1. IAANO. PAGE OF INTERAGENCY AGREEMENT NRC-HQ-20-14-T-0017 1

2. ORDER NO. 3. REQUISITION NO. 4. SOLICITATION NO.

NRR-14-0169

5. EFFECTIVE DATE 6- AWARD DATE 7. PERIOD OF PERFORMANCE 06/04/2014 06/04/2014 06/16/2014 TO 03/15/2016
8. SERVICING AGENCY 9. DEIVER TO PACIFIC NORTHWEST NAT LAB BERNARD GRENIER ALC: 11555 ROCKVILLE PIKE DUNS: +4: MAILSTOP OWFN 13 F15 US DEPARTMENT OF ENERGY ROCKVILLE MD 20852 PACIFIC NORTHWEST SITE OFFICE PO BOX 350 MS K9-42 RICHLAND WA 99352 POC Genice Madera TELEPHONENO. 509-372-4010
10. REQUESTING AGENCY 11. INVOICEOFFICE ACQUISITION MANAGEMENT DIVISION US NUCLEAR REGULATORY COMMISSION ALC: 3100001 DUNS: 040535809 +4: ONE WHITE FLINT NORTH US NUCLEAR REGULATORY COMMISSION 11555 ROCKVILLE PIKE ONE WHITE FLINT NORTH MAILSTOP 03-E17A 11555 ROCKVILLE PIKE NRCIPACRESOURCENRCGOV ROCKVILLE MD 20852-2738 ROCKVILLE MD 20852-2738 POC MORIE GUNTER-HENDERSON TELEPHONENO. 301 287-0893
12. ISSUING OFFICE 13. LEGISLATVE AUTHORITY US NRC - HQ Energy Reorganization Act of 1974 ACQUISITION MANAGEMENT DIVISION MAIL STOP 3WFN-05-C64MP WASHINGTON DC 20555-0001 14. PROJECT ID
15. PROJECT TITLE SEE BLOCK 18 BELOW
16. ACCOUNTING DATA 2014-X0200-FEEBASED-20-20D007-11-4-149-1034-253D
17. 18. 19. 20. 21. 22.

ITEM NO. SUPPLIESISERV1CES QUANTITY UNIT UNIT PRICE AMOUNT TASK ORDER NUMBER: NRC-HQ-20-14-T-0017 TASK ORDERING AGREEMENT  : NRC-HQ-20-14-D-0014 AGREEMENT/TASK ORDER: NRC-HQ-20-14-D-0014 -

NRC-HQ-20-14-T-0017 The NRC and the DOE Lab (PNNL) hereby enter intc this Agreement/Task Order, NRC-HQ-20-14-D-0014 NRC-HQ-20-14-T-0017, for the project entitled:

Review of License Amendment Request for the Prairie Nuclear Generating Plant, Units 1 and 2, Transition to National Fire Protection Continued ...

23. PAYMENT PROVISIONS 24. TOTALAMOUNT

$30,000.00 25a. SIGNATURE OF GOVERNMENT REPRESENTATIVE (SERVICING) 263. S(ATURE OF GOVERWENTiEPRESENTATIE/EQUESTING) 25b. NAMEANDTITLE 25C. DATE 261.CONTRACTING OFFI . DATE IMORIE E. GUNTER-HENDERSON 119 / /L ThMPLTF DM 00 SUNSI REVIEW COMPLETE ju)L... ,2O4 410152

IA OORDER NO ____ ______[PAGE OF NRC-HQ)-20-14-T-0017 112 3 Association Standard 805 (NFPA 805),

Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2011 Edition in the Areas Related to Nuclear Power Plant Fire Protection and Fire Protection Engineering, Nuclear Power Plant Safe Shutdown Analysis and Circuit Analysis and Fire Probabilistic Risk Assessment.

The performance period for this agreement shall commence on June 16,. 2014 and will expire on March 15, 2016.

Consideration and Obligations:

(a) Authorized Cost Ceiling $455,041.00 (b) The amount presently obligated with respect to this DOE Agreement is $30,000.00. When and if the amount(s) paid and payable to the DOE Laboratory hereunder shall equal the obligated amount, the DOE Laboratory shall not be obligated to continue performance of the work unless and until the NRC Contracting Officer shall increase the amount obligated with respect to this DOE Agreement. Any work undertaken by the DOE Laboratory in excess of the obligated amount specified above is done so at the DOE Laboratory's sole risk.

The following documents are hereby made part of this Agreement:

(1) Statement of Work (Attachment No. 1)

(2) PNNLs proposal dated May 21, 2014 is incorporated by reference This agreement is entered into pursuant to the authority of the Energy Reorganization Act of 1974, as amended (42 U.S.C 5801 et seq.). This work will be performed in accordance with the NRC/DOE Memorandum of Understanding dated November 24, 1998. To the best of our knowledge, the work requested will not place the DOE and its contractor in direct competition with the domestic private sector.

X I Fee Recoverable Work Non-fee Recoverable Work The total amount of award: $455,041.00. The Continued ...

4 & 1

IAANO ORDER NO PAGE OF NRC-HQ-20-14-T-0017 o 1 3 3 jobligation for this award is shown in box 24.1