Termination of Reactor Oversight Process for Vermont Yankee Nuclear Power Station and Commencement of Decommissioning Inspection Program
ML15020A482
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 01/20/2015
From: Marc Ferdas
Division of Nuclear Materials Safety I
To: Wamser C
Entergy Nuclear Operations
References
Download: ML15020A482 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 January 20, 2015 Mr. Christopher Wamser Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station P.O. Box 250 Vernon, VT 05354

SUBJECT:

TERMINATION OF REACTOR OVERSIGHT PROCESS FOR VERMONT YANKEE NUCLEAR POWER STATION AND COMMENCEMENT OF DECOMMISSIONING INSPECTION PROGRAM

Dear Mr. Wamser:

This letter is to inform you that oversight activities by the U.S. Nuclear Regulatory Commission (NRC) at the Vermont Yankee Nuclear Power Station (Vermont Yankee) will no longer be performed in accordance with our operating power reactor inspection program. The NRCs oversight of your future activities at Vermont Yankee will be conducted in accordance with our decommissioning power reactor inspection program and will be led by our Region I Division of Nuclear Materials Safety (DNMS).

On September 23, 2013, Entergy Nuclear Operations, Inc. (Entergy) notified the NRC of their intent to permanently shut down Vermont Yankee (ADAMS Accession Number: ML13273A204).

On January 12, 2015, Entergy certified cessation of power operations and the permanent removal of fuel from the Vermont Yankee reactor vessel (ADAMS Accession Number:

ML15013A426). The NRC will no longer use Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, IMC 0608, Performance Indicator Program, and IMC 2515, Light-Water Reactor Inspection Program when conducting oversight activities and assessing site performance. Therefore, it is also no longer necessary to report Reactor Oversight Process performance indicator data for Vermont Yankee. The results of inspection activities completed under IMC 2515 will be provided in future correspondence. Although the inspection program for NRC oversight at your facility has changed, all license commitments remain in effect until altered by formal action from the NRC.

The NRCs oversight of your licensed activities as you progress through decommissioning will be conducted under the provisions in IMC 2561, Decommissioning Power Reactor Inspection Program. The objectives of the decommissioning inspection program are to verify that decommissioning activities are being conducted safely, that spent fuel is safely being stored, and that site operations and license termination activities are in conformance with applicable regulatory requirements, licensee commitments, and management controls.

As defined in IMC 2561, Vermont Yankee is currently in the "Post-Operation Transition Phase" of decommissioning and the inspections as detailed in IMC 2561, Appendix A, Core Inspection Procedures for that phase will be conducted at Vermont Yankee. In addition, the

C. Wamser 2 inspection procedures listed in IMC 2561, Appendix B, Discretionary Procedures for Decommissioning Power Reactors could be performed based on site activities and conditions.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5022 or Steve Hammann, Senior Health Physicist, at (610) 337-5399, with any questions you may have regarding this letter.

Sincerely,

/RA/

Marc S. Ferdas, Chief Decommissioning & Technical Support Branch Division of Nuclear Materials Safety Docket No. 50-271 License No. DPR-28 cc: Distribution via ListServ

C. Wamser 2 inspection procedures listed in IMC 2561, Appendix B, Discretionary Procedures for Decommissioning Power Reactors could be performed based on site activities and conditions.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5022 or Steve Hammann, Senior Health Physicist, at (610) 337-5399, with any questions you may have regarding this letter.

Sincerely,

/RA/

Marc S. Ferdas, Chief Decommissioning Branch Division of Nuclear Materials Safety Docket No. 50-271 License No. DPR-28 cc: Distribution via ListServ Distribution: (via E-mail)

D. Dorman, RA J. DeBoer, DRP OEMail D. Lew, DRA S. Rutenkroger, DRP, SRI RIDSNRRDIRS H. Nieh, DRP B. Watson, FSME PUBLIC M. Scott, DRP J. Hickman, FSME RidsNrrPMVermontYankee R. Lorson, DRS S. Rich, DRP, RI Resource J. Trapp, DRS A. Rancourt, DRP, OA RidsNrrDorlLpI1-1 Resource R. McKinley, DRP K. Morgan-Butler, RI OEDO ROPreports Resource S. Shaffer, DRP J. Kim, NRR DOCUMENT NAME: G:\WordDocs\Current\Misc Letter\VY transition letter.docx ML15020A482 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DNMS Ri/DRP RI/DNMS NAME SRich/sr via email SHammann/sth RMcKinley/rm MFerdas/msf DATE 01/14 /15 01/14/15 01/20/15 01/20/15 OFFICIAL RECORD COPY