Shine Medical Technologies, Inc. Application for Construction Permit Submittal of the Phase I Environmental Site Assessment, Stevens Point, Wisconsin
ML15027A063
Person / Time
Site: SHINE Medical Technologies
Issue date: 01/13/2015
From: Bynum R
SHINE Medical Technologies
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML15027A047 List:
References
SMT-2015-001
Download: ML15027A063 (3)


Text

TM

  • SHINE w" Medical Technologies January 13, 2015 SMT-2015-001 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 SHINE Medical Technologies, Inc. Application for Construction Permit Submittal of the Phase I Environmental Site Assessment, Stevens Point, Wisconsin

References:

(1) SHINE Medical Technologies, Inc. letter to NRC, dated March 26, 2013, Part One of the SHINE Medical Technologies, Inc. Application for Construction Permit (ML130880226)

(2) SHINE Medical Technologies, Inc. letter to NRC, dated May 31, 2013, Part Two of the SHINE Medical Technologies, Inc. Application for Construction Permit (ML13172A361)

(3) NRC letter to SHINE Medical Technologies, Inc., dated September 11, 2013, Requests for Additional Information for the Environmental Review of the SHINE Radioisotope Production Facility Construction Permit Application (ML13231A041)

(4) SHINE Medical Technologies, Inc. letter to NRC, dated October 4, 2013, SHINE Medical Technologies, Inc. Application for Construction Permit Response to Environmental Requests for Additional Information (ML13303A887)

Pursuant to 10 CFR 50.30, SHINE Medical Technologies, Inc. (SHINE) submitted an application for a construction permit to construct a medical isotope facility to be located in Janesville, WI (References 1 and 2). The NRC staff determined additional information was required to complete the environmental review (Reference 3).

Via Alternatives Request #1, the NRC requested that SHINE provide the Phase 1 Environmental Site Assessment for the Stevens Point site (Reference 3). At the time of the SHINE response to the environmental requests for additional information (Reference 4), SHINE did not have access to the final revision of the Phase I Environmental Site Assessment for the Stevens Point site. SHINE provided the Draft Phase I Environmental Site Assessment for the Stevens Point site as Attachment 19 to Enclosure 1 of Reference (4). SHINE stated in the response that when the finalized Phase I Environmental Site Assessment for the Stevens Point site became available, it would be provided to the NRC. provides the finalized Phase I Environmental Site Assessment for the Stevens Point site. Enclosure 1 is being provided via optical storage media (OSM) as OSM#1.

The only changes made between the draft and the final versions of this document were administrative in nature.

If you have any questions, please contact Mr. Jim Costedio, Licensing Manager, at 608/210-1730.

'ý01 n 2555 Industrial Drive I Monona, WI 53713 1P (608) 210-1060 1F (608) 210-2504 1 www.shinemed.com 0 ýý

Document Control Desk Page 2 I declare under the penalty of perjury that the foregoing is true and correct.

Executed on January 13, 2015.

Very truly yours, R. Vann Bynum, Ph.D.

Chief Operating Officer SHINE Medical Technologies, Inc.

Docket No. 50-608 Enclosure cc: Administrator, Region III, USNRC Project Manager, USNRC Environmental Project Manager, USNRC Supervisor, Radioactive Materials Program, Wisconsin Division of Public Health

ENCLOSURE 1 SHINE MEDICAL TECHNOLOGIES, INC.

SHINE MEDICAL TECHNOLOGIES, INC. APPLICATION FOR CONSTRUCTION PERMIT SUBMITTAL OF THE PHASE I ENVIRONMENTAL SITE ASSESSMENT STEVENS POINT, WISCONSIN PHASE I ENVIRONMENTAL SITE ASSESSMENT STEVENS POINT, WISCONSIN REVISION 1 MAY 11, 2012 (OSM#1)