Submittal of Integrated Initial License Training Examination Materials Byron Letter 2014-0045
ML14104A183
Person / Time
Site: Byron  Constellation icon.png
Issue date: 04/14/2014
From: Kearney F
Exelon Generation Co
To: Pederson C
Document Control Desk, NRC/RGN-III
References
1.10.0101, 2014-0045
Download: ML14104A183 (2)


Text

- Byron Generating Station 4450 North German Church Rcad Exelon Generation.

April 14, 2014 LTR: BYRON 2014-0045 File: 1.10.0101 Cynthia D. Pederson Regional Administrator Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and SIN 50-455

Subject:

Submittal of Integrated Initial License Training Examination Materials

Dear Ms. Pederson:

Enclosed are the examination materials Byron Station is submitting in support of the initial license exam scheduled June 2-13, 2014 at Byron Station.

This submittal includes the Senior Reactor Operator and Reactor Operator Written Examinations, Job Performance Measures and Integrated Plant Operation Scenario guides.

These examination materials have been developed in accordance with NUREG-1 021, Revision 9, Supplement 1, Operator Licensing Examination Standards. Please note that reference materials are attached to each individual examination question or item.

Some minor modifications have been made to the Integrated Examination Outline in order to improve balance and content. A list of outline changes and justifications is included. These changes improve examination quality and are in compliance with NUREG-1 021, Revision 9, Supplement 1, Operator Licensing Examination Standards.

Some modifications or adjustments to the examination material may be required due to procedural changes.

In accordance with NUREG-1 021, Revision 9, Supplement 1, Section E-201, please ensure these materials are withheld from public disclosure until after the examinations are complete.

Should you have any questions concerning this letter, please contact Mr. Steven A. Gackstetter, Regulatory Assurance Manager, at (815) 406-2800. For questions concerning examination materials, pleasecontact Mr. Robert F. Peterson, Senior Ops Training Instructor, at (815) 406-3209.

Respecifu Ily, WA/LI Faer A. KearrTy Site Vice President Byron Station FAK/R FP/LZ/sg Enclosures cc: Raymond K. Walton, Chief Examiner, NRC Region Ill, w/enclosures Chief Operations Branch NRC, w/o enclosures NRC Senior Resident Inspector, Byron Station, w/o enclosures Letter enclosure distribution as follows:

Cynthia D. Pederson, without enclosures Enclosures listed below will be hand delivered to Raymond K. Walton, Chief Examiner, NRC Region Ill:

  • RO / SRO Composite Examination with references attached