Lr Hearing - Draft Telecon Summary for Call on February 20, 2014
ML14077A384
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 03/18/2014
From:
Office of Nuclear Reactor Regulation
To:
Division of License Renewal
References
Download: ML14077A384 (8)


Text

IPRenewal NPEmails From: Green, Kimberly Sent: Tuesday, March 18, 2014 11:29 AM To: Waters, Roger M. (rwater1@entergy.com)

Cc: Uribe, Juan; IPRenewal NPEmails

Subject:

Draft Telecon Summary for Call on February 20, 2014 Attachments: Telecon Summary 02-20-14 DRAI on ISGs.docx

Roger, Attached is the draft telecon summary for the call that was held on February 20, 2014. Please let me know if any changes or corrections are needed to the summary.

Ive copied Juan Uribe on this email. If Im out of the office, he will be able to answer your questions.

Thanks, Kim 1

Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 4502 Mail Envelope Properties (F5A4366DF596BF458646C9D433EA37D701682075C23D)

Subject:

Draft Telecon Summary for Call on February 20, 2014 Sent Date: 3/18/2014 11:29:29 AM Received Date: 3/18/2014 11:29:39 AM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients:

"Uribe, Juan" <Juan.Uribe@nrc.gov>

Tracking Status: None "IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>

Tracking Status: None "Waters, Roger M. (rwater1@entergy.com)" <rwater1@entergy.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 322 3/18/2014 11:29:39 AM Telecon Summary 02-20-14 DRAI on ISGs.docx 35536 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Indian Point Nuclear Generating Unit Nos. 2 and 3

SUBJECT:

SUMMARY

OF CONFERENCE CALL HELD ON FEBRUARY 20, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING A DRAFT REQUEST FOR ADDITIONAL INFORMATION ON LR-ISG-2012-02 AND DRAFT LR-ISG-2013-01 Representatives of the U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc., (Entergy or the applicant) held a conference call on February 20, 2014, to discuss a draft request for additional information (RAI) on LR-ISG-2012-02 and Draft LR-ISG-2013-01. A list of the participants is enclosed.

By email dated February 2, 2014, the staff sent a draft RAI to Entergy regarding the recently issued interim staff guidance (ISG) document on management of aging effects on internal surfaces of piping, and the recently issued draft ISG document on management of aging effects for internal coatings. In both ISG documents, the staff recommends that initial inspections of certain piping and coatings be conducted within five years and ten years, respectively, prior to entering the period of extended operation. Indian Point Nuclear Generating Unit 2 (IP2) is already operating in the period of extended operation, and Indian Point Nuclear Generating Unit 3 (IP3) will enter the period of extended operation at midnight on December 12, 2015.

Therefore, Entergy wanted clarification on when the initial inspections must be conducted, and whether conduct of the recommended inspections would be a condition of receiving a renewed license.

The staff stated that it understands the issue of timing for the IP units, and that an exception to the timing for the conduct of the initial inspections could be requested. The staff would review the exception and make a determination regarding the timing of the planned initial inspections.

The applicant had an opportunity to comment on this summary.

Kimberly J. Green, Sr. Mechanical Engineer Aging Management of Plant Systems Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286

Enclosure:

List of Participants

cc w/encl: Listserv LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Indian Point Nuclear Generating Unit Nos. 2 and 3

SUBJECT:

SUMMARY

OF CONFERENCE CALL HELD ON FEBRUARY 20, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING A DRAFT REQUEST FOR ADDITIONAL INFORMATION ON LR-ISG-2012-02 AND DRAFT LR-ISG-2013-01 Representatives of the U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc., (Entergy or the applicant) held a conference call on February 20, 2014, to discuss a draft request for additional information (RAI) on LR-ISG-2012-02 and Draft LR-ISG-2013-01. A list of the participants is enclosed.

By email dated February 2, 2014, the staff sent a draft RAI to Entergy regarding the recently issued interim staff guidance (ISG) document on management of aging effects on internal surfaces of piping, and the recently issued draft ISG document on management of aging effects for internal coatings. In both ISG documents, the staff recommends that initial inspections of certain piping and coatings be conducted within five years and ten years, respectively, prior to entering the period of extended operation. Indian Point Nuclear Generating Unit 2 (IP2) is already operating in the period of extended operation, and Indian Point Nuclear Generating Unit 3 (IP3) will enter the period of extended operation at midnight on December 12, 2015.

Therefore, Entergy wanted clarification on when the initial inspections must be conducted, and whether conduct of the recommended inspections would be a condition of receiving a renewed license.

The staff stated that it understands the issue of timing for the IP units, and that an exception to the timing for the conduct of the initial inspections could be requested. The staff would review the exception and make a determination regarding the timing of the planned initial inspections.

The applicant had an opportunity to comment on this summary.

Kimberly J. Green, Sr. Mechanical Engineer Aging Management of Plant Systems Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286

Enclosure:

List of Participants cc w/encl: Listserv DISTRIBUTION:

See next page

  • concurrence via e-mail OFFICE LA: DLR/RPB1* PM: DLR/RAPB BC: RPB1:DLR LA: DLR/RPB1 PM: DLR/RAPB NAME KGreen YDiaz KGreen DATE

SUBJECT:

SUMMARY

OF CONFERENCE CALL HELD ON FEBRUARY 20, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING A DRAFT REQUEST FOR ADDITIONAL INFORMATION ON LR-ISG-2012-02 AND DRAFT LR-ISG-2013-01 DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource YDiaz ABurritt, RI KGreen DonaldJackson, RI WHolston GMeyer, RI DPickett MModes, RI STurk, OGC NSheehan, RI OPA BMizuno, OGC DScrenci, RI OPA DRoth, OGC DTifft, RI BHarris, OGC NMcNamara, RI SBurnell, OPA GNewman, RI DMcIntyre, OPA JSStewart, RI EDacus, OCA AmiPatel, RI

TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS FEBRUAR 20, 2014 PARTICIPANTS: AFFILIATIONS:

Kim Green U.S. Nuclear Regulatory Commission (NRC)

William Holston NRC Roger Waters Entergy Nuclear Operations, Inc. (Entergy)

Charlie Caputo Entergy John Curry Entergy Dave Lach Entergy Sal Zulla Entergy Tom Orlando Entergy Peter Guglielmino Entergy Alan Cox Entergy Andy Taylor Entergy ENCLOSURE