MONTHYEARML24292A1832024-10-30030 October 2024 Summary of Meeting with Tennessee Valley Authority, October 16, 2024, to Discuss Proposed License Amendment Regarding Implementation of an Online Monitoring Methodology ML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement ML20351A4212021-01-19019 January 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar, Unit 2, Steam Generator Replacement ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20351A2192021-01-11011 January 2021 Summary of Conference Calls Regarding the Fall 2020 Steam Generator Tube Inspections ML20337A0402020-12-15015 December 2020 Summary of November 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification 5.9.9, Steam Generator Tube Inspection Report ML20323A0662020-11-27027 November 2020 Summary of October 28, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification Surveillance Requirement 3.6.15.4, Shield Building ML20244A1892020-09-11011 September 2020 Summary of Teleconference Call with Tennessee Valley Authority Regarding a Proposed Change to the Containment Leakage Rate Testing Program ML20233A8352020-08-25025 August 2020 Summary of August 11, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20213C7112020-08-25025 August 2020 Summary of July 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned Alternative Request for Watts Bar Nuclear Plant, Unit 1 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20211L8222020-08-10010 August 2020 Summary of Teleconference Call with the Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20150A4162020-06-24024 June 2020 Summary of May 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20153A3622020-06-22022 June 2020 Summary of May 27, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20135H2702020-05-28028 May 2020 Summary of May 5, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20143A1692020-05-28028 May 2020 Summary of May 14, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2 ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20034F5232020-02-12012 February 2020 Summary of Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 2024-09-23
[Table view] |
Text
U.S. Nuclear Regulatory Commission Public Meeting Summary October 24, 2014
Title:
Public Meeting Watts Bar Nuclear Unit 2 Construction Project Meeting Identifier: ML14260A495 Date of Meeting: Wednesday, October 1, 2014 Location: Comfort Inn, Athens, TN Type of Meeting: Category 3 Purpose of the Meeting(s):
To discuss the status of the Watts Bar Unit 2 Construction Project, including major milestones, the status of NRC licensing and inspection activities, and potential challenges that may impact the project schedule.
General Details:
The NRC conducted an open house beginning at 4:30 p.m. eastern daylight time (EDT) where members of the public met informally with NRC staff and asked questions related to the Watts Bar Nuclear Unit 2 construction project. A category 1 meeting was scheduled from 5:00 - 5:30 p.m. Fifteen NRC staff members were present. The meeting began with an introduction of NRC staff and a review of meeting ground rules by William Jones, Director, Division of Construction Projects, Region II. This was followed by a presentation on the Watts Bar Unit 2 completion status by the Tennessee Valley Authority (TVA). Following the Category 1 meeting, at 5:45 p.m. the NRC began the Category 3 meeting. The NRC gave a presentation focused on the status of NRC licensing and inspection activities. The remaining portion of the meeting was dedicated to answering questions on these activities and on the status of Watts Bar Nuclear Unit 2, as well as receiving comments from members of the public. The meeting ended at approximately 6:45 p.m.
Approximately 50 people participated in the meeting, both in-person and remotely using a teleconference line and webinar. Four participants asked questions and provided comments. In addition to members of the public, meeting participants included representatives of the Tennessee Emergency Management Agency, Southern Alliance for Clean Energy, the Union of Concerned Scientists, the Tennessee Environmental Council, the nuclear industry, public advocacy groups, and TVA.
Summary of Presentations:
TVA provided a presentation to the NRC during the Category 1 portion of the meeting.
TVAs presentation covered the following areas:
- project completion status
2
- special topics (Hydrology, Fukushima, Safety Culture, Outreach)
The NRC presented to the public for the Category 3 meeting. The NRC discussed the overall license review process, highlighting recent accomplishments and remaining licensing activities. The NRC discussed the inspection program which is unique to Watts Bar Unit 2 and gave the current status of inspection activities. The NRC gave an update on the upcoming major milestones for the project related to licensing and inspection activities.
Public Participation Themes:
During the public question and answer session of the meeting, NRC staff received questions on the following topics. The following answers were either provided during the meeting or the questions were researched and the answers provided below:
- Hydrology o A member of the public inquired about the current status of open licensing items regarding hydrology.
o The NRC has received TVAs hydrology submittal and is in the process of its review.
o The NRC staff has engaged TVA on these issues and is expecting a response by the end of October, which will be made publically available.
- The use of the term complete when discussing the construction project o A member of the public questioned the meaning of the term complete as it was used in the presentation regarding auxiliary feedwater system alignment.
o The NRC staff explained that when used in the context of this meeting, complete means either (1) NRC staff has completed a technical review and published a safety evaluation report; or (2) the inspection regarding the item has been completed and an inspection report has been issued.
- Drawing updates o A member of the public referenced problems in the past involving a large backlog of drawing updates. It was asked if this issue is currently being addressed by the NRC.
o NRC inspectors conduct as-built inspections, where inspectors review completed design packages and walk-down as-built systems to verify the as-built matches the design. Because this inspection involves the review of updated drawings, NRC has assessed the adequacy of drawing updates.
- Fukushima response order requirements o A member of the public asked how the Fukushima Response Order (EA 049) regulatory requirements apply to the licensing of Watts Bar Unit 2.
3 o The NRC explained that the Orders for Spent Fuel Pool instrumentation and Mitigating Strategies must be addressed prior to receiving an operating license. An inspection of TVAs compliance with the orders is planned.
- TVAs proposed fuel load date o A member of the public inquired about what the impact of TVAs proposed fuel load date of May 14, 2015 is on major milestones.
o The NRC explained that some dates will be affecting since the milestones dates presented by the NRC during the meeting were based on an April fuel load date. The NRC still needs to complete the safety review and inspection of construction, testing, and operational readiness. The dates for the Advisory Committee on Reactor Safeguards meetings are not expected to change.
- Decommissioning funding o A member of the public inquired about the decommissioning process and expressed a concern over how decommissioning will be funded for two reactors at Watts Bar.
o The funding mechanism for decommissioning is explained on the NRC public website: http://www.nrc.gov/waste/decommissioning/faq.html#20
- Safety culture o A member of the public asked how TVA is addressing safety culture and the handling of whistle blowers.
o TVA responded by stating that a strong nuclear safety culture is a basic tenet and that retaliation is not tolerated. The NRC staff noted that the NRC takes an independent review of safety culture and is engaged through inspections and the allegation process.
- Anonymous concerns o A member of the public asked how the NRC handles anonymous concerns that are entered into TVAs corrective action program.
o The NRC routinely reviews problem evaluation reports and regularly communicates with the employee concerns program staff. The staff reviews the information available and looks for trends if applicable. NRC inspectors do not attempt to seek out individuals who submit anonymous concerns within TVAs corrective action program.
- Seismic regulations o The public inquired about the consideration of updated seismic regulations and how they apply to the licensing of Unit 2.
o The NRC noted that Unit 2 is being built to the same standard as Unit 1, a safe shutdown earthquake of 0.18g ground motion acceleration. As part of the agencys response to Fukushima events, the NRC issued a 50.54(f) letter related to updated seismic hazards. The NRC will review TVAs response to that letter to identify any issues.
- Insurance liability o A member of the public noted a concern about the adequacy of insurance liability and the amount expected to be covered by the Price-Anderson Act.
4 o Details regarding the Price-Anderson Act and background on nuclear insurance and disaster relief can be found on the NRC public website at:
http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/nuclear-insurance.html
- Concrete o An individual commented on the statement made by TVA during the presentation that the plant is being made like new. The individual disagreed with the statement, and noted that for concrete poured in the 1970s, it is not possible to make like new. The individual stated that a response to the comment was not required.
Action Items/Next Steps:
- The next public meeting to discuss Watts Bar Nuclear Unit 2 Construction Project will take place at NRC headquarters in Rockville, MD in January 2015.
- An additional public meeting near Watts Bar will be held with NRC senior management approximately three months before a decision on an operating license is made.
Enclosures:
- 1. Meeting agenda - ML14260A495
- 2. NRC staff presentation - ML14297A281
- 3. TVA presentation - ML14297A246
_ML14300A338_____ _____ SUNSI REVIEW COMPLETE OFFICE RII:DCP RII:DCP RII:DCP RII:DCP RII:DCP RII:DCP RII:DCI SIGNATURE AAW RCH NAME A. Wilson R. Haag DATE 10/24/2014 10/24/2014 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO