AttEn tenro Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 November 12, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
REFERENCE:
Submittal of Non-Proprietary Version of Holtec International Report HI-2104715 Revision 7 "Seismic Analysis of the Loaded HI-TRAC in the SFP and SFP Slab Qualification" Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No. 50-293 License No. DPR-35
- 1. Entergy Letter to NRC, Entergy Response to NRC Request for Additional Information (RAI) Regarding the Heavy Loads License Amendment Request (TAC NO. MF3237), dated October 3, 2014 (2.14.069)
LETTER NO: 2.14.077
Dear Sir or Madam:
The Attachment 1 to this letter provides a non-proprietary version of Holtec International Report HI-2104715 Revision 7 "Seismic Analysis of the Loaded HI-TRAC in the SFP and SFP Slab Qualification". A proprietary version of this Holtec International report had been previously submitted as Attachment 11 in Reference 1.
This letter does not contain any new regulatory commitments.
If you have any questions regarding the subject matter, please contact Everett P. Perkins at (508) 830-8323.
Sincerely,
&xv" Everett P. Perkins, Jr.
Manager, Regulatory Assurance EPP/mew
Attachment:
- 1. Non-Proprietary Version of Holtec International Report HI-2104715 Revision 7 "Seismic Analysis of the Loaded HI-TRAC in the SFP and SFP Slab Qualification"
Entergy Letter No. 2.14.077 Page 2 of 2 cc:
Ms. Nadiyah Morgan, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North O-8F4 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 NRC Resident Inspector Pilgrim Nuclear Power Station John Giarrusso, Jr.
Planning and Preparedness Section Chief Mass Emergency Management Agency (MEMA) 400 Worcester Road Framingham, MA 01702 John Priest, Director, Massachusetts Department of Public Health (MDPH)
Radiation Control Program Commonwealth of Massachusetts 529 Main Street, Suite 1M2A Charlestown, MA 02129-1121
ATTACHMENT 1 to Entergy Letter No. 2.14.077 Non-Proprietary Version of Holtec International Report HI-2104715 Revision 7 "Seismic Analysis of the Loaded HI-TRAC in the SFP and SFP Slab Qualification" (101 Pages)