2014-05-Draft Outline Comments
ML14184B321
Person / Time
Site: Fort Calhoun 
Issue date: 05/22/2014
From: Vincent Gaddy
Operations Branch IV
To:
Omaha Public Power District
laura hurley
References
Download: ML14184B321 (2)


Text

Attachment 6 OBDI 202 - IOLE Process Rev 1 DRAFT OUTLINE COMMENTS Facility: FCS First Exam Date: May 19, 2014 Written Exam Outline Comment Resolution 1

Many of the KAs rejected were inappropriate - will discuss with the exam author.

Following the discussion many of the original KAs were restored.

2 3

4 5

Administrative JPM Outline Comment Resolution 1 No Comments.

2 3

4 5

Control Room / In-Plant System JPM Outline (Date)

Comment Resolution 1 No Comments.

2 3

4 5

Simulator Scenario Outline Comments (Date)

Comment Resolution 1

Change Event 6 to a Major Transient (M)

Change Event 8 to a Component failure (C)

Add a normal event (swap pumps, fans, etc.) to the beginning of the scenario These comments were addressed during the on-site validation.

OBDI 202 - IOLE Process Rev 1 2

Add a normal event at the beginning of the scenario There are no I/C failures for the BOPO prior to the major transient Delete one ATCO and/or add two BOPO I/C events prior to the major transient Combine Event 3 and 4 into one event.

3 Delete Event 2 Only one TS event identified -

there needs to be 2 4

Add event numbers to outline Add normal event to beginning of outline There is only one BOPO I/C event prior to the major transient

- add one.

5