ML15096A452

From kanterella
Jump to navigation Jump to search
Comment (35) by Carol Levin on NRC-2015-0004 Re Vermont Yankee Nuclear Power Station Post-Shutdown Decommissioning Activities Report
ML15096A452
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 03/23/2015
From: Levin C
New England Coalition on Nuclear Pollution
To:
Rules, Announcements, and Directives Branch
References
80FR1975 00035, NRC-2015-0004
Download: ML15096A452 (1)


Text

Page'l of I RULE-)' .:9-,CT As of: 3/30/15 3:42 PM Received:

March 23, 2015 PUB I Status: PendingPost P B IAUS I 1:41 Tracking No. ljz-8hwO-hg49 Comments Due: March 23, 2015 Submission Type: Web Docket: NRC-2015-0004 DF(7. ..\/_D Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station Post-Shutdown Decommissioning Activities Report Comment On: NRC-2015-0004-0001 Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station Post-Shutdown Decommissioning Activities Report Document:

NRC-2015-0004-DRAFT-0036//

.Comment on FR Doc # 2015-00450 c/L" f,- / T Submitter Information Name: Carol Levin Organization:

New England Coalition on Nuclear Pollution General Comment 1. Two top Entergy officials names are mispelled in that document -Michael Twomey (not Toomey) and Jay Thayer (not Faer)2. I'd like to reiterate my two recommendations

-a. The cast storage needs be consider and prepared as if it were going to be in Vermont permanently as there is no designated place for it to be taken, and not consider it a temporary placement as it is too great a risk for the tri-state and the enviornment.

b. The decomissioning of Vermont Yankee needs to commence as soon as radiologically feasible, and not "wait for the money to grow", particularly since there are known leaks of various toxic and radiologically active materials from the grounds and buildings which need to be cleaned up now. The decomissioning fund has sufficient funds to get started, and should be used for this purpose now. Site restoration and on-site storage costs are not to come out of the decommissing fund and are to be paid separately by the company.3. The comment period needs to be extended from today (as we just received access to the transmission Friday past, and the deadline is today March 23, 2015.SUNSI Review Complete Template = ADM -013 E-RIDS= ADM-303 Add= 09.-, 0648 1f 3 03/30/2015