Request for Additional Information, Relief Request 3ISI-14 - Use of Code Case N-702 for Nozzle-Vessel Weld and Inner Radius Exams for the Third 10-Year Inservice Inspection Interval
ML14206A009
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/31/2014
From: Lyon C
Plant Licensing Branch IV
To: Reddemann M
Energy Northwest
Lyon C
References
TAC MF3435
Download: ML14206A009 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 31, 2014 Mr. Mark E. Reddemann Chief Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT:

COLUMBIA GENERATING STATION- REQUEST FOR ADDITIONAL INFORMATION RELATED TO INSERVICE INSPECTION PROGRAM REQUEST 31SI-14 (TAC NO. MF3435)

Dear Mr. Reddemann:

By application dated February 6, 2014, to the U.S. Nuclear Regulatory Commission (NRC)

(Agencywide Documents Access and Management System (ADAMS) Accession No. ML14042A160), Energy Northwest, the licensee, submitted request 31SI-14 to use an alternative to certain inspection requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Subarticle IWB-2500 for Columbia Generating Station.

The NRC staff has reviewed the information provided in your application and determined that additional information is required in order to complete its review. The enclosed questions were provided to Ms. L. Williams of your staff on July 24, 2014. Please provide a response to the questions within 30 days of the date of this letter.

If circumstances result in the need to revise the requested response date, please contact me at (301) 415-2296 or by e-mail at fred.lyon@nrc.gov.

Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397

Enclosure:

Request for Additional Information cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION RELIEF REQUEST 31SI-14 ENERGY NORTHWEST COLUMBIA GENERATING STATION DOCKET NO. 50-397 By application dated February 6, 2014, to the U.S. Nuclear Regulatory Commission (NRC)

(Agencywide Documents Access and Management System (ADAMS) Accession No. ML14042A160), Energy Northwest, the licensee, submitted request 31SI-14 to use an alternative to certain inspection requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Subarticle IWB-2500 for Columbia Generating Station (CGS).

Based on its review, the NRC staff requests the following additional information to complete its safety evaluation of the application.

EVIB-RAI-1 Relief Request 31SI-14 applying the ASME Code Case N-702, "Alternative Requirements for Boiling Water Reactor (BWR) Nozzle Inner Radius and Nozzle-to-Shell Welds," for the CGS third 10-year inservice inspection (lSI) interval does not mention the examination method for the nozzle radii. The NRC has approved use of ASME Code Case N-702, except for the VT-1 visual examination specified in the code case, for all past similar relief requests.

Therefore, please modify your request specifying your examination methodology to be either ultrasonic (UT) examination or VT-1 in accordance with the conditions placed upon the use of Code Case N-648-1, "Alternative Requirements for Inner Radius Examinations of Class 1 Reactor Vessel Nozzles," as specified in the most recent edition of Regulatory Guide (RG) 1.147, "lnservice Inspection Code Case Acceptability, ASME Section XI, Division 1,"or provide additional information as to why your request should not be modified.

Please note that the condition placed by RG 1.147, Revision 16 (ADAMS Accession No. ML101800536), on the use of Code Case N-648-1 is to be revised, and a different condition is proposed in RG 1.147, Revision 17 for Code Case N-648-1, which is expected to be issued near the end of this year.

Enclosure

ML14206A009 *email OFFICE NRR/DORULPL4-1 /PM NRR!DORULPL4-1/LA NRRIDE/EVIB/BC* NRR!DORULPL4-1 /BC(A) NRRIDORULPL4-1 /PM NAME FLyon JBurkhardt SRosenberg EOesterle FLyon DATE 7/28/14 7/25/14 7/22/14 7/31/14 7/31/14