NRR E-mail Capture - Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Proposed Changes Cyber Security Plan Milestone 8
ML14140A297
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 05/19/2014
From: Wang A
Division of Operating Reactor Licensing
To: Seiter J
Entergy Nuclear Operations
References
MF3325
Download: ML14140A297 (2)


Text

NRR-PMDAPEm Resource From: Wang, Alan Sent: Monday, May 19, 2014 10:51 AM To: SEITER, JEFFERY ALAN Cc: Burkhardt, Janet

Subject:

Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Proposed Changes Cyber Security Plan Milestone 8 (TAC No. MF3325)

Jeff, by letter dated December 19, 2013 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML140064A081), Entergy Operations, Inc. (the licensee) submitted a license amendment request (LAR) to revise the Grand Gulf Nuclear Station, Unit No. 1 (GGNS) Cyber Security Plan Implementation Schedule. Specifically, this LAR proposed a change to the GGNS Cyber Security Plan Milestone 8 implementation date. The US Nuclear Regulatory Commission (NRC) staff has reviewed the Entergy submittal dated December 19, 2013, regarding changes to the Milestone 8 implementation date and has determined that the following additional information is required to complete its review of the amendment request:

1) The LAR provides details about the impact of the additional time requested on the effectiveness of the overall cyber security program in the context of milestones already completed. However, the information provided does not include information about Milestone 5 Implement observation and identification of obvious cyber related tampering to existing insider mitigation rounds by incorporating the appropriate elements. Milestone 5 was scheduled for completion no later than December 31, 2012. Provide details about the impact of the additional time requested on the effectiveness of the overall cyber security program in the context of Milestone 5.

This request was discussed with Mr. Jeffery Seiter of your staff on May 19, 2014, and it was agreed that a response would be provided within 30 days from the issuance of this email. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1445 or via e-mail at Alan.Wang@nrc.gov.

Alan B. Wang Project Manager (Grand Gulf Nuclear Station)

Nuclear Regulatory Commission Division of Operating Reactor Licensing 1

Hearing Identifier: NRR_PMDA Email Number: 1287 Mail Envelope Properties (Alan.Wang@nrc.gov20140519105100)

Subject:

Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Proposed Changes Cyber Security Plan Milestone 8 (TAC No. MF3325)

Sent Date: 5/19/2014 10:51:06 AM Received Date: 5/19/2014 10:51:00 AM From: Wang, Alan Created By: Alan.Wang@nrc.gov Recipients:

"Burkhardt, Janet" <Janet.Burkhardt@nrc.gov>

Tracking Status: None "SEITER, JEFFERY ALAN" <jseiter@entergy.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1909 5/19/2014 10:51:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: