L-14-421, Request to Change Cyber Security Implementation Plan Milestone 8 Completion Date

From kanterella
(Redirected from ML15009A265)
Jump to navigation Jump to search

Request to Change Cyber Security Implementation Plan Milestone 8 Completion Date
ML15009A265
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/09/2015
From: Harkness E
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML15009A264 List:
References
L-14-421
Download: ML15009A265 (6)


Text

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION WITHHOLD IN ACCORDANCE WITH 10 CFR 2.390 Pe,y Nuc/ear^P/a.

10 Center Road P.O.Box 97 FirstEnergy Nuclear Operating Company Perry,.Ohio 44081 January 9,2015 .:,- .10 CFR 50.90 L-14-421 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Perry Nuclear Power Plant, Unit No. 1 Docket No. 50-440, License No. NPF-58 Reguest to Change Cyber Security Implementation Plan Milestone 8 Completion Date In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Section 50.90, "Application for amendment of license, construction permit, or early site permit," FirstEnergy Nuclear Operating Company (FENOC) hereby requests amendment of Operating License NPF-58 for the Perry Nuclear Power Plant, Unit No. 1 (PNPP).

An evaluation of the proposed amendment is enclosed. FENOC is requesting Nuclear

-Regulatory Commission (NRC) staff approval by June 1, 2015 with an implementation period of 30 days following issuance of the amendment.

FENOC requests that the enclosure, which contains security-related information, be withheld from public disclosure in accordance with 10 CFR 2.390.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager-Fleet Licensing at (330) 315-6810.

I declare under penalty of perjury that the foregoing is true and correct. Executed on January Q 2015.

Sincerely, Ernest J. Harkness

Enclosure:

Evaluation of Proposed Request for Licensing Action The enclosure to this letter contains security-related information.

Withhold from public disclosure under 10 CFR 2.390.

Upon removal of the enclosure, this letter is uncontrolled.

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

Perry Nuclear Power Plant, Unit No. 1 L-14-421 Page 2 cc: NRC Region III Administrator Nuclear Reactor Regulation Project Manager NRC Resident Inspector Executive Director, Ohio Emergency Management Agency, State of Ohio (NRC Liaison) (w/o enclosure)

ATTACHMENT 2 Proposed Facility Operating License Change (Mark-up)

(1 Page Follows)

D. FENOC is exempted from: 1) the requirements of Section III.D.2(b)(li), containment airlock testing requirements, Appendix J to 10 CFR Part 50, due to the special circumstance described in Section 6,2.6 of SER Supplement No. 7 authorized by 10 CFR 50.12(a)(2)(iii) and 2) the requirements of Section IV.F., Full Participation Exercise, of Appendix E to 10 CFR Part 50, due to the special circumstance described in the Exemption dated November 6,1986. These exemptions are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security. The exemptions are hereby granted pursuant to 10 CFR 50.12. With the granting of these exemptions, the facility will operate, to the extent authorized herein, In conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.

E. FENOC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans, including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55

{61 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).

The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Perry Nuclear Power Plant Physical Security Plan" Revision 2, submitted by letter dated May 18, 2006.

FENOC shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The FENOC CSP was approved by License Amendment No. 158.

F. Deleted [Insert: , and amended by License Amendment No. xxx l G. The licensees shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1964, as amended, to cover public liability claims.

Amendment No. 158

ATTACHMENT 3 Proposed Facility Operating License Change (Re-typed)

(1 Page Follows)

D. FENOC is exempted from: 1) the requirements of Section III.D.2(b)(ii), containment airlock testing requirements, Appendix J to 10 CFR Part 50, due to the special circumstance described in Section 6.2.6 of SER Supplement No. 7 authorized by 10 CFR 50.12(a)(2)(iii) and 2) the requirements of Section IV.F., Full Participation Exercise, of Appendix E to 10 CFR Part 50, due to the special circumstance described in the Exemption dated November 6,1986. These exemptions are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security. The exemptions are hereby granted pursuant to 10 CFR 50.12. With the granting of these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.

E. FENOC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans, including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (61 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).

The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Perry Nuclear Power Plant Physical Security Plan" Revision 2, submitted by.letter dated May 18, 2006.

FENOC shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The FENOC CSP was approved by License Amendment No. 158, and amended by License Amendment No. .

F. Deleted G. The licensees shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1964, as amended, to cover public liability claims.