1 Fermi2LRANPEm Resource From:

Randall D Westmoreland [westmorelandr@dteenergy.com]

Sent:

Thursday, August 28, 2014 9:02 AM To:

Perkins, Leslie Cc:

Lynne S Goodman; Bill McDermott; Angela Rudolph

Subject:

Re: FW: Fermi 2 Environmental Audit Schedule

Leslie, O.K. I will fix the schedule and return. Thanks.

Randall Westmoreland DTE Electric Company Major Enterprise Projects Technical Expert Fermi Office: 734-586-1445 CARING ABOUT THE ENVIRONMENT IS THE NATURE OF OUR JOB.


"Perkins, Leslie" <Leslie.Perkins@nrc.gov> wrote: -----

To: "Lynne S Goodman (goodmanl@dteenergy.com)" <goodmanl@dteenergy.com>, "Randall D Westmoreland (westmorelandr@dteenergy.com)" <westmorelandr@dteenergy.com>

From: "Perkins, Leslie" <Leslie.Perkins@nrc.gov>

Date: 08/28/2014 08:41AM

Subject:

FW: Fermi 2 Environmental Audit Schedule Randy/Lynne, Kevin Folk would to participate in the REMP tour with Bill. Please see the Kevins email below.

Thanks, Leslie From: Folk, Kevin Sent: Thursday, August 28, 2014 8:38 AM To: Perkins, Leslie Cc: Rautzen, William; Wrona, David

Subject:

RE: Fermi 2 Environmental Audit Schedule Leslie:

2 Please add me to Thursdays REMP tour with Bill. Although not listed in the notes, I (we) would also like the tour to include selected REMP/groundwater protection program monitoring locations. I will be Bill Fords backup on groundwater so we wanted to lay eyes on some of those wells. Thanks.

Kevin From: Perkins, Leslie Sent: Thursday, August 28, 2014 6:47 AM To: Grange, Briana; Folk, Kevin; Klementowicz, Stephen; Rautzen, William; Logan, Dennis; Moser, Michelle; Larson, Emily; Rikhoff, Jeffrey; Martinez, Nancy; Hoffman, Robert; Chazell, Russell; Wittick, Brian

Subject:

FW: Fermi 2 Environmental Audit Schedule

All, Attached is the revised schedule for the Fermi Audit. The DTE made couple of changes to schedule. Please let me know if you have any questions or concerns that I need to pass on to the applicant. If there are no questions or concerns then the attached will be the schedule for the audit.
Thanks, Leslie From: Randall D Westmoreland [1]

Sent: Wednesday, August 27, 2014 6:16 PM To: Perkins, Leslie Cc: Lynne S Goodman; Bill McDermott; Angela Rudolph; Kim Stapleton; Rick Buckley

Subject:

Fermi 2 Environmental Audit Schedule Hi Leslie, Here is the latest and greatest schedule for the environmental audit. This includes the changes you gave to Lynne and one other item. We moved the radiation protection, radwaste, mixed waste breakout session from Thursday to Wednesday so it occurs immediately after the tour from 1100 to 1200. Please let me know when this looks final, then we will send out calendar invites to all our people. Regards.

3 Randall Westmoreland DTE Electric Company Major Enterprise Projects Technical Expert Fermi Office: 734-586-1445 CARING ABOUT THE ENVIRONMENT IS THE NATURE OF OUR JOB.

Hearing Identifier:

Fermi2_LR_NonPublic Email Number:

123 Mail Envelope Properties (OF1022727F.44899ECF-ON85257D42.00479CAB-85257D42.00479CAD)

Subject:

Re: FW: Fermi 2 Environmental Audit Schedule Sent Date:

8/28/2014 9:02:11 AM Received Date:

8/28/2014 9:02:13 AM From:

Randall D Westmoreland Created By:

westmorelandr@dteenergy.com Recipients:

"Lynne S Goodman" <goodmanl@dteenergy.com>

Tracking Status: None "Bill McDermott" <mcdermottb@dteenergy.com>

Tracking Status: None "Angela Rudolph" <rudolpha@dteenergy.com>

Tracking Status: None "Perkins, Leslie" <Leslie.Perkins@nrc.gov>

Tracking Status: None Post Office:

dteenergy.com Files Size Date & Time MESSAGE 2999 8/28/2014 9:02:13 AM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: