RN-15-002, Issuance of Final Significance Determination; NRC 95002 Supplemental Inspection Report 05000293/2014008, Pilgrim (EA-14-229)
ML15021A297
Person / Time
Site: Pilgrim
Issue date: 01/21/2015
From: Faria-Ocasio C, Marjorie Mclaughlin, Wray J
NRC/OE
To:
Entergy Nuclear Operations
Faria C
References
EA-14-229, RN-15-002 IR 2014008
Download: ML15021A297 (2)


See also: IR 05000293/2014008

Text

January 21, 2015

RN-15-001

OFFICE OF ENFORCEMENT

NOTIFICATION OF SIGNIFICANT REGULATORY ACTION

Licensee: Entergy Nuclear Operations, Inc. (EA-14-229)

Pilgrim Nuclear Power Station

Docket No. 05000293

Subject: ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION; NRC 95002

SUPPLEMENTAL INSPECTION REPORT 05000293/2014008

This is to inform the Commission that two White Significance Determination Process (SDP)

findings will be issued on or around January 26, 2015, to Pilgrim Nuclear Power Station as a

result of an NRC 95002 supplemental inspection at the facility. These two parallel performance

inspection findings are being opened and given the same color as the Unplanned Scrams per

7000 Critical Hours Performance Indicator (PI) (White) and Unplanned Scrams with

Complications PI (White) in accordance with Section 11.02 from Inspection Manual Chapter 0305. This guidance document requires a parallel PI inspection finding be opened and given the

same color as the PI if there are significant weaknesses in the licensees evaluation of a

performance issue associated with a PI.

The parallel inspection findings for the Unplanned Scrams per 7000 Critical Hours and

Unplanned Scrams with Complications PIs should take effect at the beginning of the quarter the

PI returned to Green. The findings will then be removed from consideration of future agency

action (per the Action Matrix) in the quarter following the successful completion of the follow-up

supplemental inspection. The findings will not be double-counted in the assessment process.

These findings do not involve violations of any NRC requirements.

The licensee has not yet been informed of the specific nature of the regulatory action.

The schedule of issuance and notification is:

Mailing of Final Significance Determination January 26, 2015

Telephone Notification of Licensee January 26, 2015

The Commonwealth of Massachusetts will be notified.

CONTACTS: Carolyn Faría, OE/EB, Marjorie McLaughlin, R1

(301) 415-4050 (610) 337-5240

Distribution: RN-15-002, January 21, 2015

OWFN OWFN TWFN Regional Offices

Chairman Burns EDO OCFO RI RII

Comm. Svinicki DEDR OIS RIII RIV

Comm. Ostendorff DEDMRS RES

Comm. Baran OE ACRS

SECY OGC NRO MAIL

OCA NRR OE Staff

OPA OI 3WFN

OIP OIG NMSS

NSIR

OPS CENTER

DISTRIBUTION:

NHilton, OE OE R/F EN binder

ADAMS Accession Number: ML15021A297

OFFICE OE/EB: ES OE/EB: BC

NAME CFaria JWray (Acting)

DATE 1/21/2015 1/ 21/2015

OFFICIAL RECORD COPY