Category:Deficiency Correspondence (per 10CFR50.55e and Part 21)
MONTHYEARML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML16174A3952016-06-21021 June 2016 Fisher Information Notice, (FIN) 2016-05 - Insufficient Valve Cage Hardfacing ML16127A5952016-05-0404 May 2016 Rotork Controls Inc. Part 21 Notification Concerning V12 (Pt No. N69-921) and K5 (N69-838 & N69-926) Safety Related Micro Switches ML14335A2952014-11-13013 November 2014 Interim 10 CFR Part 21 Report Regarding Submodules CA20-03 and CA20-07A Nonconformances for V. C. Summer Unit 2, AP1000 Project ML14255A0172014-08-27027 August 2014 Interim 10 CFR Part 21 Report Regarding Submodule and Embedment Deviations for V. C. Summer Unit 2 AP1000 Project ML14090A4332014-03-27027 March 2014 Interim Report- 10CFR 21 Evaluation Regarding Potential Deficiencies in Justification of Use of Prorate Spring in PV-62 ML14090A4322014-03-27027 March 2014 Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Seismic Qualifications for PV-62 ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML0701704602007-01-0808 January 2007 10CFR21 for FMEA and Pre-installation Setup of Woodward Digital Reference Unit (Dru); Fairbanks Morse Engine Reporting Id# 06-05 ML0602502602006-01-12012 January 2006 Attachment to 10CFR21 for Woodward Dru Fm Id# 06-01 2017-03-20
[Table view] Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping ML23087A1292023-03-23023 March 2023 Trillium Valves USA - Part 21 Written Notification - Event Number: 56420 ML23082A1122023-03-17017 March 2023 10 CFR Part 21 Report Inconsistent Crimping of Motor Leads to Ring Terminal Connectors and Failure to Comply. Trillium Valves USA Part 21 Evaluation I211003 ML22089A2442022-03-30030 March 2022 10 CFR 21 Report- Feedwater Isolation Valve Poppet Seal Failure ML21187A1242021-06-28028 June 2021 10CFR Part 21 Update - Deviation Identified in the Bolting Utilized to Maintain Seismic Qualification ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML16349A5902016-12-0202 December 2016 Interim 10 CFR Part 21 Report Regarding a Piping Spool Weld Nonconformance for AP1000 Project ML16174A3952016-06-21021 June 2016 Fisher Information Notice, (FIN) 2016-05 - Insufficient Valve Cage Hardfacing ML16188A3772016-06-21021 June 2016 Part 21 - Insufficient Valve Cage Hardfacing ML16127A5952016-05-0404 May 2016 Rotork Controls Inc. Part 21 Notification Concerning V12 (Pt No. N69-921) and K5 (N69-838 & N69-926) Safety Related Micro Switches ML15103A4852015-04-0707 April 2015 Itt Engineered Valves - 2nd Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M I Diaphragms, Customer Testing ML14335A2952014-11-13013 November 2014 Interim 10 CFR Part 21 Report Regarding Submodules CA20-03 and CA20-07A Nonconformances for V. C. Summer Unit 2, AP1000 Project ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14261A1502014-09-17017 September 2014 Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M1 Diaphragms, Customer Testing ML14255A0172014-08-27027 August 2014 Interim 10 CFR Part 21 Report Regarding Submodule and Embedment Deviations for V. C. Summer Unit 2 AP1000 Project ML14113A3982014-04-17017 April 2014 Part 21 - Bearing Defect ML14090A4312014-03-27027 March 2014 Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Testing of PV-62 ML14090A4322014-03-27027 March 2014 Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Seismic Qualifications for PV-62 ML14099A5062014-03-27027 March 2014 Interim Report- 10CFR 21 Evaluation Regarding Potential Deficiencies in Testing of PV-62 ML14090A4332014-03-27027 March 2014 Interim Report- 10CFR 21 Evaluation Regarding Potential Deficiencies in Justification of Use of Prorate Spring in PV-62 ML14079A3532014-03-17017 March 2014 Notification of Part 21 Re Bearing Defect ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12075A1062012-03-14014 March 2012 Notification of Potential Part 21 Re Defect on Arvan Electrical Terminal Blocks ML12058A1412012-02-23023 February 2012 Part 21 Report - Rosemount Nuclear Instruments, Inc., Pressure Transmitter with Nonzero Based Calibrations ML11186A9042011-06-30030 June 2011 Notification of Potential Part 21 Appendix R Analyses Fails to Recognize Hot-Short Failure Resulting in the Loss of an Essential Electrical Bus ML11182A9172011-06-29029 June 2011 Part 21 Notification, Appendix R Analyses Fails to Recognize Hot-Short Failure Resulting in the Loss of an Essential Electrical Bus ML1017204862010-06-16016 June 2010 Part 21 Notification - Tyco Electronic Relay Recall ML0831900172008-11-12012 November 2008 Notification of Potential Part 21 on All Dimensionally Verified Commercial Grade Items Processed Per Fisher Manufacture Procedure Fmp 2K28 ML0823901062008-08-25025 August 2008 Notification of Potential Part 21 on Failure of F and G Switches ML0819902102008-07-15015 July 2008 USNRC 10CFR Part 21 Notification ML0710002292007-04-0606 April 2007 Rosemount Nuclear Instruments, Inc., Submittal of Notification Under 10 CFR Part 21 for Certain Model 1152 Pressure Transmitters ML0713703092007-03-0707 March 2007 Velan, Inc., Piston Check Cv Information ML0332401342003-11-18018 November 2003 Part 21 Notification (Initial Report) Re Potential Exists for Incorrect Solder Used on the Internal High Voltage & Signal Solder Connections in Model 877-1 High Range Containment Monitor Detectors ML0301601692002-11-20020 November 2002 Power Shield Tap Block Solder Joints 10CFR Part 21 Report 2024-01-18
[Table view] Category:Letter
MONTHYEARML24038A0322024-02-0707 February 2024 (Vcsns), Unit 1, 10 CFR 21 Report - Emergency Diesel Generator Flash Contactor Relay IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 ML24022A1582024-01-22022 January 2024 (Vcsns), Unit 1 - Reply to a Notice of Violation: EA-23-093 ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) ML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 ML23361A1042023-12-21021 December 2023 Inservice Testing Program for Pumps and Valves Fifth Interval Update and Associated Relief and Alternative Requests IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 ML23354A1802023-12-20020 December 2023 301 Examination Report with Cover Letter ML23347A0492023-12-12012 December 2023 Technical Specification Bases Changes Updated Through November 2023 ML23334A2462023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2372023-11-30030 November 2023 (Vvsns), Unit 1 - Annual Commitment Change Summary Report ML23332A1942023-11-28028 November 2023 (Vcsns), Unit 1, Correction of Typographical Error in License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23317A2242023-11-0909 November 2023 (Vcsns), Unit 1 - License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23289A1172023-11-0303 November 2023 Tribal Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1152023-11-0303 November 2023 Ltr to R. Nelson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1162023-11-0303 November 2023 Ltr to W. Emerson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 ML23284A1792023-10-16016 October 2023 Subsequent License Renewal Application Online Reference Portal ML23275A0142023-10-11011 October 2023 SLRA - Acceptance and Opportunity for Hearing - Letter ML23284A1662023-10-10010 October 2023 (Vcsns), Unit 1 - Request for Regulatory Conference; (EA-23-093) IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 ML23250A3112023-09-20020 September 2023 Request to Revise Reactor Vessel Material Surveillance Capsule Withdrawal Schedules ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations ML23235A0432023-09-0505 September 2023 Receipt and Availability of the Subsequent License Renewal Application IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 ML23242A1192023-08-29029 August 2023 (Vcsns), Unit 1 - Inservice Inspection (ISI) Owner'S Activity Report (OAR) for Refueling Outage 27 ML23243B0362023-08-25025 August 2023 Request for FEMA Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23233A1752023-08-17017 August 2023 Application for Subsequent Renewed Operating License IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23190A0012023-07-0909 July 2023 Special Report 2023-003 Inoperable Radiation Monitoring Instrumentation Channel ML23187A5092023-07-0606 July 2023 Request for Federal Emergency Management Agency Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23173A1052023-06-22022 June 2023 Special Report 2023-002 Inoperable Loose-Part Monitoring System Channel ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23159A2332023-06-0808 June 2023 License Amendment Request - Emergency Response Organization Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes ML23156A3092023-06-0505 June 2023 Requalification Program Inspection Virgil C. Summer Nuclear Station Unit 1 - 05000395/2023003 2024-02-07
[Table view] |
Text
a' CB&I 128 South Tryon Street Charlotte, NC 28202 Tel: +1 704 343 7500 www.CBI.com 10 CFR 21.21 November 13, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
INTERIM 10 CFR PART 21 REPORT REGARDING SUBMODULES CA20-03 AND CA20-07A NONCONFORMANCES FOR V.C. SUMMER UNIT 2 AP1000 PROJECT The attachment to this letter provides an interim report in accordance with 10 CFR 21.21 pertaining to submodules CA20-03 and CA20-07A supplied by CB&I Lake Charles for the V.C. Summer Unit 2 AP1000 nuclear project. Based on information in a quality assurance inspection report, some welds were found on these submodules to have some lack of fusion.
Evaluation of reportability in accordance with 10 CFR Part 21 was not able to be completed within the 60-day evaluation period due to the recent discovery that the initial reportability review of these conditions incorrectly determined that no additional evaluation was required.
This condition was discovered during review of a corrective action report regarding these conditions. It is currently expected that the evaluation of this condition will be completed by January 8, 2015.
If you have any questions pertaining to this information, please contact Curtis Castell, Licensing Manager, at 980-321-8314.
Sincerely, Don DePierro Senior Vice President, Nuclear cc: Regional Administrator, USNRC, Region II Attachment
-4*
Attachment to Letter Dated November 13, 2014 Page 1 of 2 INTERIM 10 CFR PART 21 REPORT REGARDING SUBMODULES CA20-03 AND CA20-07A NONCONFORMANCES FOR V.C. SUMMER UNIT 2 AP1000 PROJECT This report is being provided as an interim report in accordance with 10 CFR 21.21.
(i) Name and address of the individual or individuals informing the Commission.
Mr. Don DePierro CB&I Nuclear 128 S. Tryon St., Suite 1000 Charlotte, NC 28202 (ii) Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect.
No basic components have been determined to fail to comply or contain a defect. This is an interim report. CB&I Lake Charles is supplying basic components associated with modular construction for the V.C. Summer Unit 2 AP1000 nuclear project. Based on information in a quality assurance inspection report, some welds on these submodules were found to have some lack of fusion.
(iii) Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.
No basic components have been determined to fail to comply or contain a defect. This is an interim report. The nonconformances pertain to submodule fabrication that was performed by CB&I Lake Charles, 3191 West Lincoln Rd., Lake Charles, LA 70605.
(iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
No basic components have been determined to fail to comply or contain a defect. This is an interim report. Evaluation of the condition is expected to be completed by January 8, 2015.
(v) The date on which the information of such defect or failure to comply was obtained.
The discovery date of the deviations that require evaluation is October 12, 2013, based on the date of the inspection report that originally discovered the deviations. Evaluation of reportability in accordance with 10 CFR Part 21 was not completed within the 60 day evaluation period due to the recent discovery that the initial reportability review of these conditions incorrectly determined that no additional evaluation was required. This condition was discovered during review of a corrective action report regarding these conditions. It is currently expected that the evaluation of this condition will be completed by January 8, 2015.
(vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
Attachment to Letter Dated November 13, 2014 Page 2 of 2 No basic components have been determined to fail to comply or contain a defect. This is an interim report.
(vii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
No basic components have been determined to fail to comply or contain a defect. This is an interim report.
(viii) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
None at this time.
(ix) In the case of an early site permit, the entities to whom an early site permit was transferred.
Not applicable.