ML14107A450

From kanterella
Jump to navigation Jump to search
NRC Staff Monthly Status Report, in the Matter of Tennessee Valley Authority (Sequoyah Nuclear Plant, Units 1 and 2)
ML14107A450
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 04/17/2014
From: Matt Young
NRC/OGC
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-327-LR, 50-328-LR, ASLBP 13-927-01-LR-BD01, RAS 25828
Download: ML14107A450 (2)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-327-LR & 50-328-LR

)

(Sequoyah Nuclear Plant, Units 1 and 2) )

)

NRC STAFF MONTHLY STATUS REPORT In accordance with the Atomic Safety and Licensing Boards Initial Scheduling Order, dated August 26, 2013, the staff of the Nuclear Regulatory Commission (Staff) is filing this monthly status report on its best estimate of the dates for issuance of the Draft Supplemental Environmental Impact Statement (DSEIS), Final Supplemental Environmental Impact Statement (FSEIS), Safety Evaluation Report (SER) with open items, and the final SER. In the Revised Monthly Status Report that it filed on March 4, 2014, the Staff reported that it expects to publish the SER with open items in January 2015, the final SER in May 2015, the DSEIS in July 2014, and the FSEIS in March 2015. There have been no changes to these date estimates. In accordance with the Boards Initial Scheduling Order, the Staff will apprise the Board of any change to the estimated publication dates.

Respectfully submitted,

/Signed (electronically) by/

Mitzi A. Young Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15-D21 Washington, DC 20555-0001 Telephone: (301) 415-3830 E-mail: Mitzi.Young@nrc.gov Dated at Rockville, Maryland this 17th day of April, 2014

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-327-LR & 50-328-LR

)

(Sequoyah Nuclear Plant, Units 1 and 2) )

)

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305, I hereby certify that copies of the foregoing NRC STAFF MONTHLY STATUS REPORT, dated April 17, 2014, have been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above-captioned proceeding, this 17th day of April, 2014.

/Signed (electronically) by/

Mitzi A. Young Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15-D21 Washington, DC 20555-0001 Telephone: (301) 415-3830 E-mail: Mitzi.Young@nrc.gov