Assessment - Errors in Decay Group Uncertainty Factors (LBLOCA)
Errors were discovered in the calculation of decay heat in WCOBRA!TRAC. The uncertainty 238 238 239 factors for 239 Pu were applied to U, and those for U were applied to Pu. This error 239 causes an over-prediction of the uncertainty in decay power from Pu and an under-prediction of the uncertainty in decay power from 238 U. Further, the decay group uncertainty factor for Decay Group 6 of 235 U was erroneously coded as 2.5% instead of 2.25%. Evaluation of these errors resulted in an estimated PCT impact of 0°F.
- 12) Current LOCA Model Assessment - Fuel Rod Gap Conductance Error (SBLOCA)
An error was identified in the fuel rod gap conductance model in the NOTRUMP computer code.
This error is associated with the use of an incorrect temperature in the calculation of the cladding emissivity term. Evaluation of this error resulted in an estimated PCT impact of 0°F.
- 13) Current LOCA Model Assessment - Radiation Heat Transfer Model Error (SBLOCA)
Two errors were discovered in the calculation of the radiation heat transfer coefficient within the fuel rod model of the NOTRUMP computer code. First, existing logic did not preclude non-physical negative or large (negative or positive) radiation heat transfer coefficients from being calculated. These erroneous calculations occurred when the vapor temperature exceeded the cladding surface temperature or when the predicted temperature difference was less than 1°F.
Second, a temperature term incorrectly used degrees Fahrenheit instead of Rankine. The effect of these errors was estimated to be 0°F.
Annual Report of the Emergency Core Cooling System Evaluation Model Changes and Errors Assessments as of April 9, 2015 Attachment 2 Assessment Notes Page 3 of 3
- 14) Current LOCA Model Assessment- SBLOCTA Pre-DNB Cladding Surface Heat Transfer Coefficient Calculation (SBLOCA)
Two errors were discovered in the pre-departure from nucleate boiling (pre-DNB) cladding surface heat transfer coefficient calculation in the SBLOCTA code. The first error is a result of inconsistent time units (hours vs. seconds) in the parameters used for the calculation of the Reynolds and Prandtl numbers, and the second error relates to an incorrect diameter used to develop the area term in the cladding surface heat flux calculation. The correction of these errors led to an estimated PCT impact of 0°F.
[
Reference:
LTR-LIS-15-79, "R.E. Ginna 10 CFR 50.46 Annual Notification and Reporting for 2014," February 19, 2015.]