ML14181B120

From kanterella
Jump to navigation Jump to search
Letter from David R. Vasbinder Building Release Surveys Performed at the University at Buffalos Buffalo Materials Research Center to Prepare the Building for Demolition
ML14181B120
Person / Time
Site: University of Buffalo
Issue date: 06/25/2014
From: Vasbinder D
University of Buffalo
To:
Document Control Desk, NRC/FSME
References
Download: ML14181B120 (1)


Text

Unfmrut at suffS.

The State University of New York Environment, Health & Safety Services June 25, 2014 Docket 50-57 License R-77 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 -0001

Dear Sir or Madam:

This submission is in follow up to previous submissions, dated June 5"h and May 22nd, 2014, detailing supplemental information and data to address comments provided by ORISE and the N.R.C. regarding building release surveys performed at the University at Buffalo's Buffalo Materials Research Center to prepare the building for demolition.

During conference calls, some issues were discussed that required further clarification.

Attached is a letter and data from the University's Decommissioning Management Contractor, Enercon to Mr. Dave Vasbinder detailing supplemental information addressing those issues that were identified.

We have also provided courtesy copies of this information to our Project Manager, Ted Smith and Region I Inspector, Steve Hammann as well as to ORISE.

If you have any questions or wish further information, please contact me at (716) 829-3301 or dvasbind@buffalo.edu.

David R. Vasbinder Director, Buffalo Materials Research Center Cc:

Ted Smith, U.S.N.R.C. Project Manager 4

Steve Hammann, NRC Region 1 Nick Altic, ORISE C-- ~2, C